From Oct. 18 to Oct. 22 inclusive, Boeing took advantage of a break in the weather to fly 6 different production 787s on their B-1 flights. The aircraft were obviously ready but bad weather forced a hold on all B-1 flights. Thus when the break came Boeing released the planes for flight. However because of the delay, I expect that none of these airplanes will be able to be delivered by the end of the month. It does potentially set up November as a big month for deliveries but there may be a knock on efffect as 787s that were scheduled for flights around this time will be pushed back to later this month and certainly into early November.
10/18/2012
ZA270 (LN 61, SP-LRA) - LOT Polish Airlines
10/20/2012
ZA430 (LN 73, B-2728) - Hainan Airlines
ZA290 (LN 77, N26906) - United Airlines
10/21/2012
ZA239 (LN 60, VT-ANK) - Air India
10/22/2012
ZA261 (LN 44, ET-AOP) - Ethiopian Airways
ZA460 (LN 57, A7-BCA) - Qatar Airways
In addition to the increase B-1 flights, there was a very noticable increase in follow on flights of other airframes that have already flown. There included a C-1 flight for ZA238 (LN 54, VT-ANJ) which is expected to be delivered to Air India before the end of the month, hopefully).
Given the increased activity, however, I do not expect a lot of deliveries in the next 8 days. There are really 3 airplanes that are ready for delivery or will be ready for delivery. There is a possibility of one more airplane that could be delivered this month but it only has an outside chance.
Ready or almost ready for delivery:
ZA537 (LN 74, CC-BBB) - LAN
ZA264 (LN 75, ET-AOS) - Ethiopian
ZA238 (LN 54, VT-ANJ) - Air India (only had one C-1 flight may need more)
The one airframe that might make it for delivery by the end of this month is:
ZA511 (LN 63, JA816A) - ANA
The last aircraft still needs to perform customer flights and I am not sure if it has completed all the Boeing test flights at this point even though it has flown twice.
It is apparent that if Boeing can maintain an aggressive flying schedule in November, they can have a lot delivieries in that month. Much depends on the aircraft condition after completing final assembly/change incorporation as well as weather and the ability to work through the backlog of planes that are finished and need to go through testing.
Showing posts with label ZA537. Show all posts
Showing posts with label ZA537. Show all posts
Monday, October 22, 2012
6 787s fly for the first time in 5 days
Labels:
787,
787 Deliveries,
Air India,
ANA,
Ethiopian,
Hainan Airlines,
LAN,
LOT,
Qatar Airways,
United Airlines,
ZA238,
ZA239,
ZA261,
ZA264,
ZA270,
ZA290,
ZA430,
ZA460,
ZA511,
ZA537
Friday, October 19, 2012
Several 787s getting set for 1st flight
Boeing seems to be ready to fly several 787s on their first flights as well as continue flight testing several more in preparation for delivery. As of today Boeing has delivered 29 planes to 7 worldwide customers.
There have been several Flightaware alerts for several 787s that are sitting at Everett and Charleston.
Yesterday there were several Flightaware alerts for several 787 B-1 flights. Those that were slated to fly were ZA460 (LN 57, A7-BCA) for Qatar Airways, ZA270 (LN 61, SP-LRA) for LOT Polish Airlines, ZA290 (LN 77, N26906) for United Airlines. However by the end of the day only ZA270 flew while the other two conducted taxi tests around Everett. Today there were Flightaware alerts for 2 B-1 flights: ZA430 (LN 73. B-2728) for Hainan Airlines and ZA239 (LN 60, VT-ANK) for Air India, the later being the third Charleston built 787 which should deliver sometime around November. As of now these 787s have not flown and have probably ran taxi tests around their respective airfields. I also expect that ZA261 (LN 44, ET-AOP) for Ethiopian should also take flight by sometime next week from Everett. This is an indication that Boeing is trying to aggressively ramp up the delivery process once the airplanes have left the EMC or the assembly line. I would expect that within the next couple of day that all these airplanes will fly as well as continued flight test activity from the airplanes that have already flown in preparation for delivery. The big factor nowadays is the weather around Washington State which is keeping the airplanes grounded (today for instance).
Meanwhile production and re-work continues at a pretty good pace with ZA538 (LN 80, CC-BBC) for LAN and ZA289 (LN 55, N26905) for United Airlines both entering the paint hangars at Everett. Assembly continues to pace at a little over 4/month. New airframes are being loaded in Everett at about 1 every week with the next one slated to load on Oct. 25. There are currently two 787s that are ready for delivery one for LAN (ZA537, LN 74, CC-BBB) and one for Ethiopian (ZA264, LN 75, ET-AOS).
There have been several Flightaware alerts for several 787s that are sitting at Everett and Charleston.
Yesterday there were several Flightaware alerts for several 787 B-1 flights. Those that were slated to fly were ZA460 (LN 57, A7-BCA) for Qatar Airways, ZA270 (LN 61, SP-LRA) for LOT Polish Airlines, ZA290 (LN 77, N26906) for United Airlines. However by the end of the day only ZA270 flew while the other two conducted taxi tests around Everett. Today there were Flightaware alerts for 2 B-1 flights: ZA430 (LN 73. B-2728) for Hainan Airlines and ZA239 (LN 60, VT-ANK) for Air India, the later being the third Charleston built 787 which should deliver sometime around November. As of now these 787s have not flown and have probably ran taxi tests around their respective airfields. I also expect that ZA261 (LN 44, ET-AOP) for Ethiopian should also take flight by sometime next week from Everett. This is an indication that Boeing is trying to aggressively ramp up the delivery process once the airplanes have left the EMC or the assembly line. I would expect that within the next couple of day that all these airplanes will fly as well as continued flight test activity from the airplanes that have already flown in preparation for delivery. The big factor nowadays is the weather around Washington State which is keeping the airplanes grounded (today for instance).
Meanwhile production and re-work continues at a pretty good pace with ZA538 (LN 80, CC-BBC) for LAN and ZA289 (LN 55, N26905) for United Airlines both entering the paint hangars at Everett. Assembly continues to pace at a little over 4/month. New airframes are being loaded in Everett at about 1 every week with the next one slated to load on Oct. 25. There are currently two 787s that are ready for delivery one for LAN (ZA537, LN 74, CC-BBB) and one for Ethiopian (ZA264, LN 75, ET-AOS).
Labels:
787,
787 Deliveries,
Air India,
Boeing Charleston,
Ethiopian,
Hainan Airlines,
LAN,
LOT,
Qatar Airways,
United Airlines,
ZA239,
ZA261,
ZA264,
ZA270,
ZA289,
ZA290,
ZA430,
ZA460,
ZA537,
ZA538
Friday, August 17, 2012
No 787 delivery to Air India today
Sources have confirmed to me that Boeing did not deliver a 787 to Air India today and further revealed that the company was not expecting to make a delivery from the Boeing Charleston facility today. There is still no confirmed date as to when Air India will allow a delivery to take place. Boeing is ready to deliver the three 787s parked at Charleston and is awaiting word from Air India. It was close, it seems, as of last Wednesday when ZA236 took a test flight but then rumors started to come out that the Indian Ministry of Finance as not signed off on the transfer of the final payment to Boeing. Again this further erodes any confidence that these airplanes will be delivered anytime soon. This entire episode is further proof of the incompetence and mismanagement at Air India and the Government of India itself.
In the meantime there are 4 787s (3 with Air India livery) that are parked at Charleston. The fourth aircraft is widely believed to be ZA238 which experienced the engine issue last month and now has a replacement engine. I anticipate that this airplane can make its first flight in about two weeks.
Lastly there was a line move in Everett and ZA537 (LN 74, CC-BBB) for LAN has been pushed out onto the 40-51 ramp to finish off minor assembly tasks before being sent over to the paint hangar. I anticipate that this airplane can deliver sometime in early to mid October since Boeing has a very full ramp of 787s that they need to deliver ahead of this particular aircraft.
Meanwhile ANA will be gearing up to take ownership of its 12th 787 as ZA100 conducts it customer test flights.
In the meantime there are 4 787s (3 with Air India livery) that are parked at Charleston. The fourth aircraft is widely believed to be ZA238 which experienced the engine issue last month and now has a replacement engine. I anticipate that this airplane can make its first flight in about two weeks.
Lastly there was a line move in Everett and ZA537 (LN 74, CC-BBB) for LAN has been pushed out onto the 40-51 ramp to finish off minor assembly tasks before being sent over to the paint hangar. I anticipate that this airplane can deliver sometime in early to mid October since Boeing has a very full ramp of 787s that they need to deliver ahead of this particular aircraft.
Meanwhile ANA will be gearing up to take ownership of its 12th 787 as ZA100 conducts it customer test flights.
Labels:
787,
787 Deliveries,
Air India,
ANA,
Boeing,
Boeing Charleston,
LAN,
ZA100,
ZA236,
ZA537
Sunday, July 1, 2012
Air India 787s on the move, Qatar 787 readied for Farnborough
Over the weekend Matt Cawby spotted the two Air India 787s that are ready for delivery sporting temporary US registration numbers on their fuselages. This lead to speculation that the aircraft are to be flown out of Everett for possible storage, maybe in the desert. Well the speculation was mostly correct. The two 787s, ZA233 (LN 29,VT-AND) and ZA236 (LN 35, VT-ANH) will be flown to Charleston to join sistership ZA237 (LN 46, VT-ANI) on Monday, July 2nd. Now the reason why it is being flown to Charleston isn't officially disclosed but the obvious reason could be for a triple delivery to AIr India and that still could happen but sources have told me that delivery to Air India is still listed as "TBD". It is conceivable that these three airframes for Air India will be delivered from Charleston but another reason is that if Boeing is able to turn the keys over to the carrier between July 4th and July 8th, they will be unable to fly away during those dates as the runway at Everett will be closed. This way Boeing leaves open the delivery and fly away during those dates by transferring these airplanes to Charelston. The most likely reason is to free up space in Everett for other aircraft that are ready to be delivered. Already ZA135 (LN 66, JA815A) is already out of paint and need to prepare for pre-flight. ZA100 (LN 7, JA803A) is currently sitting in the fuel dock sans its rudder (don't know why) this aircraft is projected to be delivered at the end of July but it still needs to have its rudder reattached and go through pre-flight. The pace of aircraft reaching the flightline ready for pre-flight is quickening and Boeing needs the space. Given the uncertainty of the Air India deliveries this is a good move to keep the pace at Everett moving. ZA461 (LN 58, A7-BCB) for Qatar Airways is already at Boeing Field to prepare to fly to Farnborough later this week this airplane is still projected to deliver later this month. Another flightline stall should open up tomorrow as ZA509 (LN 56, JA812A) will deliver today, as far as I know, and should fly away tomorrow July 2. ZA508 (LN 51, JA811A) should deliver around July 11th with fly away on July 12th.
On Tuesday another line move should occur which will push out ZA119 (LN 69) for ANA and will mark the start of final assembly for ZA537 (LN 74) for LAN.
On Tuesday another line move should occur which will push out ZA119 (LN 69) for ANA and will mark the start of final assembly for ZA537 (LN 74) for LAN.
Wednesday, April 4, 2012
First SC built 787 to roll out at end of April, 787 production update
Boeing announced that the first 787 built in North Charleston will roll out of final assembly on April 27th. This aircraft, ZA237 (L/N46), is destined for Air India and should be delivered this summer. Even though it is rolling out it will probably go through a more extensive battery of ground and gauntlet testing as this is the first 787 built outside of Everett where most of the assembly technicians are new to building this aircraft. After gauntlet testing Boeing will conduct a B-1 test flight and then fly the aircraft to Texas where it will be painted. It will return to North Charleston to finish pre-delivery Boeing and customer test flights. I don't know if it already has the customer interior installed but that could happen just before painting but after flying the initial test flight. In case the test flight has uncovered any issues that need to be corrected, Boeing techs will probably want unrestricted access to any areas. Interior fittings like seats, galleys, and restrooms can get in the way.
Lastly, I updated the 787 production firing order with LN71-LN75. One slight change is that LN 63 which was going to be for Hainan Airlines is now going to ANA with Hainan now getting LN 73. I was able to get some information on where these particular airplanes will be built as well. These 5 frames are, for now, scheduled to go to Ethiopian (2 frames), Air India, Hainan, and LAN. Interesting no new first delivery frames in this lot.
Lastly, I updated the 787 production firing order with LN71-LN75. One slight change is that LN 63 which was going to be for Hainan Airlines is now going to ANA with Hainan now getting LN 73. I was able to get some information on where these particular airplanes will be built as well. These 5 frames are, for now, scheduled to go to Ethiopian (2 frames), Air India, Hainan, and LAN. Interesting no new first delivery frames in this lot.
Subscribe to:
Posts (Atom)