Sunday, February 18, 2018

787 February 2018 Mid Month Report

Boeing is well on track to deliver around 10 to 12 787s in February.  Thsu far, Boeing has delivered 8 787-9s to customers including the last 2 787-9s on United Airlines' order of 25.  United now has the 14 787-10 left on their large 787 order left to be delivered. Air Canada also had its 25th 787-9 delivered (out of an order for 29) during the last couple of weeks.  Thus far Boeing has delivered 16 787s (all -9s).

One thing to note is that Xiamen Airlines apparently did not take delivery of its 5th 787-9 and is still at Charleston which engine covers still on but parked at the delivery center.  Their 6th and last 787-9 is still on Charleston flightline awaiting its first flight.  Hopefully I'll have a little more information as to the delivery delay and when it should finally deliver.

Boeing is also readying the first 787-10 for delivery around March 14th.  ZC004 (LN 656, 9V-SCA) has taken several flight tests, presumably to test not just the aircraft but the customer furnished equipment that Singapore has wanted installed in their -10s.  I expect that there will be a few filight tests since this is the 1st 787-10 being delivered and this is Singapore's first  direct 787 delivery (not counting Scoot, of course).

Production is moving at the typical pace with 7 Dreamliners rolled out and another 6 which have started final assembly.  Over the next few months we should see more 787-10s rolling out of Charleston all destined for Singapore followed by a short pause and then the GE powered -10s for Etihad and United should start to follow.  Speaking of the production of the -10, Boeing got approval from the FAA on the -10 production at Charleston in the form of the 787-10 production certificate.   This means that the production system and the support for production has met all FAA requirements.  All three 787-10 flight test aircraft are now at Charleston and I'm presuming that they will now undergo change incorporation and re-work at Charleston over the next 6 to 9 months in preparation for delivery to Singapore and United.

In the meantime, continue to browse through the 787 production spreadsheets for more information:

787 Spreadsheets

Tuesday, November 12, 2013

Another correction, JAL took delivery of the 100th Dreamliner (seriously this time)

There has been plenty of confusion as to who received the 100th Dreamliner but thanks to Greg, an eagle eyed reader of this blog we might be able to finally declare who the winner is:

Japan Airlines received the 100th 787.  It was ZA175 (LN 20, JA821J)

this aircraft was seen by Matt Cawby at the Everett Delivery Center on Nov. 5th and a Flightwaware alert popped up showing that this aircraft was to leave that evening for Tokyo.  The aircraft never left and was ultimately towed back to the flightline at Everett.

Since then Hainan Airlines took delivery of a 787, ZA434 (LN 85, B-2730) at Charleston and flew it to China so that left many assuming that this aircraft was number 100.

Then Greg found a posting on Boeing's New Airplane Flight tracker web site.  Boeing has delivered 101 787 as of November 8, 2013.  This can only mean that ZA175 was delivered as not other 787 except for ZA434 has been seen at the Everett Delivery Center or the Charleston Delivery Center.  Since ZA175 was at the EDC on Sept. 5 and ZA434 showed up at the CDC on Nov. 8th it should follow that ZA175 was delivered before ZA434.