Showing posts with label ZA430. Show all posts
Showing posts with label ZA430. Show all posts

Sunday, November 4, 2012

787 now solidly at 5/month production rate. Chinese 787s into storage, LOT 787s delivery schedule clarified....a bit

Boeing has moved three 787s for two Chinese carriers into long term storage at Everett's South Ramp while a fourth 787 awaiting change incorporation is also being stored on a runaway parking spot.

Boeing has moved ZA380 (LN 34, B-2725) and ZA382 (LN 43, B-2727) bot h for China Southern Airlines as well as ZA430 (LN 73, B-2728) for Hainan Airlines into the South Ramp and has taped and sealed the aircraft to protect them until they are ready to be delivered. ZA381 (LN 36, B-2726) had been stored on the Everett's RWY 11/29 with other 787s awaiting change incorporation and will probably be there for some time until the issues with the CAAC are resolved. There are 7 other 787s that are in production or final assembly and I am not sure if those airframes will be reallocated or will be produced for Hainan and China Southern and then stored. It seems to me that it will be the former as buyer furnished equipment such as the engines and galleys have, at this stage, been ordered and delivered or will be delivered soon to Boeing's facilities in Charleston and Everett.  These items require lead time and Boeing did go ahead with production on the Chinese airframes even through the issues with China was not resolved.

On a brighter note, I received information regarding LOT Polish Airlines' 787 deliveries.  The first contractual delivery of ZA270 (LN 61, SP-LRA) is tentatively scheduled for November 9th.  This aircraft will remain in Everett for about 5 days for crew training before flying to Warsaw on the 14th.

Future deliveries flights of LOT's other 787s to Warsaw are scheduled as follows:

ZA271 (LN 78, SP-LRB) - delivery to Warsaw is in early January 2013 (probably contractual delivery in late December 2012)

The other three in production are to be delivered at monthly intervals during the first quarter of 2013 but they will all be waiting in Everett in storage which begs the question,why start producing them now when delivery is months away?  I don't have an answer for that, unfortunately.

In production news, Charleston is starting to move faster on production out put of 787s.  The 5th Charleston built 787 was moved out to the flightline within the last couple of days.  This is ZA241 (LN 72, VT-ANM) for Air India. This means that Boeing has achieved a 1/month production rate on the 787s at Charleston and a solid 4/month at Everett.. During the day today, Boeing sent ZA240 (LN 65, VT-ANL) to Ft Worth for painting and ZA239 (LN 60, VT-ANK) was flown back to Charleston to finish pre-delivery test flights.  It is rumored that Boeing will deliver ZA238 (LN 54, VT-ANJ) this week to Air India but there is still some uncertainty due to Air India's financing the purchases of the Dreamliner.

Boeing continues to work on the '87s at Everett that need re-work.  They had recently started change incorporation on ZA504 (LN 15) for ANA and this past weekend, they moved ZA234 (LN 30, VT-ANE) to the EMC.  Given the amount of re-work needed on these frames it'll be sometime around the first quarter of 2013 before this aircraft is delivered.










Friday, November 2, 2012

I'm Baaaack...but only for the moment - Post Sandy 787 Update

Hello everyone,
First off I want to thank you all who have sent me best wishes during the last few days. It's been difficult as I have no power, heat (temps are in the low 40s F overnight) and hot water (for bathing, cleaning, etc.).  I'm hopingto have power back in the enxt couple of days but we're not sure when it'll happen.  Right now I'm camped out in the local public library where there is WIFI (real slow due to all the residents who are also here), electricity and heat.  I'll put up a post but not sure when I will be able to do so again.

Anyway on to business.

Boeing had two quick deliveries on Halloween, let's call them "ghost deliveries" as they weren't expected.  In particular the delivery to United of its 2nd 787.  the information coming from United and even Boeing itself didn't indicate a delivery was imminent but they did deliver ZA290 (LN 77, N26906) on Wednesday.  United just announced that they have finished FAA certification of their 787 operations and now should be ready to start limited service on Monday, Nov. 4th. Boeing should still be able to deliver the two Dreamliners to the carrier in November.  These frame are re-worked frames so we would have to see how fast they would go through the pre-delivery and test flight process as ZA290 was a new build that didn't need any re-work and had only needed 2 test flights before being delivered to United.  It's not known when United will press ZA290 into service. 

The second airplane that was delivered was ZA511 (LN 63, JA816A) to ANA which is a reworked frame that had 3 test flights prior to being delivered.  For October, Boeing matched the monthly high of 7 deliveries which was achieved in September.

November as mentioned in the prior post may be big but there are issues that may depress deliveries.  First is the uncertainty over deliveries to the Chinese carriers.  There is a certification issue, rumor has it, with the Chinese aviation authorities (CAAC). 

When asked about it Boeing replied: "In keeping with our standard practices, we work with regulatory authorities in advance of local airlines taking delivery of a new model of airplane. Also, as we’ve stated before, we don’t provide forward-looking comments regarding the production or delivery schedules of our customers."

The issue with CAAC has been reinforced when Boeing put both  ZA382 (LN 43, B-2727) for China Southern Airlines and ZA430 (LN 73, B2728) for Hainan into storage at Everett's South Ramp.  This indicates that the issue will take some time to sort out.  Boeing has one more 787s for Hainan Airlines that is on the flightline but so far they have not made a move to store it...yet.  There are several 787s that are in production for both Chinese carriers.  In addition to the aforementioned airplanes that have flown or been pulled out of final assembly and on the flightline, there are 2 787s for China Southern that are in storage or in change incorporation.  At Boeing Charleston there are 3 787s in final assembly for Hainan Airlines and 3 more (all for China Southern) are to start final assembly at either Everett of Boeing Charleston by the end of the year or early January.  This is a total of 11 airframes that are potentially to be stored if the issues are not resolved with CAAC.

Boeing as of today has 14 airplanes that are in pre-flight, flight testing or ready to be delivered.  Rumor has it that ZA238 (LN 54, VT-ANJ) is to be delivered sometime next week to Air India.  It was to have been delivered last month and it is unknown as to why there was a delay but this is Air India. 'Nuff said.

Qatar Airways seems to be moving towards taking 2 more 787s in November though I'm still trying to get confirmation on this LOT Polish Airlines should take their first 787 in about 10 days as well.  That is 4 aircraft thus far.

Here is what I think will be delivered this month:

ZA261 - Ethiopian - 2 test flights already and flying a 3rd today
ZA286 - United Airlines - in pre-flight
ZA238 - Air India - ready for delivery
ZA289 - United Airlines - in pre-flight
ZA460 - Qatar Airways - 2 test flights thus far
ZA239 - Air India - 2 test flights and in paint
ZA270 - LOT Polish Airlines - 2 Boeing test flights thus far
ZA463 - Qatar Airways - 4 test flights thus far
ZA271 - LOT Polish Airlines - in pre-flight may deliver late this month or by end of December
ZA538 - LAN - in pre-flight and should fly soon

This is a total of 9 (with a possibility of 10) 787s being delivered this month.  Obviously I am not counting any of the Chinese airframes. It remains to be seen how those airframes that are currently in production will fare in terms of getting through pre-flight and being delivered by the end of the month but I can see one more airframe being delivered to ANA in November (probably the re-work frame) and one for JAL may also make it by the end of the month.

Boeing also has moved one of the "terrible teens" from runaway storage to the EMC to start chagne incorporation.  This aircraft is ZA504 (LN 15).  Right now this aircraft is listed to go to ANA but this may change.  ANother aircraft for Qatar Airways has completed change incorporation and paint is now spotted at the Everett Fuel Dock.  This aircraft is ZA462 (LN 62, A7-BCC).  Lastly, Boeig loaded ZA184 (LN 89, JA830A) into position 1 in the 40-24 surge line to start final assembly.  Boeing is keeping up the assembly rate at around 5 airplanes per month.








Monday, October 22, 2012

6 787s fly for the first time in 5 days

From Oct. 18 to Oct. 22 inclusive, Boeing took advantage of a break in the weather to fly 6 different production 787s on their B-1 flights.  The aircraft were obviously ready but bad weather forced a hold on all B-1 flights. Thus when the break came Boeing released the planes for flight.  However because of the delay, I expect that none of these airplanes will be able to be delivered by the end of the month.  It does potentially set up November as a big month for deliveries but there may be a knock on efffect as 787s that were scheduled for flights around this time will be pushed back to later this month and certainly into early November.

10/18/2012
ZA270 (LN 61, SP-LRA) - LOT Polish Airlines

10/20/2012
ZA430 (LN 73, B-2728) - Hainan Airlines
ZA290 (LN 77, N26906) - United Airlines

10/21/2012
ZA239 (LN 60, VT-ANK) - Air India

10/22/2012
ZA261 (LN 44, ET-AOP) - Ethiopian Airways
ZA460 (LN 57, A7-BCA) - Qatar Airways

In addition to the increase B-1 flights, there was a very noticable increase in follow on flights of other airframes that have already flown.  There included a C-1 flight for ZA238 (LN 54, VT-ANJ) which is expected to be delivered to Air India before the end of the month, hopefully). 

Given the increased activity, however, I do not expect a lot of deliveries in the next 8 days.  There are really 3 airplanes that are ready for delivery or will be ready for delivery.  There is a possibility of one more airplane that could be delivered this month but it only has an outside chance.

Ready or almost ready for delivery:

ZA537 (LN 74, CC-BBB) - LAN
ZA264 (LN 75, ET-AOS) - Ethiopian
ZA238 (LN 54, VT-ANJ) - Air India (only had one C-1 flight may need more)

The one airframe that might make it for delivery by the end of this month is:

ZA511 (LN 63, JA816A) - ANA

The last aircraft still needs to perform customer flights and I am not sure if it has completed all the Boeing test flights at this point even though it has flown twice.

It is apparent that if Boeing can maintain an aggressive flying schedule in November, they can have a lot delivieries in that month.  Much depends on the aircraft condition after completing final assembly/change incorporation as well as weather and the ability to work through the backlog of planes that are finished and need to go through testing.








Friday, October 19, 2012

Several 787s getting set for 1st flight

Boeing seems to be ready to fly several 787s on their first flights as well as continue flight testing several more in preparation for delivery.  As of today Boeing has delivered 29 planes to 7 worldwide customers.

There have been several Flightaware alerts for several 787s that are sitting at Everett and Charleston.

Yesterday there were several Flightaware alerts for several 787 B-1 flights.  Those that were  slated to fly were ZA460 (LN 57, A7-BCA) for Qatar Airways, ZA270 (LN 61, SP-LRA) for LOT Polish Airlines, ZA290 (LN 77, N26906) for United Airlines. However by the end of the day only ZA270 flew while the other two conducted taxi tests around Everett.  Today there were Flightaware alerts for 2 B-1 flights: ZA430 (LN 73. B-2728) for Hainan Airlines and ZA239 (LN 60, VT-ANK) for Air India, the later being the third Charleston built 787 which should deliver sometime around November.  As of now these 787s have not flown and have probably ran taxi tests around their respective airfields. I also expect that ZA261 (LN 44, ET-AOP) for Ethiopian should also take flight by sometime next week from Everett.  This is an indication that Boeing is trying to aggressively ramp up the delivery process once the airplanes have left the EMC or the assembly line.  I would expect that within the next couple of day that all these airplanes will fly as well as continued flight test activity from the airplanes that have already flown in preparation for delivery.  The big factor nowadays is the weather around Washington State which is keeping the airplanes grounded (today for instance).

Meanwhile production and re-work continues at a pretty good pace with ZA538 (LN 80, CC-BBC) for LAN and ZA289 (LN 55, N26905) for United Airlines both entering the paint hangars at Everett. Assembly continues to pace at a little over 4/month.  New airframes are being loaded in Everett at about 1 every week with the next one slated to load on Oct. 25.  There are currently two 787s that are ready for delivery one for LAN (ZA537, LN 74, CC-BBB) and one for Ethiopian (ZA264, LN 75, ET-AOS).








Wednesday, April 4, 2012

First SC built 787 to roll out at end of April, 787 production update

Boeing announced that the first 787 built in North Charleston will roll out of final assembly on April 27th. This aircraft, ZA237 (L/N46), is destined for Air India and should be delivered this summer. Even though it is rolling out it will probably go through a more extensive battery of ground and gauntlet testing as this is the first 787 built outside of Everett where most of the assembly technicians are new to building this aircraft. After gauntlet testing Boeing will conduct a B-1 test flight and then fly the aircraft to Texas where it will be painted. It will return to North Charleston to finish pre-delivery Boeing and customer test flights. I don't know if it already has the customer interior installed but that could happen just before painting but after flying the initial test flight. In case the test flight has uncovered any issues that need to be corrected, Boeing techs will probably want unrestricted access to any areas. Interior fittings like seats, galleys, and restrooms can get in the way.

Lastly, I updated the 787 production firing order with LN71-LN75. One slight change is that LN 63 which was going to be for Hainan Airlines is now going to ANA with Hainan now getting LN 73. I was able to get some information on where these particular airplanes will be built as well. These 5 frames are, for now, scheduled to go to Ethiopian (2 frames), Air India, Hainan, and LAN. Interesting no new first delivery frames in this lot.