Friday, June 20, 2014

Revised June Delivery Estimate For 787

In my previous post, I estimated that Boeing could deliver about 14 787s in June.  New information now leads me to revise that estimate upwards to as many as 16 though it is quite possible that some of these deliveries can spill over into July for delivery.  They have already delivered 8 thus far in June.


Obviously with the quarter end coming up, Boeing wants to book as many deliveries and income as possible, thus this is the rationale for the push to deliver as many as possible.


Given the new information here is a list of aircraft that I believe can be delivered in the next 10 days:


ZA267 (LN 168, ET-AOV)
ZB003 (LN 169, ZK-NZE) - this plane should deliver at the end of the month but expect it to stay in Everett until July 10th for crew training.
ZA219 (LN 175, VK-VKF) - this plane also should deliver at the end of the month but the delivery may spill over to July.
ZA541 (LN 185, CC-BBF) - should deliver around 6/24.
ZA295 (LN 186, N28912) - should also deliver around 6/24.
ZA456 (LN 187, G-ZBJG) - this aircraft still needs to conduct its first flight but is tentatively scheduled to be delivered at the end of this month.
ZA588 (LN 190, HS-TQA)  - should be delivered at the end of this month but it may spill over to July.
ZA321 (LN 191, G-TUIE) - should be delivered at the end of this month but it may spill over to July.


If Boeing can deliver all 8 then they would have achieved 50 787 deliveries in the first 6 months of 2014 and will have put themselves in a good position to deliver 60 to 70 more in the second half of the year.