Today, according to sources, Boeing may have made a contractual delivery of Air India's first 787. ZA236 (LN 35, VT-ANH) was seen at the Boeing Charleston Delivery Center today and a source did say that the aircraft may be delivering today (contractually). The contractual delivery date is the date that the paperwork is signed and the final delivery payment is made to Boeing by the customer. When asked if this was the case, Boeing spokesperson, Candy Eslinger, replied: "The Air India delivery team is in South Carolina for the delivery scheduled next week." This is confirmation that Boeing will be delivering at least one if not two 787s to Air India this month. I have heard that ZA236 would deliver on Aug. 27 (ceremonial delivery perhaps) and fly away that afternoon/evening for New Delhi. For now there isn't any confirmation about the contractual delivery being made though I suspect that this event may have taken place today (Aug. 24th). In addition to ZA236 being delivered this month, a source has told me that the following deliveries may take place during the next week. Please take this information with a grain of salt as we have seen that some may not materialize due to different circumstances.
ZA536 (LN 68, CC-BBA) to LAN on Aug. 27
ZA461 (LN 58, A7-BCB) to Qatar Airways on Aug. 30
ZA118 (LN 67, JA813A) to ANA on Aug. 30
ZA182 (LN 70, JA828J) to Japan Airlines on Aug. 30 (this airplane has had only one test flight)
ZA233 (LN 29, VT-AND) to Air India on Aug. 31
Additionally ZA237 (LN 46, VT-ANI) is almost ready for delivery but doesn't have a delivery date as of yet. It appears that Air India is trying to pick up one delivery ready 787 each week so it could be that ZA237 could deliver in September. There are two other 787s for Air India both built at Charleston that have yet to take their B-1 flights so I anticipate that those deliveries may happen in late September but more likely in October.
There is also further information on September deliveries which, once again, should be taken with a grain of salt.
ZA119 (LN 69, JA814A) to ANA on Sept. 12
ZA263 (LN 71, ET-AOR) to Ethiopian on Sept. 18 (hasn't taken its B-1 yet)
ZA288 (LN 53, N20904) to United on Sept. 18
ZA178 (LN 27, JA824J) to Japan Airlines on Sept. 20 (hasn't taken its B-1 yet)
ZA463 (LN 64, A7-BCL) to Qatar Airways on Sept. 25 (hasn't taken its B-1 yet)
ZA135 (LN 66, JA815A) to ANA on Sept. 25 (hasn't taken its B-1 yet)
ZA382 (LN 43, B-2727) to China Southern on Sept. 27 (hasn't taken its B-1 yet)
All told the total number of deliveries in August and September may total 16, IF this scheduled is kept.
Showing posts with label ZA536. Show all posts
Showing posts with label ZA536. Show all posts
Friday, August 24, 2012
Saturday, August 11, 2012
Updated 787 delivery information
Activity around Everett has increased in recent days as far as the 787 is concerned. ZA100 (LN 7, JA803A) continues pre-delivery test flight, ZA262 (LN 49, ET-AOQ) performed a customer test flight and ZA118 (LN 67, JA813A) conducted its B-1 flight). Even though August is almost one half over a posting on airliners.net says that there will be 7 Dreamliner deliveries made this month not including deliveries to Air India. The delivery train starts this Monday (August 14th) with first delivery to Ethiopian of ZA262. Less than a week later ZA100 will deliver to ANA on the 20th.Qatar Airways is scheduled to be the 4th carrier to take the 787 (ZA461) around August 22nd followed by LAN (ZA536) on August 27th. ANA takes one on August 28th (ZA119). Both JAL (ZA182) and ANA (ZA118) take one each on August 30th. Again this schedule is subject to change and many of these deliveries can move to a later date. If this schedule holds then it would be the most 787s delivered by Boeing in one month and will add 3 new airlines flying the 787.
It is possible that Air India could be added this month but they are having a very hard time arranging financing to pay for the jets that are ready for delivery and is reflective of their financial distress. It is unknown if Boeing will penalize them for not taking delivery in a timely manner but Air India has been aware that these airplanes are ready for delivery but chose not to pursue financing until after they got approval to take delivery from the GoI. This reinforces the view of many that this is a very poorly managed airline. The Air India -787 saga continues, unfortunately.
September is also promising to be just as good as August was in terms of '87 deliveries with United and China Southern both taking their first airplanes. All September deliveries are tentatively scheduled for the second half of September and kcks off with Ethiopian taking delivery of ZA264 (LN 71, ET-AOR) on Sept. 18th as well as United (ZA288, LN 53, N20904) also signing for its first 787 on the same day. Two days later Japan Airlines will take its 6th 787 which is an early build Dreamliner, ZA178 (LN 27, JA824J). ANA takes a 787 which is the first 787 to be rolled out without needing to go to the EMC. ZA135 (LN 66, JA815A) should deliver around September 25th. Qatar Airways will take its second 787, ZA463 (LN 64, A7-BCD) on September 27 but also delivering on that date will be the first '87 for China Southern. This airplane is ZA382 (LN 43, B-2727).
All together this is 13 787s that is scheduled to be delivered over the next 6 weeks and will take Boeing to 25 787 delivered in 2012 not including tentative deliveries to Air India if and when that happens. By the end of September, if all goes according that what I laid out in this post, then there will be 7 customers flying the 787 by the end of the third quarter possibly 8 with Air India.
It is possible that Air India could be added this month but they are having a very hard time arranging financing to pay for the jets that are ready for delivery and is reflective of their financial distress. It is unknown if Boeing will penalize them for not taking delivery in a timely manner but Air India has been aware that these airplanes are ready for delivery but chose not to pursue financing until after they got approval to take delivery from the GoI. This reinforces the view of many that this is a very poorly managed airline. The Air India -787 saga continues, unfortunately.
September is also promising to be just as good as August was in terms of '87 deliveries with United and China Southern both taking their first airplanes. All September deliveries are tentatively scheduled for the second half of September and kcks off with Ethiopian taking delivery of ZA264 (LN 71, ET-AOR) on Sept. 18th as well as United (ZA288, LN 53, N20904) also signing for its first 787 on the same day. Two days later Japan Airlines will take its 6th 787 which is an early build Dreamliner, ZA178 (LN 27, JA824J). ANA takes a 787 which is the first 787 to be rolled out without needing to go to the EMC. ZA135 (LN 66, JA815A) should deliver around September 25th. Qatar Airways will take its second 787, ZA463 (LN 64, A7-BCD) on September 27 but also delivering on that date will be the first '87 for China Southern. This airplane is ZA382 (LN 43, B-2727).
All together this is 13 787s that is scheduled to be delivered over the next 6 weeks and will take Boeing to 25 787 delivered in 2012 not including tentative deliveries to Air India if and when that happens. By the end of September, if all goes according that what I laid out in this post, then there will be 7 customers flying the 787 by the end of the third quarter possibly 8 with Air India.
Monday, August 6, 2012
Air India, Ethiopian moving towards first 787 deliveries
Despite Friday's announcement that Air India has now been cleared to accept 787 deliveries from Boeng, it looks more likely that the first non-Japanese carrier to take ownership of a 787 will be Ethiopian. In a press release, Ethiopian says that they will take delivery of their first 787 on August 14th and fly away on August 15th to Washington Dulles. Air India is still trying to decide when to take formal ownership of the three 787s that are currently ready for delivery at Boeing Charleston. The delivery is clouded by the failure of the GEnx engine in late July though the carrier is still taking delivery. Neither the FAA or the NTSB as ordered a grounding of GEnx equipped aircraft and deliveries are continuing and are going to continue unless a significant issue is discovered by the parties investigating the incident. Because of this Air India is obligated to take delivery of the airplanes or they can face storage fees and other costs. The GEnx issue will nto be an impediment to delivery at this point unless there is something seriously wrong with the engine. Air India still has to communicate to Boeing when they plan on taking the aircraft and rumors say that it could be as early as the end of this week. I'm counting on a low key delivery ceremony given the tortuous path to delivery to Air India. In the Wall Street Journal article, Jon Ostrower says that the three aircraft would be delivered one at a time spaced by 7 to 10 days which means that the three deliveries would take about a month to complete due to the need to send the Air India personnel back to Charleston to pick up each aircraft.
In the meantime, LAN's frst airplane, ZA536 (LN 68, CC-BBA) has taken its first flight today and is moving towards a late August to early September delivery to the airline. I do anticipate further first flights of the 787s that are in preflight including a gaggle of 787s for ANA and JAL that are on the flightline.
Here's the text of Ethiopian's Press Release:
In the meantime, LAN's frst airplane, ZA536 (LN 68, CC-BBA) has taken its first flight today and is moving towards a late August to early September delivery to the airline. I do anticipate further first flights of the 787s that are in preflight including a gaggle of 787s for ANA and JAL that are on the flightline.
Here's the text of Ethiopian's Press Release:
Ethiopian Airlines to Receive its first Boeing 787 on August 14
Press Release
Addis Ababa, Ethiopia: Ethiopian Airlines, the fastest growing airline in Africa, is pleased to announce that it will take delivery of its first Boeing 787 Dreamliner on August 14, 2012, in Seattle, Washington.
Ethiopian is proud to be the first airline from Africa, Europe, Americas and Middle East to take delivery of the Dreamliner, and to be able to offer its passengers the ultimate travel experience on-board this game changing aircraft before other carriers. “The fact that we are the first airline outside Japan to receive this ultra modern aircraft is an affirmation of our continuing pioneering role in African aviation. It is also a testimony of our commitment to give our passengers the best possible travel experience, with the best industry products and services.,” said Tewolde Gebremariam, CEO of Ethiopian.
After taking delivery, Ethiopian will fly its Dreamliner to Washington D.C. the next day, where the aircraft will be on display. During the exhibition, Ethiopian Dreamliner is expected to be visited by US Senators and House Representatives as well as Ambassadors, Executives from the World Bank and IMF, members of the Ethiopian community, the media and other invited guests.
Ethiopian Dreamliner, the first to be received by a non-Japanese carrier, will make its historic trip to Africa and will touchdown at Bole Addis Ababa International Airport on August 16, 2012. The airline will hold celebrations in Addis Ababa for the arrival of the aircraft and will soon announce its first Dream destinations.
Friday, July 27, 2012
First 787 B-1 flight in almost 3 weeks scheduled to be conducted today
The first 787 B-1 flight to be conducted in almost three weeks is scheduled to take place today at about 10AM PT (1PM ET) today. ZA100 (LN 7, JA803A) will fly its first flight. This aircraft is the first production airplane to be assembled though it is also the aircraft that needed the most modifications. It has been in Everett for over three years since it started final assembly. If goes according to plan, this aircraft should deliver to ANA by middle to late August depending on any issues that would need to be corrected. The flight is on Flightaware.
According to a posting on the airliners.net forum, Boeing is planning to deliver some where around 7 '87s in August as follows:
ZA100 (LN 7, JA803A) to ANA - 2nd to 3rd week of August
ZA461 (LN 58, A7-BCB) to Qatar - 4th week of August
ZA262 (LN 49, ET-AOQ) to Ethiopian - 4th week of August
ZA118 (LN 67, JA813A) to ANA - last week of August
ZA536 (LN 68, CC-BBA) to LAN - last week of August
ZA119 (LN 69, JA814A) to ANA - last week of August
ZA182 (LN 70, JA828J) to JAL - last week of August
Notable is the absence of ZA135 (LN 66, JA815A) which was the first 787 that did not need to go to the EMC. This airplane probably needs a little bit more time to finish off the 300 some assembly tasks that remained after being pulled out of the assembly line. This list has the potential of adding 3 maybe 4 more 787s if the Indian Government finally approves the compensation deal between Air India and Boeing. That is the potential of 10 to 11 deliveries next month and would take Boeing to almost to the 2/3 point of the total 787 deliveries that they have projected for 2012 (35 to 42 with 12 currently delivered).
According to a posting on the airliners.net forum, Boeing is planning to deliver some where around 7 '87s in August as follows:
ZA100 (LN 7, JA803A) to ANA - 2nd to 3rd week of August
ZA461 (LN 58, A7-BCB) to Qatar - 4th week of August
ZA262 (LN 49, ET-AOQ) to Ethiopian - 4th week of August
ZA118 (LN 67, JA813A) to ANA - last week of August
ZA536 (LN 68, CC-BBA) to LAN - last week of August
ZA119 (LN 69, JA814A) to ANA - last week of August
ZA182 (LN 70, JA828J) to JAL - last week of August
Notable is the absence of ZA135 (LN 66, JA815A) which was the first 787 that did not need to go to the EMC. This airplane probably needs a little bit more time to finish off the 300 some assembly tasks that remained after being pulled out of the assembly line. This list has the potential of adding 3 maybe 4 more 787s if the Indian Government finally approves the compensation deal between Air India and Boeing. That is the potential of 10 to 11 deliveries next month and would take Boeing to almost to the 2/3 point of the total 787 deliveries that they have projected for 2012 (35 to 42 with 12 currently delivered).
Tuesday, July 24, 2012
Trent 1000 gear box issue holding up deliveries: Aviation Week
According to an article by Guy Norris in Aviation Week, the gear box issue is holding up deliveries of the Trent 1000 powered aircraft as Boeing needs replacement gear boxes from Hamilton Sundstrand. There are numerous 787s on the Boeing flightline waiting to be delivered. Of the 9 airplanes that I have listed as in final preps for delivery at Everett, 5 are equipped with the Trent 1000 engine. According to Guy Norris' report, 17 Trents in total are affected by the gear box issue of which nine are on undelivered 787s that are earmarked for ANA. Boeing and Rolls Royce are waiting for replacement gear boxes from Hamilton Sundstrand. Of the other 4 787s at Everett/Ft. Worth that are waiting to be delivered, one is in paint (ZA262), one for JAL (ZA182) just emerge from the paint hangar and will robably start pre-flight work soon, the one for Qatar Airways is still finishing up interior IFE work (ZA461) and another 787 that just appeared at the Boeing fuel dock, looks to be United Airlines first 787 (ZA288) and still has to go through painting before moving on the pre-flight. All these are equipped with the GEnx engines.
So it appears the bottleneck may be with the gear box issue with the Trent 1000 engines as each of the 5 Trent 1000 aircraft are all at different point in the pre-flight timeline. Each aircraft has to wait it turn while the aircraft that is further along must clear each pre-flight milestone before the B-1 flight.
In the meantime, the Trent 1000 gear box issue is likely a minor problem that affects a very small portion of the 787s in service but it's an issue that has attracted significant attention because it is the 787.
Lastly, LAN says it is expected to take delivery of its first 787 (ZA536) in late August or early September.
So it appears the bottleneck may be with the gear box issue with the Trent 1000 engines as each of the 5 Trent 1000 aircraft are all at different point in the pre-flight timeline. Each aircraft has to wait it turn while the aircraft that is further along must clear each pre-flight milestone before the B-1 flight.
In the meantime, the Trent 1000 gear box issue is likely a minor problem that affects a very small portion of the 787s in service but it's an issue that has attracted significant attention because it is the 787.
Lastly, LAN says it is expected to take delivery of its first 787 (ZA536) in late August or early September.
Labels:
787,
ANA,
Boeing,
GEnx,
Hamilton Sundstrand,
LAN,
Rolls Royce,
Trent 1000,
ZA182,
ZA262,
ZA288,
ZA461,
ZA536
Tuesday, July 17, 2012
Updated 787 delivery info for July and August
There is new updated delivery information from a variety of sources concerning future deliveries of the 787. First off, ANA apparently has taken delivery of another 787 probably yesterday. ZA508 (LN 51, JA811A) was delivered and should fly to Japan tonight. Apparently that looks to be the only delivery being made this month. However there is more clarity on future deliveries including those to Air India.
Air India - Ajit Singh, the Minister of Civil Aviation, reported that the GoI's CCEA should be taking up the matter of the compensation deal between Air India and Boeing in about 15 days. Now how soon after approval will these airplanes be delivered is another question. According to a posting on airliners.net, the carrier can take delivery of four '87s before August 5th from the flightline at Charleston. This is a rumor and there is nothing official to back it up as of yet. We just have to stay tuned for this drama to play out.
LAN - The first aircraft for LAN has now been moved to the flightline and will presumably be starting the pre-flight testing prior to its B1 flight. There has been some confusion as to when LAN will take this airplane but now there seems to be some clarification. The CEO of LAN told Flightglobal that the carrier will take delivery in September.
ANA - ANA's 787 fleet is well into double digits with several more on the way. There are 4 787s that are winding its way through pre-flight at Everett. According to a posting in airliners.net, ZA100 (LN 7, JA803A) should be making it's B1 flight tomorrow (July 18). This airplane is projected (of course not certain) to deliver around August 8th. The three other 787s are all airplanes that didn't need any re-work done at the EMC. It is quite possible that all these four airplanes can deliver in August though it's more likely that a couple will deliver in August and a couple more in September from this batch. There are still 2 more late build airplanes that are in storage that wold have to finish some amount of change incorporation and I would expect that these airplanes will be delivered later this fall. a, ZA118 is registered as JA813A (LN 67).
Finally, here's an interesting article that sums up Farnborough 2012 air show from aerospace analyst Saj Ahmad.
Air India - Ajit Singh, the Minister of Civil Aviation, reported that the GoI's CCEA should be taking up the matter of the compensation deal between Air India and Boeing in about 15 days. Now how soon after approval will these airplanes be delivered is another question. According to a posting on airliners.net, the carrier can take delivery of four '87s before August 5th from the flightline at Charleston. This is a rumor and there is nothing official to back it up as of yet. We just have to stay tuned for this drama to play out.
LAN - The first aircraft for LAN has now been moved to the flightline and will presumably be starting the pre-flight testing prior to its B1 flight. There has been some confusion as to when LAN will take this airplane but now there seems to be some clarification. The CEO of LAN told Flightglobal that the carrier will take delivery in September.
ANA - ANA's 787 fleet is well into double digits with several more on the way. There are 4 787s that are winding its way through pre-flight at Everett. According to a posting in airliners.net, ZA100 (LN 7, JA803A) should be making it's B1 flight tomorrow (July 18). This airplane is projected (of course not certain) to deliver around August 8th. The three other 787s are all airplanes that didn't need any re-work done at the EMC. It is quite possible that all these four airplanes can deliver in August though it's more likely that a couple will deliver in August and a couple more in September from this batch. There are still 2 more late build airplanes that are in storage that wold have to finish some amount of change incorporation and I would expect that these airplanes will be delivered later this fall. a, ZA118 is registered as JA813A (LN 67).
Finally, here's an interesting article that sums up Farnborough 2012 air show from aerospace analyst Saj Ahmad.
Saturday, July 14, 2012
Are 787 deliveries slowing down?
UPDATE: I got word that Qatar's first 787 will be delivered in August but it's still open as to when in August. Given that at Everett there are only three 787s that have had their B-1 flight thus far (ANA, Qatar, & Ethiopian), I'm going to say that only one 787 will be delivered this month. There hasn't been any word on other 787s that will have their B-1 flight but I expect that at least 2 more will take to the skies for the B-1 flight before the end of July in order to be delivered next month (ZA100 and ZA135).
There has been raised hopes and expectations that aviation geeks around the world would see an avalanche of 787 deliveries starting this summer. However we've seen only a trickle and I am at a loss to explain it. The Everett ramp is getting full of 787s that have either finished change incorporation or are airframes that do not need to go through the EMC but just have a few hundred small jobs left to be done. As successive airplanes come out of 40-26 the number of jobs that remain have fallen to less than 150 with ZA182 (LN 70) for JAL. This aircraft has yet to appear on the Everett flightline though it has been more than 9 days per line move on July 3, about 12 days ago. We may yet see ZA182 as early as tomorrow or Monday.
In terms of getting these planes ready for delivery, while the monster jobs of change incorporation have been completed on those airplanes, there is still a long line for delivery as these planes must go through the step by step process of pre-flight ground test, Boeing flight tests, customer flight tests as well as customer inspections and quality control reviews. It appears that there doesn't seem to be enough resources to tackle all this work for the 8-9 aircraft that are lined up ready for their turn. Both ZA508 (LN 51, JA811A) and ZA100 (LN 7, JA803A) were expected to be delivered this month to ANA. It's looking like on ZA508 will make it and there is rumors of extra work needed to prepare ZA100 for flight. This is the aircraft that needed the most rework as it was the first production standard 787 to enter final assembly. It is not known when this airplane is to finally take to the air.
In the meanwhile the first 787 for LAN, ZA536 (LN 68, CC-BBA) is now on the 40-51 ramp after being painted and is presumably finishing up some assembly tasks. There is some controversy about when it is to be delivered. with some reports saying delivery is in August but LAN is saying that they expect to take delivery of its first 787 late this year. Right next to is a 787 for ANA registered JA813A. This is registration that was assigned to ZA510 (LN 59) and previously I had it listed as in storage and not undergoing any change modification. I doubt that this airplane could have prepared to quickly though it is possible that this airplane may certainly have had some work completed while outside the EMC and it engines attached. I'm trying to find out the true identity of this airplane beyond the registration. There are some late build 787, notably ZA118 (LN 67, JA816A) and ZA119 (LN 69, JA817A) that have "gone missing." I'm assuming that these airplanes, if one of them is not the ANA 787 that currently is sitting on the 40-51 ramp, are in the paint hangar.
Lastly, it is quite possible that ZA262 (LN 49, ET-AOQ) for Ethiopian and ZA461 (LN 58, A7-BCB) for Qatar Airways could be ready for delivery by the end of this month. The former has conduct two Boeing test flights (including the ferry flight to Ft worth) and is currently being painted in Texas. I would expect this airplane back in Everett in about 7 to 8 days. It could could still conceivably conduct customer flights after its return to Everett before the end of the month. ZA461 is more of a question mark as Boeing needs to complete some interior assembly tasks (may be related to the IFE System) prior to further Boeing and customer test flights. Again it is entirely possible that his airplane could deliver by the end of this month.
Don't even ask me about Air India.
There has been raised hopes and expectations that aviation geeks around the world would see an avalanche of 787 deliveries starting this summer. However we've seen only a trickle and I am at a loss to explain it. The Everett ramp is getting full of 787s that have either finished change incorporation or are airframes that do not need to go through the EMC but just have a few hundred small jobs left to be done. As successive airplanes come out of 40-26 the number of jobs that remain have fallen to less than 150 with ZA182 (LN 70) for JAL. This aircraft has yet to appear on the Everett flightline though it has been more than 9 days per line move on July 3, about 12 days ago. We may yet see ZA182 as early as tomorrow or Monday.
In terms of getting these planes ready for delivery, while the monster jobs of change incorporation have been completed on those airplanes, there is still a long line for delivery as these planes must go through the step by step process of pre-flight ground test, Boeing flight tests, customer flight tests as well as customer inspections and quality control reviews. It appears that there doesn't seem to be enough resources to tackle all this work for the 8-9 aircraft that are lined up ready for their turn. Both ZA508 (LN 51, JA811A) and ZA100 (LN 7, JA803A) were expected to be delivered this month to ANA. It's looking like on ZA508 will make it and there is rumors of extra work needed to prepare ZA100 for flight. This is the aircraft that needed the most rework as it was the first production standard 787 to enter final assembly. It is not known when this airplane is to finally take to the air.
In the meanwhile the first 787 for LAN, ZA536 (LN 68, CC-BBA) is now on the 40-51 ramp after being painted and is presumably finishing up some assembly tasks. There is some controversy about when it is to be delivered. with some reports saying delivery is in August but LAN is saying that they expect to take delivery of its first 787 late this year. Right next to is a 787 for ANA registered JA813A. This is registration that was assigned to ZA510 (LN 59) and previously I had it listed as in storage and not undergoing any change modification. I doubt that this airplane could have prepared to quickly though it is possible that this airplane may certainly have had some work completed while outside the EMC and it engines attached. I'm trying to find out the true identity of this airplane beyond the registration. There are some late build 787, notably ZA118 (LN 67, JA816A) and ZA119 (LN 69, JA817A) that have "gone missing." I'm assuming that these airplanes, if one of them is not the ANA 787 that currently is sitting on the 40-51 ramp, are in the paint hangar.
Lastly, it is quite possible that ZA262 (LN 49, ET-AOQ) for Ethiopian and ZA461 (LN 58, A7-BCB) for Qatar Airways could be ready for delivery by the end of this month. The former has conduct two Boeing test flights (including the ferry flight to Ft worth) and is currently being painted in Texas. I would expect this airplane back in Everett in about 7 to 8 days. It could could still conceivably conduct customer flights after its return to Everett before the end of the month. ZA461 is more of a question mark as Boeing needs to complete some interior assembly tasks (may be related to the IFE System) prior to further Boeing and customer test flights. Again it is entirely possible that his airplane could deliver by the end of this month.
Don't even ask me about Air India.
Wednesday, July 11, 2012
First 787 for LAN painted and on the flightline
Everett photographer Matt Cawby got a stunning photo of LAN's first 787 ZA536 (LN 68, CC-BBA) out on the 40-51 ramp after being painted. The aircraft though reported by CAPA to be delivered in November is supposed to be delivered in August. I expect that LAN should have at least two more 787s delivered by the end of this year.
Friday, June 22, 2012
More 787s coming out the door - June 22, 2012
Boeing is really on a roll in terms of getting 787s outthe door and prepared for delivery. Tonight ZA536 (LN 68) will pushed out the door and parked on the 40-51 ramp to finish off minor assembly tasks before moving on to the paint hangar and then on to pre-flight. This airplane will be the first one for LAN. I'm not sure if the other airframes on the apron will be moved to make room for the third airplane. Additionally, ZA262 (LN 49) for Ethiopian was moved from the Everett Modification Center to the Fuel Dock. I suspect it will go through paint and fueling tests before moving out to flightline for pre-flight in the next couple of weeks. Word is that we should see the first flight of Qatar's first 787, ZA461 (LN 59, A7-BCB) this Sunday but that is the rumor for now and nothing concrete as of yet. Lastly, United Airlines confirmed that it will be receiving its first 787 in September. More than likely this will be ZA288 (LN 53, N27904). This aircraft is still in the EMC being prepared for delivery but recently had its GEnx engines attached.
Labels:
787,
787 Entry into Service,
Boeing,
EMC,
Ethiopian,
LAN,
Qatar Airways,
United Airlines,
ZA262,
ZA288,
ZA461,
ZA536
Sunday, June 17, 2012
787 Deliveries to take place soon
According to a post on a forum on Airliners.net, ANA should be taking delivery of 2 787s. ZA506 (LN 47, JA809A) will deliver tomorrow June 18 and ZA507 (LN48, JA810A) will deliver on June 19. Additionally ZA509 (LN56, JA812A) will deliver on June 28th according to the post. In terms of the Air India deliveries, that is still to be determined. It seems that the GoI has not given the go ahead as of yet on the deal between Air India and Boeing. If approval comes this week then I can see deliveries starting very soon thereafter.
July deliveries
The post also said that ZA100 (LN 7, JA803A) and ZA508 (LN 51, JA811A) will be delivered around July 31 and July 11 respectively and it may be possible for ZA135 (LN 66, JA813A) to be delivered during this month as well, this aircraft is still undergoing final assembly tasks on the apron. Qatar Airways, it seems may not take delivery this month but that Boeing will conduct its first flight and then send it to Farnborough under Boeing control and ownership after which Boeing will complete all necessary pre-delivery operations prior to handing the aircraft over to Qatar Airways. I also wouldn't be surprised to see further handover of aircraft to JAL and Air India in July.
Finally, I expect a line move late this week, around Friday the 22nd which should push out the first 787 for LAN, this is ZA536 (LN 68).
July deliveries
The post also said that ZA100 (LN 7, JA803A) and ZA508 (LN 51, JA811A) will be delivered around July 31 and July 11 respectively and it may be possible for ZA135 (LN 66, JA813A) to be delivered during this month as well, this aircraft is still undergoing final assembly tasks on the apron. Qatar Airways, it seems may not take delivery this month but that Boeing will conduct its first flight and then send it to Farnborough under Boeing control and ownership after which Boeing will complete all necessary pre-delivery operations prior to handing the aircraft over to Qatar Airways. I also wouldn't be surprised to see further handover of aircraft to JAL and Air India in July.
Finally, I expect a line move late this week, around Friday the 22nd which should push out the first 787 for LAN, this is ZA536 (LN 68).
Wednesday, May 30, 2012
Boeing readies more ANA 787s but AI planes are in limbo
Where to begin as there's a lot of new stuff.
First let's take a look at the positives. Boeing has 4 787s being readied at Everett for ANA. These are ZA506 (LN 47, JA809A), ZA507 (LN 48, JA810A), ZA508 (LN 51, JA811A), and ZA509 (LN 56, JA812A). ZA 508 is currently in the paint hangar but this plane had spent some time at EMC so I do believe that it is getting its aqueous wash and paint job done before being pulled to the fuel dock for fueling tests then to the flightline for mini gauntlet, engine start and first flight. Thus Boeing will have 4 787s ready for ANA in June maybe more. There has been a line move and currently the 4 787s that are inside 40-26 are ZA135 (LN 66, position 4), ZA118 (LN 67, position 3), ZA536 (LN 68, position 2) and ZA119 (LN 69, position 1). All but ZA536 are for ANA with ZA536 going to LAN. It is conceivable but not certain that ZA135 can go straight to paint and flightline with its engines and start preparation for delivery in about 2 weeks and can possibly be delivered at the end of June. This will be a major milestone for Boeing when it happens. Also ZA461 (LN 58) has made an appearance at the Everett Fuel Dock and I believe that this airplane is being prepared for delivery. I expect it will go into the paint hangar shortly before re-emerging for pre-delivery tests and final delivery to Qatar Airways in June and on display at Farnborough in July. Lastly, ZA237 (LN 46) has filed a flight plan fro Charleston to Fort Worth so this airplane can be painted for Air India. It is currently still in Charleston delayed by weather in the Dallas area. This last point is a nice lead into....
The Negatives
Only one (HUGE) negative which Air India. and here I just don't know where to start my rant. I (and probably 99.9% of of the world) thought that the issue of compensation to Air India for the delays was settled. According to the Govt. of India it is not and thus Boeing may have a dozen 787s for Air India sitting on the ramps at Everett and Charleston waiting to be delivered. The Air India debacle is a case study on how not to run an airline particularly when you are government owned and you have bureaucrats who know nothing of the airline industry making key decisions. ZA233 (LN 29, VT-AND) is all ready to be delivered and I suspect so is ZA236 (LN 35, VT-ANH). How long it will take to complete the negotiations on compensation is anyone's guess but this is Air India attempting to have Boeing pay for the decisions made by the carrier mistakes once again. The pilots strike over who flies the Dreamliner is also bleeding the carrier so they need money and they're going to Boeing for that money. This saga won't end until Boeing has delivered the 27th and final 787 to Air India and washes their hands of them.
First let's take a look at the positives. Boeing has 4 787s being readied at Everett for ANA. These are ZA506 (LN 47, JA809A), ZA507 (LN 48, JA810A), ZA508 (LN 51, JA811A), and ZA509 (LN 56, JA812A). ZA 508 is currently in the paint hangar but this plane had spent some time at EMC so I do believe that it is getting its aqueous wash and paint job done before being pulled to the fuel dock for fueling tests then to the flightline for mini gauntlet, engine start and first flight. Thus Boeing will have 4 787s ready for ANA in June maybe more. There has been a line move and currently the 4 787s that are inside 40-26 are ZA135 (LN 66, position 4), ZA118 (LN 67, position 3), ZA536 (LN 68, position 2) and ZA119 (LN 69, position 1). All but ZA536 are for ANA with ZA536 going to LAN. It is conceivable but not certain that ZA135 can go straight to paint and flightline with its engines and start preparation for delivery in about 2 weeks and can possibly be delivered at the end of June. This will be a major milestone for Boeing when it happens. Also ZA461 (LN 58) has made an appearance at the Everett Fuel Dock and I believe that this airplane is being prepared for delivery. I expect it will go into the paint hangar shortly before re-emerging for pre-delivery tests and final delivery to Qatar Airways in June and on display at Farnborough in July. Lastly, ZA237 (LN 46) has filed a flight plan fro Charleston to Fort Worth so this airplane can be painted for Air India. It is currently still in Charleston delayed by weather in the Dallas area. This last point is a nice lead into....
The Negatives
Only one (HUGE) negative which Air India. and here I just don't know where to start my rant. I (and probably 99.9% of of the world) thought that the issue of compensation to Air India for the delays was settled. According to the Govt. of India it is not and thus Boeing may have a dozen 787s for Air India sitting on the ramps at Everett and Charleston waiting to be delivered. The Air India debacle is a case study on how not to run an airline particularly when you are government owned and you have bureaucrats who know nothing of the airline industry making key decisions. ZA233 (LN 29, VT-AND) is all ready to be delivered and I suspect so is ZA236 (LN 35, VT-ANH). How long it will take to complete the negotiations on compensation is anyone's guess but this is Air India attempting to have Boeing pay for the decisions made by the carrier mistakes once again. The pilots strike over who flies the Dreamliner is also bleeding the carrier so they need money and they're going to Boeing for that money. This saga won't end until Boeing has delivered the 27th and final 787 to Air India and washes their hands of them.
Monday, August 8, 2011
787 Production Update
I've learned today the customers who will be receiving 787s designated from LN 64 to LN70.
They are as follows:
ZA463/LN64 to Qatar Airways
ZA182/LN65 to Japan Airlines
ZA135/LN66 to ANA
ZA118/LN67 to ANA
ZA536/LN68 to LAN
ZA119/LN69 to ANA
ZA240/LN70 to Air India
I don't have information, as of yet, where each will be built (Everett or Charleston) but I'm working to try and get that information. Boeing is planning to increase its 787 production rate to 2.5 airplanes a month by the end of this month.
They are as follows:
ZA463/LN64 to Qatar Airways
ZA182/LN65 to Japan Airlines
ZA135/LN66 to ANA
ZA118/LN67 to ANA
ZA536/LN68 to LAN
ZA119/LN69 to ANA
ZA240/LN70 to Air India
I don't have information, as of yet, where each will be built (Everett or Charleston) but I'm working to try and get that information. Boeing is planning to increase its 787 production rate to 2.5 airplanes a month by the end of this month.
Subscribe to:
Posts (Atom)