Sunday, February 18, 2018

787 February 2018 Mid Month Report

Boeing is well on track to deliver around 10 to 12 787s in February.  Thsu far, Boeing has delivered 8 787-9s to customers including the last 2 787-9s on United Airlines' order of 25.  United now has the 14 787-10 left on their large 787 order left to be delivered. Air Canada also had its 25th 787-9 delivered (out of an order for 29) during the last couple of weeks.  Thus far Boeing has delivered 16 787s (all -9s).

One thing to note is that Xiamen Airlines apparently did not take delivery of its 5th 787-9 and is still at Charleston which engine covers still on but parked at the delivery center.  Their 6th and last 787-9 is still on Charleston flightline awaiting its first flight.  Hopefully I'll have a little more information as to the delivery delay and when it should finally deliver.

Boeing is also readying the first 787-10 for delivery around March 14th.  ZC004 (LN 656, 9V-SCA) has taken several flight tests, presumably to test not just the aircraft but the customer furnished equipment that Singapore has wanted installed in their -10s.  I expect that there will be a few filight tests since this is the 1st 787-10 being delivered and this is Singapore's first  direct 787 delivery (not counting Scoot, of course).

Production is moving at the typical pace with 7 Dreamliners rolled out and another 6 which have started final assembly.  Over the next few months we should see more 787-10s rolling out of Charleston all destined for Singapore followed by a short pause and then the GE powered -10s for Etihad and United should start to follow.  Speaking of the production of the -10, Boeing got approval from the FAA on the -10 production at Charleston in the form of the 787-10 production certificate.   This means that the production system and the support for production has met all FAA requirements.  All three 787-10 flight test aircraft are now at Charleston and I'm presuming that they will now undergo change incorporation and re-work at Charleston over the next 6 to 9 months in preparation for delivery to Singapore and United.

In the meantime, continue to browse through the 787 production spreadsheets for more information:

787 Spreadsheets

Tuesday, August 9, 2016

787 program takes another financial hit as program deliveries continue to meet expectations, near term deliveries in question due to thrust reverser issue.

Number
Testing Complete3
To be assembled in Everett172
To be assembled in Charleston121
Parts Arriving6
Undergoing final assembly10
Storage0
Storage/Change Incorporation and Re-Work0
Change Incorporation and Re-Work5
Pre-Flight Prep12
Production Testing8
Non Customer Flight Tests1
Ready for Delivery0
Donation3
Delivered446
TOTAL787

Near term deliveries of the 787 look to slow down due to unspecified issues with the thrust reversers affecting both GE and Rolls Royce powered aircraft.  A source has indicated that this is not a fleet wide problem but concerns a batch of thrust reversers that are installed on current 787s that are on the flightline or that are currently being assembled.  New thrust reversers without the issue have been manufactured and are being installed on several aircraft on the flightline including ones for Hainan, JAL and Scoot as those aircraft have their engines removed.  I do expect that these aircraft should deliver before the end of the year and that this issue should not affect final delivery numbers though it could push deliveries to the fourth quarter.

Just when followers of the 787 program thought that the program was just starting to emerge from the financial black hole that was created, it was sucked right back in with Boeing's announcement of an incredibly high charge of $847 mm against 2Q16 earnings.  The charge is due to inability by Boeing to sell the last two original 787-8 flight test aircraft, namely LN 004 (ZA004, N7874) and LN 005 (ZA005, N787FT).  The cost of refurbishing them to certification standards is too high compared to where they can sell them.  This charge was in addition to the charges that Boeing has taken on the 747-8 program ($814 mm) and the KC-46A program ($393 mm).  Boeing will be reclassifying the unit costs associated for these two airplanes from inventory to R&D expense

So what is to become of the two flight test airplanes?  Well ZA004 is currently performing certification testing for the Rolls Royce Trent 1000 TEN.  Once that is complete I expect that this airplane will be donated to a museum. ZA005 flew back to Everett in 2013 and appeared to have some re-work and change incorporation performed on it.  Many of the movable flight surfaces were taken off as were the engines. However, the aircraft has remained in that stripped down state for the more than 2 years.  Now that Boeing is taking this charge I expect that the aircraft will be further stripped for usable spare parts that will probably have to refurbished.  The airframe will probably be destroyed, perhaps Boeing use this airframe as a demonstration on how to dispose of a carbon composite fuselage in a way that is environmentally friendly as recycling CRFP aircraft parts on a large scale has never been done.  This could give Boeing an opportunity to develop proper disposal techniques.
 
Getting back to the 787 production story, Boeing delivered 14 787s (3 787-8 and 11 787-9) in July including one early build 787-8 (ZD006, LN 14, ET-ATK) for Ethiopian Airlines.  Boeing has been making very good progress in getting these airplanes ready for delivery though it's taken the better part of 5 to 6 years for each.  Boeing is slated to deliver 3 more early build 787s (one each in August, September and November) this year with one already in paint and a second one being prepped for its first flight. Other notable deliveries include the first 2 787-9s that were directly purchased by Hainan (still listed as unidentified on Boeing's order and delivery website) and Qatar's 30th and final 787-8 that they have on order.  I'm still waiting for them to exercise their options.  Any day now U-Turn Al.
With the 14 deliveries in July, Boeing has delivered 82 787s this year through the end of July and 445 since program deliveries began.  There are 309 787-8s in operation and 136 787-9s flying. With one additional delivery made this month, Boeing is 54 deliveries away from achieving 500 customer deliveries.  This is something they can achieve by the middle to end of December as long as there aren't any delays in current delivery schedule.  This equates to roughly 11 deliveries per month for the next 5 months.  Boeing has been doing well on that account for the past 3 months.

In terms of production, the two production facilities are still turning out the aircraft as the planned rate of 12 per month.  The efficiency ratio last month was at 0.79 which was driven mainly by higher deliveries from Everett which had a pretty good efficiency ratio of 0.67.  Charleston had a respectable ratio of 1.0.  It should be noted that the one early build 787-8 is included in the calculation of Everett's efficiency ratio.

Looking forward, Boeing was planning for only 9 787 deliveries in August but with the thrust reverser issue it will probably be lower, around 5-6.  One of those deliveries with, ZA155 (LN4457, CN-RGT) for Royal Air Maroc, has already been made.  ZB368 (LN 396, G-ZBKG) a 787-9 for British Airways is finally set to be delivered at the end of this month after being grounded due to issues with Zodiac in delivering the interiors to Everett for installation.  Another early build 787-8, ZD005, (LN 13, ET-ATJ) should also be delivered by the end of this month.  I can only attribute the lower delivery number to the typical August slow down for the summer as well as the aforementioned issue with the thrust reversers.  I do see the delivery rate picking back up in September to catch up to the needed 11/month delivery rate that Boeing needs to make for the remainder of the year.


I'll be following this post with another one reviewing Boeing's comments on the 787 during the 2nd quarter as well as prospects for a rate increase by the end of this decade.


787 Full Production Table