Showing posts with label ZA006. Show all posts
Showing posts with label ZA006. Show all posts

Wednesday, October 8, 2014

Boeing rolls out the first 787 for American Airlines.



Boeing rolled out the first 787 for American Airlines on Oct. 6th.  The aircraft was originally supposed to be delivered in November is now slated for delivery on December.  It is on the 40-51 Ramp finishing up assembly activities followed by painting.


Around KPAE 10-7-14 (in the fog)
First 787 for American Airlines, Photo by MOONM
Additionally Boeing has finally delivered one of 3 787-8 flight test aircraft to a customer.  The Fuerza Aérea Mexicana (Mexican Air Force) took possession of ZA006, the last test flight aircraft. After undergoing extensive re-work and re-build, the aircraft was bought up to FAA certificate standards though I am not sure if it has it full passenger interior installed or not. The aircraft is at the Charleston Delivery Center and is supposed to fly away tomorrow Oct. 9th).


ZA006 at the Charleston Delivery Center, Photo by reader
Boeing 787 production looks to be in ok shape but it is taking quite a bit of time to deliver the 787 into customer hands. I have observed a continuing movement of delivery dates to the right of the schedule that at this point I think Boeing will deliver about 10 to 11 787s in October. This is not a bad number but it only gradually reduces the built up inventory. I examined the average number of days it took Boeing to get an aircraft from final assembly to delivery.  I took out outliers or aircraft where I did not have complete information. The results may surprise you:

February, 2014 - 114.8 days
March, 2014 - 117.6 days
April, 2014 - 126.4 days
May, 2014 - 112.4 days
June, 2014 - 206.5 days
July, 2014 - 141.4 days
August, 2014 - 117.7 days
September, 2014 - 127.5 days

These averages need to be put into proper context.  They include the 787-9 (from June on)  These early 787-9s had to go through change incorporation and required more build time compared to the 787-8 thus the number of days fro the start of final assembly to delivery were  higher for these airplanes and distorted the results. Here are the average number of days it took to build the 787-8:

February, 2014 - 114.8 days
March, 2014 - 117.6 days
April, 2014 - 126.4 days
May, 2014 - 112.4 days
June, 2014 - 125.6 days
July, 2014 - 121.1 days
August, 2014 - 117.7 days
September, 2014 - 118.4 days

As you can observe the average time it takes to build the 787-8 (this includes both Charleston and Everett) is fairly stable.  As Boeing get more familiar with building the 787-9 and the need for change incorporation goes away as well as the need for extensive time  to finish traveled work, we should see build times for both versions of the 787 go down to below 100 days.

There is still no known timetable when the stabilization of the production system will occur and it appears that Boeing is continuing to struggle with traveled work which has been the bane of the 787 program currently.  There has been flashes of hope for a 90 day rate or lower (start of final assembly to contractual delivery).  For example Boeing delivered a 78 to Tui Travel in 84 days from Everett and Charleston delivered a 78 in 86 day to Kenya Airways.  2015 should bring much required and welcomed improvements to the 787 production system.

787 Full Production Table

Sunday, October 5, 2014

Boeing 787 September deliveries end third quarter on a high note.



September Month End Review

Boeing delivered 11 787s in September thus ending the third quarter on a high note after a a slow start in July.  For the quarter, Boeing delivered 31 787s.  The yearly total thus far is 80 aircraft in 2014 (includes one aircraft delivered on Oct.1) and 194 since deliveries began a little over three years ago.

The target is still 110 deliveries in 2014 and they can easily make that with and average of 10 aircraft delivered a month for the next 3 months.  Earlier I had projected that Boeing can deliver around 120 aircraft.  Clearly that number can't be reached but they do have the ability to deliver between 110 and 122.  787s deliveries were lackluster in July but rebounded nicely in August with 13 deliveries and maintained a strong pace with 10 in September.

In terms of efficiency. Charleston delivered 3 Dreamliners and rolled out only 2.  That translates to and efficiency of .667 (the lower the number the more efficient the plant is.  The Everett plane had an efficiency rating of 1 (rolled out 7 and delivered 7).

Future Deliveries

Deliveries included 3 787-9 (one each to United, ANA and Air New Zealand).

Planned deliveries for October are looking to be on the order of 11 to 13 aircraft.  This includes the 10th and final 787-8 for Ethiopian that is company owned which was delivered on October 1st.  Ethiopian will be taking 3 or 4 more 787-8s on lease from AerCap over the next year or so.  Boeing should break 200 deliveries easily though it's difficult to speculate which aircraft/customer will have that honor.

Deliveries should include:

1 787-9 to Virgin Atlantic (expected around Oct. 6)
1 787-9 to Etihad Airways
1 787-9 to United Airlines
1 787-8 to Fuerza Aérea Mexicana (Mexican Air Force) (around Oct. 8th)
1 787-8 each to Avianca, Kenya Airways, Xiamen, Thai Airways (leased from AerCap), Royal Jordanian (leased from CIT Leasing), and Air Canada
2 787-8 to Qatar Airways

Of course much of this depends on the preparations and readiness of the individual aircraft to be delivered including undertaking ground testing and production flight tests s well as the readiness of the customer to induct them into service.  Of the aircraft mentioned in the above list, three have yet to conduct their B-1 flights.

Production




Etihad 787-9 on 40-51 Ramp. Photo Courtesy of Brandon Ferris




Japan Airlines 787-9 in the EMC. Photo Courtesy of Brandon Ferris

In terms of production, Boeing should start final assembly on 10 to 11 787s this month. 4 will start on on the main line in 40-26, 3 on the surge line in 40-24 and 3 to 4 on the Charleston line.  They should roll out 10 this month but it is key that current month deliveries exceed the number of aircraft rolled out in order to reduce the carried inventory.  Boeing had built up a large 787 inventory during the first half of 2014 that they are now trying to catch up to deliveries in the second half.  They did a good job in the third quarter but the 4th quarter will be critical in reducing it further.

Boeing is also aiming to move the aged inventory (test flight aircraft plus the early build 787s (terrible teens).  ZA006 will be delivered to the Mexican Air Force and ZA003 will be donated to the Museum of Flight in November.

Sales

In the meantime, Boeing is continuing with several sales campaigns which can yield some significant orders for the 787.  However late last month they booked a cancellation for 15 787-9 for Air Berlin as part of a cost cutting move.  Interestingly, at the same time Boeing booked an unidentified order for 15 787-9s.  It is widely believed that the unidentified customer is Etihad which will use the aircraft either for itself or for one of the partner airlines in which the carrier has a financial interest.  This is reinforced by the fact that Air Berlin didn't pay any penalties for the order cancellation because Etihad took up the order.  This cancellation may have ramifications for a another sales campaign that is currently on going.  It is expected that Virgin Atlantic will exercise 5 787-9 options and I wouldn't be surprised if they make that announcement when they pick up their first 787-9 from Everett on Tuesday.  Sir Richard Branson also indicated that he is interested in the 787-10 so we might even see a new 787-10 order from them on Tuesday but let's wait and see on that one.

The two big sales campaign are Delta's order for 50 widebody aircraft.  Delta has shortlisted the selection to the 787-9 and the A350-900 and this is where the Air Berlin cancellation may have an effect.  The cancellation frees up early delivery slots which can entice Delta to buy the -9.  However, with Etihad taking up the order it remains uncertain if they kept Air Berlin's delivery slots.  If not then Boeing may have a leg up on Airbus for this order.

The second major 787 order would be one from Emirates which Boeing has coveted for a long time.  With the success of placing an incredibly huge number of 777 (777-300ER and 777X) with Emirates, Boeing still wanted to get them signed on to the 787.  With Emirates' cancellation of their entire A350 order, which will now be competed with the 787 and the A350, Boeing has a tremendous opportunity to finally place the 787 with the only holdout of the ME3 that hasn't placed a 787 order.  The decision is expected to come sometime in the first quarter of next year but I suspect that Boeing will be very aggressive in the pricing vs. the A350.

787 Full Production Table

Friday, September 26, 2014

Adjustments to 787 delivery schedule for September

Looks like there's some adjustment to the 787 delivery schedule for September.  Looks like the delivery of ZA246 (LN 208, VT-ANR) is being pushed back a bit but there isn't a new delivery date on this as of yet.

Also the line move in 40-24 has been delayed as engineers try to work an issue on ZB005 (LN 236, ZK-NZG) which requires it to be back inside.  There isn't any word on when the line move will pule to allow the next aircraft to start final assembly.

Meanwhile ZA817 (LN 241, N800AN) for American Airlines is sitting in position 3 in 40-26 still waiting for its engines to be attached.  There is some unknown issue and the first 787 for American won't have them hung until next week.

ZA003, the third 787-8 test flight aircraft, was also flown to Boeing Field earlier today as it is going to be prepared for display at Seattle's Museum of Flight.  No word on the fate of the other two undeliverable test airplanes but I wouldn't be surprised if they end up in Museums as well.  I doubt that they would be exhibited with actual engines as that would be expensive.

At this rate it does appear that Boeing will not make 10 deliveries this month and may have to settle for 9 or fewer.

Lastly, some anonymous readers have sent me pictures of ZA006 on the Charleston flight line and I'd like to share them with you.

Photo by Anonymous

Photo by Anonymous

Photo by Anonymous

Photo by Anonymous

Photo by Anonymous

Photo by Anonymous

Photo by Anonymous


787 Full Production Table

Wednesday, September 24, 2014

First pics of ZA006 in Charleston

Thanks to John C. Evans, a local aviation enthusiast in Charleston, we have a couple of photos of ZA006, the last test flight aircraft that was sold to the Govt. of Mexico and will be the first 787 to be flown by a government military though in support of government VIP travel.

Again a big shout out to John Evans!

Photo Courtesy of John C. Evans

Photo Courtesy of John C. Evans

Tuesday, September 16, 2014

Mexican Air Force to take delivery of test 787 at the end of September

As previously reported here on All Things 787, the Mexican Air Force had purchased ZA006 for use as a government transport.  when delivered it will mark the first 787 to be purchased by a government armed services.

Currently the aircraft is in New Iberia, LA. where it is probably getting a paint job and having some other work performed on it in preparation to convert it into a government transport.It is scheduled to fly to Charleston on September 22nd where it will be in stall A4 for a few days.  It will then transfer over to the delivery center at Charleston on the 25th of September and will be there until it flies away around September 28th.  It's been reported that Mexico paid $127mm for the aircraft which performed flight testing duties with the GEnX-1B engines.

Spotters at CHS, please be on the look out for this aircraft.  I'm sure a lot of people would like to see what kind of livery it will have.

Saturday, August 9, 2014

ZA006 flying again

ZA006, one of the 6 787-8 that was part of the test flight program appears to be flying according to both Flightaware and Flightradar24.  The aircraft has been at Lackland Air Force Base for about 2 years first being stored and then undergoing change incorporation and refurbishment in preparation to delivery to the Mexican Air Force for use as a VIP transport.  There's no word on delivery though it is thought that it will be delivered towards the end of the year.  Right now it appears the aircraft is doing engineering flights to verify and test the aircraft after the refurbishment.

Friday, October 18, 2013

787 test aircraft possibly moving to change incorporation to prepare for delivery

ZA005, Boeing first 787 powered by GE's GEnx-1B engines looks to be done with its career as a Boeing test aircraft testing PIP for the these engines.  Matt Cawby tweeted yesterday these two tweets:



It appears that Boeing is preparing ZA005 for its second career with a paying customer, possibly a BBJ customer, by starting change incorporation at the EMC.  It will have to have the orange test flight wiring removed and be bought up to certification specs which may take as long as a year or more.  Its sister ship ZA006, also GE powered, has been in San Antonio, ostensibly going through change incorporation as well but has been there for well over a year.  This may indicate that Boeing doesn't have a customer for it as of now and are going slow on the change incorporation.

ZB002 still on the flightline, has open panels and doesn't have the aircraft registration applied to it.  This indicates that the aircraft is not yet ready to fly but I still anticipate that it will fly towards the end of next week.

Lastly, I'd like to leave you all with a the  profound thought of the day:



Full 787 List

Current 787 Production List

Delivered 787 List

787 Monthly Delivery Tracking

787 Customer Delivery

787-9 Flight Test Hours

 








Thursday, January 3, 2013

787 Looking Back and Looking Forward: Part 2, 2013 Look Ahead

Now that Boeing has put to bed a very successful 2012 which includes regaining the title as the top commercial aircraft producer (thanks in part to the 787 deliveries that exceeded forecast), what is in store for the Dreamliner program in 2013?

There are several milestones for the 787 program coming up in the year.  Among those are:

787-9/787-10
Assembly and 1st flight of the first 787-9.  Assembly should start around early June and I anticipate that aircraft will be out about 1 month later to begin gauntlet testing in the run up for first flight in late summer or early fall. I expect Boeing to have 3 airplanes flying the certification testing and will be refurbished and delivered to customers after the planned 6 month test flight program is concluded.  Boeing is still aiming for first delivery to Air New Zealand in mid 2014.

Launch of the 787-10 variant with significant orders from major Boeing customers which may include British Airways, Qatar Airways and others.

Production and Delivery
Boeing had executed extremely well on its plan to increase 787 production from 1.5/month to 5/month at the end of the year.  Boeing's plan for production in 2013 was laid out in a conference call to investors. The plan is for Boeing to maintain the current 5/month rate through the middle of 2013 (end of June, perhaps) at which point they will break rate and go to 7/month and finally break rate again in late 2013 to the final 10/month rate.

How many can Boeing build in 2013 and how many they can deliver are two different numbers.  There is a lag between the break in rate and when the first aircraft assembled at the new rate is delivered.  Thus it is a couple of months before the increase in production rate translates to an increase in the delivery rate. 

Production Forecast:
Thus for the production rate Boeing would see a build rate of 30 787s for the first 6 months of 2013 (5/month for 6 months), followed by a build rate of 35 787s for the following 5 months (7/month for 5 months). Followed by a build rate in December of 10/month. Therefore, this total indicates that Boeing is capable of assembling a total of 75 787s during 2013.

Delivery Forecast:
I am going to attempt to quantify Boeing deliveries for 2013 but I have to make certain assumptions:

1) Boeing will produce at a rate of 5/month through June, 2013 then break to 7/month starting in July, 2013 and maintain that through November 2013.  In December 2013 Boeing will move to 10/month.  This is based on currently available information.

2) I'm assuming that there would be 9 week lag between the break from 5/month to 7/month, therefore the first 787 to deliver at 7/month would be in September, 2013.  Even though there is a break in production rate in December to 10/month this rate won't translate to a 10/month delivery rate until 2014.

3) The numbers don't account for production of 787-9s for testing purposes.  I am only looking at deliveries of 787s to customers in 2013.

4) As a point of reference, the first 787 for Royal Brunei Airlines is expected to be delivered around September 1, 2013 according to the airline.  I am assuming that September will be the first month of 7 Dreamliner deliveries from the final assembly lines.

5) Since I don't have the firing order for L/N 131 and beyond I am assuming the following deliver rates for the remainder: 4 aircraft in September and 7 each in the last three months of 2013.  This is a total of 25.  L/N 128 to L/N 130 will assumed to be delivered in September as well for a total of 7 aircraft delivered in that month.

6) Boeing will deliver 12 787s that will undergo change incorporation but this number may grow to 15.  As of January 1, 2013, Boeing has 26 787s that are under going or will under go change incorporation in preparation for delivery to customers.  This includes the last three test 787-8 (L/N 4 to L/N 6 with the last one already well into the change incorporation cycle.

7) I am assuming that all 787s earmarked for the Chinese carriers thus far will be delivered in 2013 (deliveries to start in March). I am also assuming that L/N 6 and L/N 17 will deliver but the customers are unknown at this time.  L/N 17 was originally earmarked for Royal Air Maroc but will be delivered to another 787 customer instead.

Given these assumption let's break up the deliveries between aircraft coming straight off the final assembly line and those that still require re-work through the Everett Modification Center or in San Antonio.

I am projecting that Boeing can deliver 76 787s from all three final assembly lines during 2013. As a point of reference, the first 787 for Royal Brunei Airlines should enter final assembly around late July and deliver about 2 months later in very early September.  I am projecting that from September to December that the delivery rate will be 7/month.

For the rework airplanes, I am projecting 12 787s that are going through the EMC and San Antonio (ZA006) will be delivered in 2013 but Boeing may be able to squeeze 3 more (ZA230, ZA231, and ZA115) if the modification process becomes more efficient.  Boeing is now going to work on 787s that need more time at the EMC due to all the re-work that has to be performed. The tables below summarizes my projections:






Disclaimer
While I try to be as accurate as I can the projections are my opinion and actual delivery numbers more likely differ from my estimate.  There are unforseen issues that can crop upo similar to the issues that held up deliveries to Air India, Qatar Airways and the Chinese carriers.  Additionally, labor strife may once again become a hinderance to deliveries this year if the engineers of SPEEA go on strike.  Word is that a strike may be authorized in Februrary.  Boeing and SPEEA are to go back to the Federal Mediator on January 9th to try and come to an agreement.  If one isn't forth coming then the strike will severely slow down production of all Boeing jetliners as well as significantly slow down the testing and certification of the 787-9.  Boeing can make up some work by using managment engineers but it won't be enough to fill the void. The other issue is the need to manage the production rate increases carefully.  2012 showed that Boeign can do this but they were very measured in their approach last year.  In 2013 Boeing will be more aggresive with the 787 rate increase (two rate jumps from 5 to 7 and then from 7 to 10) and any issues can mean serious trouble not unlike the production snafus in the late 1990s.

Boeing ended 2012 on an excellent note by regaining it's former position as the top commercial aircraft producer (thanks to the 46 787 deliveries).  Boeing is poised to continue that dominance but there will be issues that Boeing will need to resolve if 2013 is to be more successful in 787 deliveries than 2012.  We'll see how it tuens out.









Wednesday, December 21, 2011

Possible Delivery Delay for GEnx powered 787?

Given that the delays to the 787 for ANA are well documented, Boeing is pushing hard to get three more Dreamliners into the hands of the airline before the end of the year. The revised delivery schedule for this month shows that ZA116 should deliver around Dec. 27 with ZA104 and ZA102 delivering on Dec. 30th. Of course this is all subject to change.

The knock on effects maybe felt to the GEnx powered 787s. Let's review first. Boeing has flown almost all the test points for FAA certification of the GEnx-1B powered version of the 787. The remaining test points that need to be completed is functionality and reliability testing and ETOPs testing. Now Boeing completed some of this testing on the flight test version of the aircraft but the FAA requires that some portion of this testing to be done on a production version of the plane. Boeing has assigned ZA236 (L/N 35, VT-ANH). When Boeing ran the F&R/ETOPs testing on the Trent-1000 version of the airplane it was done on ZA102 (which is being prepared for delivery) and lasted about 300 hours.

I am assuming that Boeing will have to fly a similar number of hours for the GE powered machine but some of those hours have been done on the test flight birds (ZA005 and ZA006). It is unknown how many more hours will be needed to finish certification testing.

ZA236 has yet to fly and it seems that resources have been diverted from preparing this airplane for flight to preparing the three aforementioned ANA 787s for delivery. Flightblogger had reported that Boeing was to fly ZA236 by the middle of this month but it's now looking that it will be later this month. For the Trent-1000 version, Boeing conducted the 300 hour F&R/ETOPs over a 51 day period during this past summer. Assuming that Boeing has to only fly half that amount (150 hours) with ZA236 (with the rest already done by the test aircraft) which means about 3 to 4 weeks of flight tests and that testing starts soon after the New Year, the test program can wrap up around the end of January. Figure a couple of weeks before the FAA issues the amended type certificate (middle of February) then deliveries can take place start in middle to late February. This is assuming that there aren't any production issues holding up these airplanes and no unexpected issues that are revealed during the final F&R/ETOPs testing.

Boeing's delivery forecast for the GEnx-1B was very early 2012 (January) and internal documents up until last week had Boeing delivering the first to Japan Airlines in January 2012. This is now not the case as the situation is still very fluid.

Thursday, December 1, 2011

787 update 12/1/2011

With all the excitement over yesterday's Boeing-IAM contract extension, there wa also news about the 787 that has come out and I would like to recap here.

787-GEnx certification

Boeing is still about 95% complete with 787-GEnx-1B certification testing according to Jim Albaugh who spoke at a Credit Suisse conference in NY yesterday. Certification testing using ZA005 and ZA006 are more or less complete according to Flightblogger, in a post on Nov. 29th. Additionally, he reported that ZA006 is getting some test equipement removed pior to be sent to San Antonio for refurbishment into a customer aircraft. If the change incorporation being done on production aircraft is any indication then this work on ZA006 is likely to take quite a bit of time to complete.

Boeing has done some of the F&R testing on the test aircraft but has to do the rest on a production standard aircraft. The 787 that has been tasked for this work is L/N 35 which is a 787 to be delivered to Air India. According to Flightblogger, first flight of this airplane has been delayed to around the middle of December owing to the slower pace of change incorporation on the 787s. Because of the delay in getting the needed aircraft, delivery of the first GEnx-1B 787 has slipped to January of 2012. The first one will be delivered to Japan Airlines, probably L/N 23, ZA177 which just returned form San Antonio after undergoing change incorporation work. Just yesterday the GEnx-1B engines received it ETOPS 330 certification however both the Trent and GEnx engines in combination with the 787 airframe won't be certified for ETOPS 330 until a fix to the fuel monitoring software is implemented, tested and certified by the FAA.

ZA004 - Trent Package "B" testing

According to Guy Norris, Boeing has completed certification testing for the Trent 1000 package "B" improvements for the 787. This will allow Boeing to finally start to deliver 787 with the new Trents which bring the specific fuel consumption to within 1% of the original promised specs. Boeing had undertaken this testing using ZA004. Over the last few weeks this airplane has been flown several times a day in order to finish up all the requirements. Once the FAA has received and approved all the test data, Boeing should be able to start delivering 787s with this engine. L/N 31 will be the first 787 to be delivered with the package "B" Trent 1000 engines.

Future deliveries

The pace of deliveries is obviously being didtaced by the pace of change incorporation which is excrutiatingly slow right now. The pace has already pushed the GEnx 787 deliveries out to January as well as deliveries to Trent 1000 customers further to the right. ANA was supposed to have received 5 787 in December...it will only receive two (L/N 31 and L/N 41). Both these airplanes are Trent 1000 package "B" airplanes. There are two other ANA 787s that have their engines attached and being prepped for delivery. These are L/N 9 (ZA102, JA804A) which was just pulled out to the Everett fuel dock and L/N 42 (ZA105, JA808A) which is still in front of the EMC.

These airplanes are not due to be delivered until after January 1st but there are now more 787s appearing on the flightline in preparation for delivery which is a good sign but on the flip side most of the aircraft that are out on the flightline are very early build airplanes that need extensive re-work done before they can be delivered to customer. Just to get these 11 airplanes (L/N 7 to L/N 19) done would probably take a good 2 years. Most of the deliveries will come from the late builds, particularly L/N 30 on up.

Production and Ramp Up

Jim Albaugh gave a nice update on the status of 787 production and ramp up. Currently they are are still at producing at 2.5 787 per month with the aim of ramping to 3.5 by around March or April and then to 5 by the end of 2012. Boeing is still maintaining it guidance of 10 787s per month by the end of 2013.

Albaugh had very good things to report about the North Charleston plant. The first aircraft from that line should deliver before June of 2012. The plant is capable of producing 2.5 787 per month right now. Boeing has now opened up the delivery center as well as the 787 interiors fabrication plant to supply bins, partitions, crew rest areas, etc. for the Charleston built 787s.

Test Flight Fleet

Now that test flights are nearing the end (at least for the 787-8), Boeing is starting to make plans for the first three airplanes built. ZA004-ZA006 will be refurbished and sold to customers (BBJ). Boeing has flown ZA001, the first 787, to Palmdale Airport where it will be in storage until they figure out which museum to house it in. Likely candidates are the Museum of Flight in Seattle or the Future of Flight museum in Everett though I wouldn't count out the NASM (National Air and Space Museum) in Virginia out. ZA002 is going to be in Charleston, SC for some time for testing purposes but its long term fate is unclear. ZA003 is due to start a 6 month tour of the 787 on December 5th. First stop is China an other Asian and African countries whose airlines have bought the 787. After the tour is completed the aircraft's long term fate is also undecided. No doubt there would be some testing to be done, particularly on engine and airframe improvements to lower weight and increase fuel efficiency and reduce the noise footprint. This is why ZA002 and ZA003 will probably held by Boeing for the foreseeable future to serve as test beds for these improvements.

Monday, November 14, 2011

787 production continues; Boeing draw first blood in Dubai

With Dubai 2011 underway, Boeing has drawn first blood with a huge order from Emirates.

But first some 787 tidbits.

Boeing sent two of it's 787 test planes on international marketing trips. ZA001 is flying to various 787 customer destinations to show the aircraft around the world. First stop is New Zealand where Air New Zealand is to induct the first 787-9 into it's fleet in a little over 2 years from now. It will go on to Australia from there where Jetstar and QANTAS will take delivery starting in 2013. ZA003 is now flying with a full passenger interior with the test workstations and other flight test equipment removed. It also is sporting a new paint job which is a hybrid of the Dreamliner livery that Boeing painted on ZA001.

Meanwhile, back in Boeing has pushed another 787 out the door and has reallocated several 787 to other airlines. L/N 50 and L/N 51 are currently on the final assembly floor and each has been reallocated to United and ANA respectively . They were to have gone to Ethiopian and LAN but were changed for unknown reasons. With the start of assembly on L/N 51 Boeing is on it's way of 2.5 787s per month with the target of 3.5 to occur sometime in early 2012.

One of the early build 787s appears to have completed the change incorporation and re-work. That airplane is L/N 23 (ZA177) which is destined for Japan Airlines. The aircraft took a check test flight on Nov. 11th and was ferried back to Everett on the 13th. It still does not have a customer interior but that work will be done in Everett along with testing of the interior and then Boeing and customer test flights prior to delivery. Given that work, Boeing can deliver this plane to JAL by the end of December or early January, 2012 depending on the remaining certification activities that need to be completed on the GEnx-1B powered 787. I am still maintaining my short term view that Boeing should be able to deliver 6 more 787 in December (no November deliveries). Most if not all these deliveries will be later production airplanes for ANA with a later production GEnx airplane added in.

Speaking of which, ZA006 continues F&R and ETOPS testing. Last word from Boeing was that GEnx-1B testing was 95% complete so I do anticipate that Boeing can complete all certification testing by the end of this month will the aim of having first delivery by the end of December to either JAL or Air India.





Dubai 2011


The Dubai Air Show got of to a bang with a huge order by Emirates for 50 777-300ERs. The bang not only came in the size of the order $18bn at list prices, or the fact that this is Boeing's largest commercial aircraft order by value or that it will make Emirates the largest user of the 777. The big bang came in the message this order sent to Airbus. It has been no secret that the market really hasn't accepted the A350-1000 as a viable competitor to the 777-300ER. The market response after launching the A350 coupled with the feeble attempt by Airbus and Rolls Royce to improve the aircraft earlier this year and the 2 year delay (with possibly more delays to come) has angered customers for the airplane, namely Qatar and Emirates. Thus this order at the start of the airshow was meant as a message to Airbus about the status of the A350-1000. Additionally, the A350-1000 is barely a better airplane than the Boeing offering but with the proposed 777-8X/9X (on which Emirates has been working closely with Boeing) thus this latest order would allow Emirates to easily introduce the next iteration of the 777 as this latest order is delivered towards the end of the decade. I wouldn't be surprised if Emirates has a conversion feature in the contract that allows them to convert to the newer model after Boeing launches the airplane with delivery aimed for 2020.


Airbus did get into the order column with an order for 50 A320NEOs from ALAFCO. This same lessor announced today that they sold 6 or their 787 orders to Oman Air. So this order with Oman is really a non-order order. Boeing is still adding more MoUs for the 737 MAX. The count is 700 airplanes spread across 9 customers with only American Airlines the only named customer of those 9. I don't expect any of these MoUs to be firmed before the end of the year but most if not all should be firmed by the end of 1st quarter 2012 in addition to any new customers that would have signed on by then.


Dubai 2011 Totals


Airbus


ALAFCO - 50 x A320NEO (+30 options)

Boeing

Emirates - 50 x 777-300ER (+20 options)

Monday, June 27, 2011

Boeing starts 787/Trent 1000 F&R and ETOPs Testing

Boeing announced the start of F&R/ETOPs testing today. The sole aircraft that is conducting the tests, ZA102, kicked the testing off yesterday with a seven hour and thirty minute flight along the west coast of the US. This airplane will be conducting all the F&R and ETOPs testing with the Trent 1000 engine.

This phase should last about 300 flight test hours after which Boeing should receive type certification and can proceed with deliveries to ANA around August or September. Given the amount of testing and allowing for maintenance, I anticipate that this final phase of testing should last about 45 days which means a mid August completion for the final phase of testing.

Boeing will still have to submit any remaining deliverables to the FAA and EASA and they would take at least a couple of weeks to issue the final type certification for the 787. Therefore, it is looking like an early to mid September delivery time frame for the 787 to ANA.

F&R is testing that measures the production aircraft's response to normal as well off-normal operations which would include simulated engine and systems failures. This testing is only to certify the Trent-1000/787 engine airframe combination.

Boeing is still in discussions with the FAA regarding F&R/ETOPs testing for the GEnx version. Until those discussions are completed it is unknown which aircraft(s) with the GEnx-1B engines will be used for those tests. It is anticipated that GE F&R/ETOPs should start around August. Given this time frame the GEnx powered 787 should be delivered to Japan Airlines around October.

Meanwhile Boeing is still using the other airplanes for testing purposes. ZA001 just returned from Europe and the Paris Air Show and will be spending a week at Boeing Charleston as workers prepare to load the first 787 into the tooling fixtures at that plant. ZA002 will be making the trip to Japan for service ready validation operational validation. That airplane will be there for about a week conducting those tests. ZA003 is conducting Boeing test flights to evaluate the hybrid laminar flow control system proposed for the 787-9. ZA004 is conducting nautical air miles tests (NAMS) using the package "B" Trent 1000 engines. This testing will be used to evaluate the improved fuel efficiency over the package "A" Trents. ZA005 and ZA006 will continue certification flight tests with the GEnx-1Bs.

Here's Boeing Press Release on the start of F&R/ETOPs:


Boeing Begins Final Phase of 787 Flight Testing


EVERETT, Wash., June 27, 2011 /PRNewswire/ -- Boeing (NYSE: BA) yesterday started Function & Reliability (F&R) testing and extended operations (ETOPS) demonstrations on the 787 Dreamliner. This is the final phase of flight testing prior to certification of the airplane.

"We are ready for this final phase of flight testing," said Scott Fancher, vice president and general manager of the 787 program. "The team has created a solid plan for accomplishing the hours and test points required for F&R and ETOPS testing in support of delivery to our customer ANA in the August to September time period."

F&R testing simulates various normal and non-normal operations for the airplane, in a realistic airline-like flight environment. ETOPS refers to extended operations – for twin jets, flights that are more than 60 minutes away from a suitable landing field. During ETOPS demonstrations the company validates the airplane's ability to safely divert for a variety of reasons, including long diversions with one engine shut down.

In addition to F&R and ETOPS testing for the 787 with Rolls-Royce engines, Boeing continues certification testing on 787s with General Electric engines and will conduct a separate F&R/ETOPS test program for that version of the airplane. Other activities will continue on the flight test fleet to support Boeing objectives including examining potential technologies for the 787-9 and testing engine improvement packages.

Sunday, June 19, 2011

787 test flight fleet done

On the eve of the Paris Air Show, James Albaugh. President of Boeing Commercial aircraft, revealed that Boeing is done with 97% of the required testing on the Trent 1000 powered and that the Boeing test flight fleet ZA001- ZA006 would not be flying for certification purposes. Boeing still has to complete SROV activities in Japan early next month as well as start ETOPs/F&R testing using ZA102 (LN9) for the Trent-1000 engines.

It is unclear which GEnx powered 787 will be used to conduct the ETOPS/F&R testing for the GEnx version of the 787 though ZA177 a GE powered 787 is still in change incorporation and maybe a possible candidate to conduct those tests around August or September depending on the progress of its change incorporation. If not then the only option is for ZA005 or ZA006 to conduct those tests.

ZA102 was supposed to start F&R testing in early June but as of today it still has no started and now Boeing is saying late June for the start of testing. I have no word from sources as to the actual start date thus far.

Even though Boeing's 787 test flight fleet certification duties are over, their flight testing duties are on going with ZA004 undertaking NAMS (nautical air mile) testing with the package "B" Trent 1000 engines. ZA003 is testing the hybrid laminar flow control (HLFC) which, it is hoped, will reduce drag by delaying the transition of laminar air flow over the horizontal tail plane to turbulent air flow. If these tests are successful, then it is planned to introduce this system on the HTP for the 787-9 and possibly to the 787-8 as well. ZA001 will fly to Paris for the air show then on to Warsaw and Berlin for marketing related activities with Air Berlin and LOT. As mentioned earlier, ZA002 will be dispatched Japan for Service Ready Operational Validation Testing.

Below is the schedule for the SROV tests with ANA in Japan:

Flight 1 LV. SEA 7-3-11 5AM ARR. HND 7-4-11 6:30AM
Flight 2 LV. HND 7-5-11 6:30AM ARR. ITM 7-5-11 7:30AM
Flight 3 LV. ITM 7-5-11 11:30AM ARR. HND 7-5-11 12:30AM
Flight 4 LV. HND 7-6-11 6:30AM ARR. KIX 7-6-11 8:00AM
Flight 5 LV. KIX 7-6-11 12:00PM ARR. HND 7-6-11 1:30PM
Flight 6 LV. HND 7-7-11 6:00AM ARR. OKJ 7-7-11 7:30AM
Flight 7 LV. OKJ 7-7-11 11:00AM ARR. HND 7-7-11 12:30PM
Flight 8 LV. HND 7-7-11 3:00PM ARR. HIJ 7-7-11 5:00PM
Flight 9 LV. HIJ 7-7-11 7:00PM ARR. HND 7-7-22 8:30PM
Flight 10 LV. HND 7-9-11 1:00PM ARR. SEA 7-9-11 6:30AM

Monday, March 7, 2011

Ch...ch...ch...changes



ZA177 in San Antonio for Change Incorporation (Boeing Photos)



After flying ZA177 (LN 23 for Japan Air Lines) down to San Antonio (Lackland Air Force Base) last week, Boeing is now ready to start the process of change incorporation into the built 787s as well as incorporating the needed changes back into the supply chain.

First a little background. Throughout the testing and certification program (either ground test or flight tests) for the 787, Boeing and the FAA identified changes that needed to be made to the 787s in order for them to be certified to carry passengers. These changes can be numerous and each task can take anywhere from a few minutes to weeks to complete. The added complexity is that each task has to be undertaken in a certain order so as not to duplicate any disassembly tasks as well as not to cause any damage to the aircraft. The airplanes will not receive the customer interiors (seats, galleys, IFE, etc.) in San Antonio. That work will be done in Everett after the change incorporation process is completed.



Boeing said that a total of 6 787s will go through change incorporation in San Antonio including the last 3 787 flight test aircraft (ZA004, ZA005, and ZA006) which will be refurbished for delivery to unannounced customers. Boeing has not identified the other production 787 that will undergo change incorporation in San Antonio but has said that they send additional 787 to San Antonio for change incorporation work as they see the need. The other airplanes that are not flown to San Antonio will have work done at Everett. Currently Boeing has 35 787s assembled or are in the process of final assembly bu change incorporation will only occur on LN 4 and later. Currently that is 32 airplanes. As modifications are identified and the detailed engineering and design changes are finalized, they will be incorporated back though the final assembly process and into the supply chain (at least that's the plan). It is not known how long each aircraft will take in change incorporation. Here's Boeing's press release:
Boeing Begins Change Incorporation Work on 787 Dreamliner

787 program continues steady progress toward certification and delivery

EVERETT, Wash., March 7, 2011 /PRNewswire/ -- Today, Boeing (NYSE: BA) began change incorporation work on the 787 Dreamliner at Boeing's Global Services & Support site in San Antonio, Texas. Airplane #23, the first 787 to undergo change incorporation, on Friday flew from Everett, Wash., to San Antonio on a ferry flight. During change incorporation, airplanes that are not part of flight test are configured to conform with the standards established as part of type certification efforts. Refurbishment of three of the six 787 flight test airplanes also will take place in San Antonio after completion of flight test activities.

"The 787 team is thrilled to have the expertise and enthusiasm of the San Antonio team focused on getting these airplanes ready for delivery to our customers," said Scott Fancher, vice president and general manager of the 787 program.

The current plan is for six Dreamliners to complete change incorporation and refurbishment in San Antonio. Three will complete change incorporation and three airplanes will be refurbished after flight test is complete. However, the plan is flexible and could accommodate additional 787 production needs as flight test is completed and airplanes are prepared for delivery. The work will be performed from March 2011 through 2013.

"We continuously look for ways to leverage the strength of the Boeing enterprise, taking advantage of the team and the skills we have across the company," said Fancher. "San Antonio specializes in modification work and has the capability and capacity to get the job done. The team was a natural choice."

Some of the work done in San Antonio will include installing electronic and mechanical equipment, completing software upgrades, testing functional systems, and removing and reworking wiring or equipment that needs to be updated to current configuration requirements. Approximately 450 employees will be hired on a temporary basis to join with 1,700 experienced workers at the site to complete the work.

"Everyone on our team is excited to join the 787 program," said Kevin Devine, vice president and general manager of the San Antonio site. "This airplane is about as advanced as you can get and there are high expectations tied to this work package. I am confident that our team will get the job done."

Currently, there are about 1,500 employees at Boeing's San Antonio site performing maintenance and modification work on the following programs: KC-135 Programmed Depot Maintenance, KC-135 Global Air Traffic Management, C-17 Globemaster III Sustainment Partnership and the C-130 Avionics Modernization program.

There are other changes coming to the 787 flight test fleet...actually just one airplane. ZA004, which was to have the package "B" Trent 1000 engines installed last month will now have those engines installed between March 18th and April 6th.


Lastly, the 787 flight test fleet went over the 3,100 flight test hour mark yesterday when ZA003 completed a 2 hour and 10 minute test flight. It is epected that ETOPS testing should begin late this month and carry on into July.

Tuesday, January 25, 2011

Guy Norris: ZA005 heading to Puerto Rico

As I had mentioned earlier, ZA005 is flying to Aguadilla, Puerto Rico. At the time I wasn't sure what the test objectives are for ZA005 but Guy Norris has revealed that it is heading down to the Caribbean to undertake take off and landing tests. Boeing had the aircraft in New Mexico the last couple of days doing take off and landing tests at high altitude airport in Albuquerque. The airport at Aguadilla is at sea level.

Guy also goes into a flight test fleet update and states that ZA003 should be flying very soon as well. ZA006 is undertaking ground tests and should be flying again soon though no date is evident.

Guy Norris: Tropical Test for 787

787 Round Up

With Boeing's earnings call schedule for tomorrow, it is expected that there will be a lot of questions surrounding the 787 (schedule, certification, production and deliveries and on and on). Scott Hamilton has a nice update on his blog. One item he highlights is the ramp up to 10/months. He opines that Boeing will have trouble reaching that rate by the end of 2013 and feels that end of 2014 or into 2015 is more realistic.

Indeed it is looking that ramp up is going to be an issue. Boeing just started work on LN 32 (ZA235 for Air India) and LN 33 (ZA179 for JAL) won't be started until January 31st and LN 34 (ZA380, the first 787 for China Southern) will start final assembly on Feb. 14th. That's a 2/month production rate though I do expect that as the years wears on, this rate will increase (to what I don't know). You can read more of Scott Hamilton's post below:

Scott Hamilton: Odds and Ends: Big week for EADS, Boeing

In the same vein, Aviation Week reports Guy Norris and Mike Mecham wrote an extensive article regarding the 787 schedule. The main concerns remain what additional testing does the FAA require especially for ETOPs out of the box certification. The FAA has told Boeing that as it currently stands, the 787 won't get ETOPs certification until Boeing can prove the 787s reliability in light of the fire on ZA002 and the engine problems that Rolls Royce has encountered on the Trent 1000.

Aviation Week: Questions Remain About Boeing 787 Schedule

Boeing is trying to ramp up 787 test flights and currently has posted over 2600 of flight time over 850+ test flights. However, ZA003 and ZA006 have yet to resume test flights. It is unknown why they have not returned to test flights. Later this morning, ZA005 is schedule to make a test flight from Albuquerque, NM to Aguadilla, Puerto Rico. We'll see if this flight actually does occur.



Monday, January 17, 2011

Breaking: Boeing 787 resumes FAA Certification Flight Tests Today

Boeing announced a resumption of 787 certification flight test today in an email statement. Today Boeing had 4 787s flying (ZA001, ZA002, ZA004, and ZA005. The other two will be flying within the next one week:

787 Resumes Certification Flight Testing

Boeing has resumed certification flight testing of the 787 Dreamliner today. There are currently four airplanes back to flight status: ZA001, ZA002, ZA004 and ZA005. The others - ZA003 and ZA006 - are expected to be flying again within the next week or so.

Boeing is widely expected to announce the delivery schedule. With tonight's announcement of the resumption of certification test flights, I believe Boeing will announce the new delivery schedule sometime this week (Tuesday-Wednesday). Later this week I'm also expecting that ZA102 (LN 9) will take flight. This is the first production 787 to fly though the flight hours this airplane accumulates will not be counted towards certification flight testing (nonetheless I will try to keep track of the flights this particular airplane conducts).

Saturday, January 8, 2011

787 return to certification testing in a week; ZA102 to fly in last two weeks of January

Now that the Holiday are over, Boeing is trying to pick up the pace for the lost time due to the fire on ZA002. Boeing has been flying ZA001 and/or ZA004 since January 3rd though they haven't been flying very long duration flights (longest so far is about 5 hours).

However, in the coming days we should see more 787 rejoining the test flight program though for the next one week at least these will be only Boeing test flights and certification test flights.

According to information from sources, ZA005 should be flying again on January 9th (Sunday), and ZA002 will be flying again on January 11th. ZA006 will fly on January 14th and ZA003 will be flying again on January 16th.

More importantly, ZA004 is projected to restart certification flight tests as early as January 14th with ZA001 and ZA006 projected to follow on the 15th, ZA002 on the 16th and ZA005 on the 18th.

Also of significance is that ZA102, the first production airplane to fly may fly as early as January 15th and as late as January 24th. This airplane is out on the flightline at Everett. It is around this time that Boeing will be releasing it's 2010 full year financial results so there would be more that will probably be siad about the schedule at that point though everyone is still waiting to hear about the revised delivery schedule from Boeing.

Note that this schedule is still a projected schedule and things can still change given Boeing continued discussions with the FAA.





I hope to learn more very soon.

Monday, December 13, 2010

One Year In....The 787 year in review.

For the last 12 months I've been giving a monthly update on the 787 flight test progress with the exception of last month. With the one year anniversary of ZA001's first flight and the suspension of 787 flight activities, it seems an appropriate time to review the 787 program and try and take a look ahead to see what awaits the 787. It has been a year of triumphs and heartache within the program and the current forecast for the program is, at best, overcast.

787 - December 15, 2009 to December 14, 2010

December 15, 2009 was a day that Boeing hoped that see the start of putting the troubles of the 787 program in the rear view mirror. It was a day that cloudy and rainy (typical Pacific Northwest weather). The first 787, ZA001, made an on time takeoff and flew for a little over 3 hours. ZA002 flew one week later in a flight that was shortened by issues with the main landing gear door and the nose gear. Nevertheless these initial flights started Boeing on the path of initial airworthiness flight trials. The 787 achieved IAT in mid January 2010 which allowed Boeing to conduct test with the other test flight airplanes as well as with engineers on board. This allowed for the expansion of the787 flight test envelope which would include stability and control testings, flutter testing and functionality and reliability testing of the airplane.

Boeing added airplanes to the test flight fleet with ZA004 flying in late February, 2010 and ZA003 flying in mid March 2010. The near term goal of the program was to achieve Type Inspection Authorization for the 787. This is the point that would formally kick off the certification program for the 787. This point of the program was expected to be achieved by mid to late February, 2010 but was not granted until April 20, 2010. This was a major indicator that the program may suffer delays to the delivery schedule yet again. During this period Boeing had successfully test the 787 wing to the ultimate load limit test on ZY997, the static test airframe. This was a major certification test point that Boeing needed to accomplish given the issues that Boeing had found almost a year earlier with the side of body join and the weakness that was discovered.

Boeing continued testing throughout the spring and summer of 2010. They seemingly hit a very good flight test pace during late May/early June only to see the number of flight and flight hours flown to drop off a month later and then recover later in the summer. Progress was made in September through the early part of November with significant flight hours being posted especially with the GEnx powered 787s that had finally joined the flight test program. However there were set back to flight testing (and production) due to the time needed to inspect the horizontal stabilizers on all 787s due to Alenia's workmanship issues. Boeing needed to spend precious time and resources to inspect and conduct any repairs on the aircraft that were built and/or flying. Still despite the Alenia debacle, Boeing was still on track to deliver the 787 by end of 2010 until an early August Trent 1000 engine test in Derby, UK took a bad turn and the engine had an uncontained failure of it intermediate pressure turbine.

This was a major setback for Rolls and Boeing as it threw the entire schedule into doubt. Indeed, the engine that failed was due to be installed on ZA102 (LN 9) which was to be used for flight tests of production standard aircraft. Boeing had to delay delivery to mid February because of the unavailability of an engine for ZA102 within the needed time frame to start flight tests on this aircraft.

Still Boeing said they were confident in Rolls Royce's hardware and software fixes to prevent a recurrence of the failure and Boeing continued with flight and ground testing of the 787 through early fall until Nov. 9th.

ZA002 was flying a long duration test flight with FAA personnel aboard testing the nitrogen generating system (part of the fuel inerting system) and was on final approach to an airport in Laredo Texas when a fire erupted in the lower electronics bay near the left wing. The fire was out after about 30 seconds but the power panel where the fire originated was destroyed and the aircraft had experienced power distribution problems while in the process of landing. An emergency was declared (apparently after landing) and the crew and test personnel evacuated the aircraft using the emergency slides.

The problems that lead to the fire in the P100 power distribution panel are now well known but now at this point, one year after the first 787 flew the 787 schedule is in shambles. The aviation world is waiting for Boeing's revised schedule. The 787 has had more than its fair share of problems and delays since it was launched in 2004 and there's nothing to say that there won't be any more issues when Boeing and the FAA resumes flight testing.

Boeing is still encountering supplier and production issues and probably will continue to see sporadic halts to part deliveries into Everett. Clearly there is still plenty of issues that need to be cleaned up so that Boeing can start deliveries of the 787 and ramp up production. However, the aviation world is now waking up to the fact in light of problems in various aircraft programs (A380, 787, A400M, F-35, and the A350) that the old model that aircraft manufacturers used to develop, design, test and produce high technology aircraft is out the door. Robert Wall of Aviation Week summed it nicely in a blog post a week ago: "Skeptics quip that Airbus is effectively fighting the last war, and that the only thing it is assuring is that it will invent a whole new series of missteps. If that turns out to be true, then perhaps it is time to put to bed the idea of accelerating development cycles on major products and just learn to live with the fact that the gestation period for a major civil aircraft program is eight years or longer."

Friday, November 19, 2010

Guy Norris: Another brief 787 flight

Guy Norris says that two 787s will fly briefly on Saturday, Nov. 20th. ZA003 will fly from Everett to Boeing Field while ZA004 will fly in the opposite direction going to Everett from Boeing Field.

ZA004 will be going to Everett to get some routine maintenance accomplished. This maintenance work was preplanned. ZA003 is expected to resume ground tests at Boeing Field. ZA001, ZA005 and ZA006 are also conducting ground tests until they all can have clearance to resume test flights.

Lastly, ZA102 which is the first production 787 to fly will be rolled out of 40-24 around the end of the month according to Guy. It would be fitted with the package "A" Trent 1000 engines and is schedule to fly in December depending on what happens with the fire investigation. Even if it doesn't fly it could still conduct ground test as well as taxi tests.

Guy Norris: 787 to fly again (briefly) on Saturday