Friday, February 10, 2012
No 787 Deliveries in February
Thursday, January 12, 2012
January 787 delivery update part 2
ZA102 (JA804A, L/N 9) is scheduled to be delivered today and may flyaway a couple of days from now. There were no further test flights of both aforementioned aircraft since January 10th.
ZA117 (JA806A, L/N 40) is still scheduled (tentatively) for delivery on the 30th but this should be taken with a grain of salt as the aircraft has not appeared on the flightline yet.
Further I've gotten information that ZA236 (VT-ANH, L/N 35) may make its first flight around Jan. 16th though this is still up in the air (so to speak). This aircraft is to conduct the final portion of F&R/ETOPs testing on the GEnx powered 787 for certification purposes. If Boeing is able to get this part of the program completed in time with certification of of the GEnx 787s then They may be able to deliver two GEnx 787s starting in February. One each would go to Japan Airlines (ZA177, JA822J, L/N 22) and Air India (ZA236, VT-ANH, L/N 35). Boeing also has a 787 penciled in for ANA (ZA105, JA808A, L/N 42) next month.
There are no definitive delivery dates for these airplanes for obvious reasons and these airplanes themselves may not deliver next month due to continued issues revolving the amount of re-work and the allocation of resources to effectively deal with the amount of work. there should be further clarification of the 787 deliveries on about two weeks when Boeing has it's 2011 earnings conference call.
Saturday, December 31, 2011
Dec. 31st - no sign of further 787 deliveries
This doesn't indicate that ANA and Boeing has concluded the formal signing over of the aircraft and transferring of money and signing of documents. That may well have happened already but no aircraft has left Everett bound for Japan as of yet and there has been no announcement from Boeing or ANA of the formal delivery of any of these airplanes. ZA116 (JA805A) is still in Everett and has flown both Boeing and customer flights but I don't know if there are more test flights that have yet to be done or if there is any more work that needs to be concluded on the airplane itself. This Dreamliner is probably the one that is closest to being delivered.
The other two airplanes ZA104 (JA807A) and ZA102 (JA804A) have done some customer flights out of Everett but probably need to do a few more flights before ANA formally accepts them. I do think that Boeing can deliver all three airplanes within the next week in order for ANA to meet its newly revised international 787 service schedule. It is to start Tokyo - Beijing service in the middle of January and Tokyo - Frankfurt service in February.
As far as other airplanes, ZA236 has yet to make a flight to start finish F&R/ETOPs testing on the GEnx powered 787. There is no word on when that will happen though it has run its engines for the first time just before Christmas though there was a small fuel fire 30 minutes into the engine run. I don't know what effect that has on the schedule as of now.
Saturday, December 17, 2011
Now it's three
Friday, December 16, 2011
More on Boeing 787 delivery schedule
Dominic Gates reported yesterday evening that the reason of the delay for the third 787 to ANA is wiring issues that the FAA found during a standard inspection as well as non functioning APUs in three 787s. Because the APU didn't start, tests that were to be done with the APU running had to be put off until the units were replaced. Boeing is calling these issues minor yet they were severe enough to force ANA to revise its international plans that were supposed to start this month.
It is unknown if this is a problem that is endemic through the 787s that are sitting in Everett or it is just a one off problem. Still the upshot is that the L/N will not be delivered until middle of next week and the other three airplanes that are set to be delivered have yet to fly on their pre-delivery tests with Boeing and ANA pilots. The delay which this site reported back in mid November forced ANA to postpone the start of international 787 service to next month.
Due to the pressure to deliver these four airplanes (L/N 9, L/N 31, L/N 41, L/N 42) Boeing is having some of it workers work through the holiday season which is traditionally a week off for Boeing employees. Undoubtedly they will probably be well compensated for their time. There are only three of these airplanes on the Boeing flightline though the fourth, L/N 42, is outside in front of EMC so it might be pulled out to the flightline very soon. Interestingly according to the Bloomberg article, the APU and wire issues aren't pacing the schedule. The question then is, what is pacing the delivery schedule, at least in the near term. Both articles say that Boeing feels that the issues are minor.
As of yet L/N 41 and L/N 42 have not flown and L/N 9 while it has flown still has not begun the process of Boeing and customer check flights. L/N 31 has had quite a few flights but has not flown since Wednesday, Dec. 14th. I'll be watching to see if there is any further movement on these airplanes but certainly, if the other three airplanes have not flown by middle of next week then Boeing's hopes of delivering at least four 787 this month will be dashed.
Lastly, in a related note, L/N 35 which to perform the ETOPs/F&R testing for the GEnx-1B on a 787 production frame still has not made its first flight. IF Boeing hopes to deliver the GEnx powered 787 next month they need to start flight tests on this airplane very soon or the certification and start of deliveries can slide to the right again.
Thursday, December 15, 2011
Boeing to attempt 4 787 deliveries in December
In addition to JA805A (L/N31,ZA116) and JA807A (L/N41, ZA104); Boeing will also try to deliver JA804A (L/N9, ZA102) and JA808A (L/N42, ZA 105).
L/N 9 has already flown as it took part in the certification test program when it conducted F&R/ETOPs testing for the 787/Trent-1000 combination. Boeing should be able to deliver this airplane though it still needs to conduct pre-delivery test flights. Of the four airplanes that are mentioned above, only L/N 31 is flying customer and Boeing pre-delivery flights. It it anticipated that this airplane should be delivered within the next one week, before Christmas time.
The other three have yet to fly and are all scheduled to be delivered just before New Year'e Eve (2011 in case you were wondering). L/N 42 was to have flown on Dec. 13th and it is still not on the flightline as of yet. L/N 41 is supposed to fly on the 16th of December.
Additionally, it was revealed that Boeing has penciled in three 787 deliveries for next month. L/N 23 (JA822J, ZA177) will be the first 787 with GEnx-1B engines delivered to a customer. This airplane has just returned from San Antonio where it was undergoing change incorporation. It has received a new paint job (which has underwhelmed the aviation geek community) though I don't know if it has its customer interiors fitted as of yet. L/N 35 (VT-ANH, ZA236) for Air India is also due to be delivered in January. This airplane is supposed to start ETOPs/F&R testing in support of the certification test program for the GEnx powered 787s. According to Flightblogger, this airplane is to have it's first flight around the middle of December so far nothing yet. Lastly, L/N 40 (JA806A, ZA117) will also be delivered to ANA in January. This aircraft is still at EMC. Nothing is certain with these three airplanes and their delivery dates are dependent on getting the work done on them as well as finishing up ETOPS and F&R testing on the GEnx powerplant.
This is quite an ambitious schedule for the next two weeks for Boeing. They are still struggling with the amount of work that has to be done on the 24 or so 787s that are in Everett. Particularly vexing is the amount of work on the early build 787s. As I had mentioned before none these early build 787s are in EMC (yet) or in 40-24. They're all stacked up on the Everett flightline. Most of the deliveries are the late build models which don't require as much work. Even so, the amount of work is so daunting that Boeing is trying hard to get the late build 787s into the air and into the hands of customers. There is a rumor going around that Boeing is pulling people off the 747-8 airplanes that have to be prepared for delivery and putting them on 787. If so then 747 deliveries might fall as a consequence. Boeing has delivered 8 thus far and are planning to deliver 1-2 more 747s.
Time is running out if Boeing is to deliver even two 787s this month let alone 4.
Thursday, December 1, 2011
787 update 12/1/2011
ZA004 - Trent Package "B" testing
According to Guy Norris, Boeing has completed certification testing for the Trent 1000 package "B" improvements for the 787. This will allow Boeing to finally start to deliver 787 with the new Trents which bring the specific fuel consumption to within 1% of the original promised specs. Boeing had undertaken this testing using ZA004. Over the last few weeks this airplane has been flown several times a day in order to finish up all the requirements. Once the FAA has received and approved all the test data, Boeing should be able to start delivering 787s with this engine. L/N 31 will be the first 787 to be delivered with the package "B" Trent 1000 engines.
Future deliveries
The pace of deliveries is obviously being didtaced by the pace of change incorporation which is excrutiatingly slow right now. The pace has already pushed the GEnx 787 deliveries out to January as well as deliveries to Trent 1000 customers further to the right. ANA was supposed to have received 5 787 in December...it will only receive two (L/N 31 and L/N 41). Both these airplanes are Trent 1000 package "B" airplanes. There are two other ANA 787s that have their engines attached and being prepped for delivery. These are L/N 9 (ZA102, JA804A) which was just pulled out to the Everett fuel dock and L/N 42 (ZA105, JA808A) which is still in front of the EMC.
These airplanes are not due to be delivered until after January 1st but there are now more 787s appearing on the flightline in preparation for delivery which is a good sign but on the flip side most of the aircraft that are out on the flightline are very early build airplanes that need extensive re-work done before they can be delivered to customer. Just to get these 11 airplanes (L/N 7 to L/N 19) done would probably take a good 2 years. Most of the deliveries will come from the late builds, particularly L/N 30 on up.
Production and Ramp Up
Jim Albaugh gave a nice update on the status of 787 production and ramp up. Currently they are are still at producing at 2.5 787 per month with the aim of ramping to 3.5 by around March or April and then to 5 by the end of 2012. Boeing is still maintaining it guidance of 10 787s per month by the end of 2013.
Albaugh had very good things to report about the North Charleston plant. The first aircraft from that line should deliver before June of 2012. The plant is capable of producing 2.5 787 per month right now. Boeing has now opened up the delivery center as well as the 787 interiors fabrication plant to supply bins, partitions, crew rest areas, etc. for the Charleston built 787s.
Test Flight Fleet
Now that test flights are nearing the end (at least for the 787-8), Boeing is starting to make plans for the first three airplanes built. ZA004-ZA006 will be refurbished and sold to customers (BBJ). Boeing has flown ZA001, the first 787, to Palmdale Airport where it will be in storage until they figure out which museum to house it in. Likely candidates are the Museum of Flight in Seattle or the Future of Flight museum in Everett though I wouldn't count out the NASM (National Air and Space Museum) in Virginia out. ZA002 is going to be in Charleston, SC for some time for testing purposes but its long term fate is unclear. ZA003 is due to start a 6 month tour of the 787 on December 5th. First stop is China an other Asian and African countries whose airlines have bought the 787. After the tour is completed the aircraft's long term fate is also undecided. No doubt there would be some testing to be done, particularly on engine and airframe improvements to lower weight and increase fuel efficiency and reduce the noise footprint. This is why ZA002 and ZA003 will probably held by Boeing for the foreseeable future to serve as test beds for these improvements.
Friday, January 29, 2010
End of the month 787 Update
Hey Boeing, who did you get that idea from?
The hours they've calculated are from internal flight times they've calculated and not based on the hours that are posted on flightaware.com (you can link to the flightaware database by clicking on the individual aircraft. The number of flight hours they're calculating is about 3 hours more than what I have posted. I don't know the reason for the discrepancy.
The web site is very extensive and has a lot of information including the flight test roles for each of the 6 test airplanes, video and news reports from the flight test team and pilots, as well as the usual multimedia suspects one comes to expect. Boeing needs to be applauded for providing a greater degree of transparency at this critical stage of the 787 program.
Boeing 787 Flight Test Site
There are a few other tidbits coming out the 787 program through Matt Cawby. He has video of ZA004 gear swing test as well as reporting that the wings for LN 17 was flown in. This may mean that LN 12 has exited the final assembly line. Matt also reported that Boeing conducted VHF radio checks with ZA003. Lastly, Matt also reports that the third 747-8F (and third flight test aircraft) was moved to the Boeing flightline on Wednesday though it still is unpainted.
Matt Cawby's January 28th Posting
Monday, January 18, 2010
Boeing Complete 787 Inital Airworthiness Testing
- The 787 is safe to fly with more than just the pilot and co-pilot aboard. Now Boeing's flight test engineers can also fly aboard to monitor tests
- The 787 flight envelope can now be expanded beyond the what has already been tested thus far.
Here's Boeing's Press Release:
News Release Issued: January 15, 2010 5:28 PM ESTAs always, the other follows of the 787 program weighed in with their postings and here is a rundown of this weekends commentary.
Boeing 787 Dreamliner Achieves Initial Airworthiness Milestone
EVERETT, Wash., Jan. 15 /PRNewswire-FirstCall/ -- Boeing (NYSE: BA) has completed initial airworthiness testing on the 787 Dreamliner. This milestone will enable more crew members to take part in flights and will allow more airplanes to join the flight test program.
"This is an important step forward," said Scott Fancher, vice president and general manager of the 787 program, Boeing Commercial Airplanes. "We are very pleased with the results we have achieved so far. The airplane has been performing as we expected."
Since the first flight in mid-December, the program has conducted 15 flights, achieving several key accomplishments. Pilots have taken the airplane to an altitude of 30,000 feet (9,144 meters) and a speed of Mach 0.65. Nearly 60 hours of flying have been completed. Initial stall tests and other dynamic maneuvers have been run, as well as an extensive check-out of the airplane's systems. Six different pilots have been behind the controls of the 787.
In the weeks ahead, the team will continue to expand the flight envelope at which the 787 will operate to reach an altitude of more than 40,000 feet (12,192 meters) and a speed of Mach 0.85. Subsequent testing will push the airplane beyond expected operational conditions.
"The pilots have told me the results we are seeing in flight match their expectations and the simulations we've run. That's a real tribute to Boeing's expertise and the international team that helped develop and build the airplane," said Fancher.
Flight testing will continue in the months ahead. First delivery is planned for the fourth quarter of this year.
Flightblogger posted a great update reviewing the previous months' flight test progress as well as reviewing the status of the aircraft that have been built thus far. Here's a synopsis of the aircraft status:
ZA001/LN1 : At Boeing Field undergoing flight tests
ZA002/LN2: At Paine Field for aqueous tank wash
ZA003/LN3: At Paine Field undergoing preparations for its first flight in February
ZA004/LN4: At Paine Field fuel dock undergoing preparations for its first flight in February
ZA005/LN5: At Paine Field ATS Hangar undergoing side of body modifications
ZA006/LN6: At Paine Field ATS Hangar undergoing side of body modifications
ZA100/LN7: At Paine Field flightline awaiting side of body modifications
ZA101/LN8: At Paine Field flightline awaiting side of body modifications
ZA102/LN9: At Paine Field inside temporary hangar undergoing side of body modifications
ZA103/LN10: At Paine Field undergoing painting
ZA104/LN11: At Paine Field building 40-24
ZA105/LN12: At Paine Field undergoing final assembly
ZA115/LN13: At Paine Field undergoing final assembly
ZA116/LN14: At Paine Field undergoing final assembly
ZA117/LN15: At Paine Field undergoing final assembly
Parts for airplane 16 are starting to arrive into Everett. This airplane is the first to be assembled that will not require the side of body modifications. Lastly, Flightblogger reports that when parts for airplane 17 arrives it'll be for for Royal Air Maroc powered by GEnx engines.
787 Flight Test Update: Month One
Guy Norris had a nice synopsis of the 787 program on his blog as well. In it he said that ZA001 is going to be taking a breather while it undergoes checks. The airplane has not flown since January 14th.
Guy Norris: 787 completes initial airworthiness testing
Finally, Innovation Analysis Group, had a great Podcast featuring Jon Ostrower (Flightblogger) and Guy Norris.
Sunday, January 10, 2010
787 Update - January 10, 2010
ZA003 should show up very soon on the Everett ramp as well very soon to start it's preparations for first flight.
Both ZA003 and ZA004 are projected to have their first flights in the first week of February.
Additionally, Matt Cawby reported on his blog that the fatigue test air frame is very close to finishing its side of body modifications and should be moved to the fatigue test area around January 30th to start 3 years of fatigue testing. It will be moved out of the temporary hangar that is on the Boeing flight line.
Matt Cawby's January 9, 2010 Blog Update
Flightblogger got a great article up on the production challenges that the 787 still faces now that the aircraft has entered test flights. Thus far Boeing has completely assembled 1 complete 787s (LN 1 through LN 11) plus two test air frames (ZY997 and ZY998). Currently there are 4 aircraft undergoing final assembly (LN 12 through LN 15) and parts of LN 16 are just starting to arrive in Everett. Flightblogger is reporting that Boeing planes to start increasing production on the 787 round mid February.
Flightblogger: Dreamliner Production Challenges Lie Ahead
Finally through today, January 10, 2010, the 787 test fleet has accumulated over 45 and half hours test flight hours. Also today, Za001 flew the longest 787 test flight thus far at 5 hours and 48 minutes. You can track the 787 flight test hours by going to this spreadsheet here.
Friday, January 1, 2010
Where are the 787s in the New Year?

Now that the 787 flight test program is well underway, let's update where the fleet is.
LN1 (ZA001) Boeing Flight Test Center, Boeing Field - in flight test
LN2 (ZA002) Boeing Flight Test Center, Boeing Field - in flight test
LN 3 (ZA003) Boeing Paint Hangar, Paine Field (completed Side of Body modifications undergoing fuel tank aqueous wash and painting)
LN 4 (ZA004) Building 40-24, Paine Field (Completed Side of Body modifications, undergoing reassembly after fuel tank aqueous wash and painting)
LN 5 (ZA005) In ATS Hangar
LN 6 (ZA006) In ATS Hangar
LN 7 (ZA100) Boeing Everett Flightline awaiting side of body modification
LN 8 (ZA101) Boeing Everett Flightline awaiting side of body modification
LN 9 (ZA102) Boeing Everett Flightline awaiting side of body modification
LN 10 (ZA103) Building 40-24, Paine Field awaiting side of body modification
LN 11 (ZA104) Building 40-26, position 4 undergoing final assembly
LN 12 (ZA105) Building 40-26, position 3 undergoing final assembly
LN 13 (ZA115) Building 40-26, position 2 undergoing final assembly
LN 14 (ZA116) Building 40-26, position 1 undergoing final assembly
LN 15 (ZA117) Building 40-26, position 0 parts arriving in preparation for Final Assembly
Monday, December 14, 2009
End of the long road for the 787
Boeing will stream the 787 first flight live on it's web site as well as the newairplane.com web site. But in the meantime, Randy Tinseth, speaking for Boeing on his blog says:
Let's Go!
Great sentiment that is obviously shared! In the meantime Flightblogger has put up a new post describing, in excellent detail, the taxi tests that occurred on Saturday as well as the progress to date as well as a second post describing the test flight regime that ZA001 will be undertaking over the next few months. ZA001 apparently has been fueled for it's first flight.
Read Flightblogger's reports:
Better Know a Dreamliner - Part One - ZA001
ZA001 stretches its legs
Additionally, ZA002 (Dreamliner 2) is progressing towards it's first flight with gear swing tests.
Liz Matzelle captured some great video of this gear swing test:
ZA002 Gear Swing Tests from Liz Matzelle on Vimeo.
Dreamliner 9 is heading to the paint shop at Everett. LN 10 through LN 13, as far as I know, are still in building 40-26 going through final assembly. ZA003 is also going through preps and I wouldn't be at all surprised to see this airplane flying next month.
Finally, Aviation Week has a whole section devoted to the 787 first flight as well as featured blog post from Guy Norris and Mike Mecham.
Aviation Week's Boeing 787 First Flight Special Report
787 Countdown to first flight (resumed) Part 7It's official: 787's First Flight is Tuesday
Boeing Sets Long-Awaited 787 First Flight
Friday, November 20, 2009
Flightblogger: 787 Fleet location
Flightblogger posted a great summary of where all the 787s are and the status of each aircraft
ZA001/LN1 : In paint hangar undergoing reassembly and should move to building 40-24 (767 line) this weekend to complete those reassembly tasks
ZA002/LN2 : Finish modifications and is in building 40-24 for reassembly tasks
ZA003/LN3 : In building 40-24 under going side of body modifications
ZA004/LN4 : At the ATS Hanger under going side of body modifications
ZA005/LN5 : On the Everett flightline awaiting it's turn for side of body modification
ZA006/LN6 : On the Everett flightline awaiting it's turn for side of body modification
ZA100/LN7 : On the Everett flightline awaiting it's turn for side of body modification
ZA101/LN8 : On the Everett flightline awaiting it's turn for side of body modification
ZA102/LN9 : At the ATS Hangar awaiting it's turn for side of body modification
ZA103/LN10 : In building 40-26 undergoing final assembly
ZA104/LN11 : In building 40-26 undergoing final assembly
ZA105/LN12 : In building 40-26 undergoing final assembly
ZA115/LN13 : In building 40-26 undergoing final assembly
ZA116/LN14 : Parts are arriving (horizontal stab and wings in da house)
Flightblogger : Getting Oriented
Saturday, November 7, 2009
2nd production 787 moved to flightline
Inside building 40-26, Boeing workers continue to put together 787s LN 9 to LN 12 (all for ANA). It is expected that LN 13 should be in the Everett factory very soon.
You can view Matt Cawby's picture by clicking here you can also view his video of the aircraft roll out here. Notice that this aircraft also does not have its engines attached yet. That will happen closer to the delivery time.
Tuesday, October 27, 2009
787 Round Up
Here is some more 787 news for your reading pleasure. BTW, LN 8 (ZA101) is reported by Flightblogger to be in the Boeing paint shop. This now clears the way for Boeing to start final assembly on LN 12 once that rear fuselage secion for that airplane arrives in Everett.
- South Carolina is upping the stakes for the 2nd 787 final assembly line as the the SC State Senate approved a deal to entice Boeing to locate the line to North Charleston. This comes on the heels of news that there hasn't been much progress in Boeing's talks with the IAM to keep the second line in Everett. Paramount of Boeing's concerns is the strike by IAM that have occurred every 3 to 4 years. Boeing is trying to negotiate a 10 year moratorium on strikes by IAM. I wonder if they forgot about SPEEA?
- A couple things from Flightglobal - First Mary Kirby reported that Boeing has let an RFP to equip the 787s with wireless Internet connectivity. The connectivity would be via satcom broadband and Boeing is aiming to have it integrated into the in flight entertainment system (IFE). Panasonic and many airline customers have been pushing for this for sometime and it seems that the technology has matured enough that Boeing is now making it a priority.
Boeing RFI for 787 wireless internet connectivity
- Also from Flightglobal, is news that airline executives from Polish carrier LOT will be talking with Boeing about LOT's 787 order. The delay to the 787 has hampered LOT's ability to open up new routes. I am swilling to bet that Boeing will give the same deal and assurances to LOT that they gave to Qatar Airways.
LOT Senior Management talks 787 with Boeing
- Lastly, a new book hit the bookshelves this week. The title of this book: Boeing 787 Dreamliner by Mark Wagner and Guy Norris. The book covers the development of the 787 from the ashes of the Sonic Cruiser through today's continued issues that Boeing is still facing. It's certainly to be an eye-opening and informative book on this aircraft.
Monday, October 26, 2009
Flightblogger: Boeing complete 787 detailed design of 787 fix
Flightblogger is indicating that given that Boeing has finished the detailed design and computer validation of the fix that they have overcome the load issues that were discovered last Spring. Flightblogger is saying the test results received thus far are looking good.
Flightblogger
In other 787 news, Fleetbuzzeditorial.com came out with some great pictures of the 787 final assembly line:
Fleetbuzzeditorial.com - ZA100 and ZA101 at Everett
Additionally, Fleetbuzzeditorial.com also put out an interesting piece about the 2nd assembly line for the 787. This line is going to be crucial for Boeing to meet it delivery obligations. Here the article addresses the issues of the 2nd line, the choice ahead for Boeing and the pitfalls facing Boeing.
Second Guessing 787 Second Line
Lastly, the LCF's continue to make regular runs between the 787 suppliers and Everett. The nose section , wings, main fuselage, horizontal and vertical stabilizers for airplane 12 (LN 12) are already in Everett and I do believe the rear fuselage section is also in there though I have no confirmation. There should have been a line move already or will happen soon so that LN 8 (2nd production aircraft) will be moved out of building 40-26 thus clearing the way for airplane 12 to start final assembly in the coming days. Thus far Boeing is looking to maintain a 1 airplane/month production rate and gradually ramping that up to 10/month by the end of 2012. LN 7, the first production 787 is already outdoor on the Boeing flightline sans the Roll Royce Trent 1000s:
ZA100
Wednesday, September 30, 2009
Flightblogger 787 Update
- James Albaugh visited Boeing Charleston. There is talk of Boeing applying for permits to start clearing land for the 2nd assembly line facility. This comes right on top of Washington's State proposal to Boeing to keep the 2nd line in Everett. Also there seems to be some surveying and construction equipment at the Charleston site.
- Flightblogger made a correction regarding when the first 787-9 while be produced. Earlier he said it would be the 109th airframe to come off the line (LN 109). It will actually be the 139th airframe according to the latest production schedule.
- Well the 787 backlog is shrinking but because customers are cancelling. The latest is TUI which cancelled 10 787-8 but took purchase rights on 13 air frames. Whoop Dee Doo. Flightblogger also lists out the threats to the 787 backlog from other airlines considering cancelling their orders. It's a very dangerous time for the 787. They need to get it the air real soon.
- Production - Dreamliner 11 sections should all be in be earlier next week allowing the 787 line to move forward. The wings for Dreamliner 12 will be bought in early next week and ZA100 (LN7) will be moved out to the paint hangar to get an aqueous wash and paint job. It will not have the side of body fix installed. That will be done later but there is access to the areas of the wing and fuselage in order to install the fix. Dreamliner 11 will start final assembly later next week.
Thursday, August 20, 2009
Flightblogger: Boeing preparing revised 787 plan
Flightblogger reveals that first flight for ZA001 may take place between late November and early December. This would equate to a five month delay to the 787 program on top of the other delays. First delivery to ANA would be 4th quarter of 2010. Boeing has yet to reveal it's schedule and should do so in about 5 weeks or so.
The Z18 document is intended to make sure that everyone (Boeing, suppliers, and even customers) are on the same page with regards to assembly production and delivery of each of the 787s that Boeing is committed to delivering including all financial considerations.
The wrinkles are not going to put a wrinkle in Boeing's 787 plan.
With regards to the wrinkle issue, Flightblogger says Boeing is applying the fix to the affected airframes while it has stopped winding fuselage barrels for airplane 30 on out. The permanent fix has yet to be developed though in my communications with Boeing it seems that they would need add additional plies to the affected areas when applying the composite tape before autoclaving the structure. The affected area is the stringer edge step. Until the permanent fix is determined, the resources in Grottaglie will be reallocated to preparing the 13 sections at that worksite for shipping to Global Aeronautica. This will accelerate the preparation of the existing barrels and when Boeing and Alenia are ready to start winding barrels for airplane 30 on out, those resources will be shifted back again to get that work flowing again. It looks like that there won't be any schedule disruptions due to the wrinkle issue.
Flightblogger also says that starting with airplanes 11, 12 or 13 Boeing and it's partners will implement NC 5 (for Net Change 5). This is a standardization of the structural, wiring and systems design across all the suppliers so that travelled work is kept to a minimum and commonality is maxed out when the parts arrive in Everett for final assembly.
It is here where Boeing is hoping (I believe) that there will be no more travelled work in the production system going into Everett and this would form the basis of the production ramp up. Flightblogger says that parts for airplane 10 (LN10) should start arriving at the end of this month. I would expect that airplane 4 and 5 which are in 40-26 would be moved soon to another location so that LN 7 and LN 8 can move down the line and LN 9 can start final assembly though this is be slowed until the side of body fix in installed and tested. Boeing still wants to modify as few planes as possible after the wing-body join.
Flightblogger: What is Z18?
Tuesday, April 7, 2009
Aviation Week: Trent 1000 getting closer to spec
The improvement won't show up until later this year when ZA004 will be outfitted with the improved engines. The production ready motors will be installed on the 12th 787 (ZA105 or the 6th production standard 787).
Read Jon's article here.