Friday, October 5, 2012

787 Production Update and 1st 787 Delivery from Charleston

Boeing is continuing to make steady progress in pushing out new and re-worked 787 during this past week.

In the EMC, ZA287 (LN 52, N20903) for United went inside the EMC hangar from a spot on the EMC ramp to continue the change incorporation process. With the reshuffling that went on inside th hangar, ZA286 (LN 50, N20902), also for United, went to the paint hangar and will start the pre-flight program at Everett. 

Boeing has completed the first 787 to go through the surge line though I'm still trying to get a handle on the location.  Currently I believe that ZA538 (LN 80, CC-BBC), for LAN, is in 40-26 position 4 for final assembly activities and aqueous wash but should be going to paint very soon.  The other 787 in paint is ZA290 (LN 77, N20906), again another United Dreamliner but that should be coming out of paint very soon thus making way for ZA538. I don't have information on where ZA271 (LN 78, SP-LRB) for LOT Polish Airlines and ZA432 (LN 79, B-2730) for Hainan Airlines currently after the line move in 40-24.  Boeing has loaded ZA183 (LN 84, J8829J) for Japan Airlines into position 1 on 40-24 surge line to start final assembly.

At Charleston, ZA240 (LN 65, VT-ANL) finally saw daylight and was rolled out of the final assembly building last Sunday (Sept. 30) to start pre-flight in advance of its eventual delivery to Air India.  Brendan Kearney of the Post and Courier also reported that ZA238 (LN 54, VT-ANJ) also for Air India and the next Charleston built 787 to be delivered should be returning from Ft. Worth where it was being painted by this weekend. With the line move, Boeing has 4 787 in assembly at the Charleston plant with another 3 on the flightline going through pre-flight or pre-delivery.  It is anticipated that Air India should take delivery of another Charleston built 787 late this month but that is all dependent on the internal situation at Air India and the issues it confronts in dealing with the Government of India.

Speaking of Air India, again, Boeing did make delivery to Air India of ZA237 (LN 46, VT-ANI) which is the first 787 built at Charleston.  While the milestone was notable so was the fact that this was a very low key delivery ceremony possibly arising out of the tortured path and bad feelings in arriving at this moment.  No big speeches by politicians or dignitaries at this delivery ceremony.  We'll see how future delivereis to Air India goes but rumor has it that Air India needed bridge financing for this airplane so I have to wonder how smooth future deliveries to this airline will be. Here's Boeing's Press Release on today's delivery:

Boeing Delivers First South Carolina-built 787 Dreamliner

Historic delivery to Air India begins a new chapter of Boeing airplane production in region


NORTH CHARLESTON, S.C., Oct. 5, 2012 /PRNewswire/ -- Boeing (NYSE: BA) today marked a historic milestone with delivery of the first 787 Dreamliner built at its North Charleston, S.C., facility to Air India.   
The delivery continues the momentum of the 787 Dreamliner's entry into revenue service by customers globally and marks the beginning of a new era of commercial airplane production in South Carolina.

"Within just three years of breaking ground, we have flown and delivered our first airplane built at Boeing South Carolina," said Jack Jones, vice president and general manager, Boeing South Carolina. "This is a tribute to the remarkable Boeing South Carolina team and the support we have received from our airline customers, our supplier partners and the Boeing enterprise, as well as the relationship we have with the State of South Carolina."

Work on the Boeing South Carolina Final Assembly and Delivery Center began in November 2009. Production of the first South Carolina-built 787 began in mid-2011 and the completed airplane rolled out of the factory in April.

Boeing South Carolina fabricates, integrates and assembles the midbody and aftbody fuselage sections for all 787 Dreamliners. Completed sections are joined in South Carolina Final Assembly, or transported via the Dreamlifter to 787 Final Assembly in Everett, Wash.

"We're delighted to be the first airline in the world to take delivery of a Dreamliner from this beautiful factory and look forward to taking many more," said Air India Board Member K.M. Unni. "The 787 is an airplane with unmatched efficiency and technology, which will help in our airline's turnaround plan."

Dinesh Keskar, senior vice president of Asia Pacific and India Sales, Boeing Commercial Airplanes, praised Boeing's long, successful partnership with Air India, including delivery in September of its first two of 27 Dreamliners. "With two 787s successfully introduced to Air India's fleet, passengers are enjoying breakthrough features such as larger windows, lower cabin altitude and unprecedented flying experience," said Keskar.

Today's delivery marks the 28th 787 Dreamliner delivered to date. Boeing South Carolina will increase final assembly production to three 787s per month by the end of 2013.
The Boeing 787 Dreamliner is the first commercial jetliner made primarily of advanced composite materials. It offers exceptional passenger comfort features, including cleaner air, a lower cabin altitude, higher humidity, bigger windows that dim electronically and more overhead storage space. Airlines appreciate its fuel efficiency, which is 20 percent better than other airplanes in its class and results in 20 percent lower carbon emissions.









Monday, July 11, 2011

787/747 Update

Boeing continues to make steady progress towards the 787's delivery target schedule for sometime next month or the month after. ZA102 (LN9) has already flow about 86.25 hours of the approximately 300 hours needed to to complete F&R/ETOPs testing as of July 10th. Currently the airplane is in Hawaii for tests and will be returning to Paine Field today.

ZA002 has just completed SROV testing in Japan with final testing between Tokyo and Nagoya. From all indications, the testing went very well and the production aircraft will be service ready when they start reaching customers. Here's a recap of ZA002 schedule from the past week in Japan:

Flight 1 LV. SEA 7-3-11 5AM ARR. HND 7-4-11 6:30AM
Flight 2 LV. HND 7-5-11 6:30AM ARR. ITM 7-5-11 7:30AM
Flight 3 LV. ITM 7-5-11 11:30AM ARR. HND 7-5-11 12:30AM
Flight 4 LV. HND 7-6-11 6:30AM ARR. KIX 7-6-11 8:00AM
Flight 5 LV. KIX 7-6-11 12:00PM ARR. HND 7-6-11 1:30PM
Flight 6 LV. HND 7-7-11 6:00AM ARR. OKJ 7-7-11 7:30AM
Flight 7 LV. OKJ 7-7-11 11:00AM ARR. HND 7-7-11 12:30PM
Flight 8 LV. HND 7-7-11 3:00PM ARR. HIJ 7-7-11 5:00PM
Flight 9 LV. HIJ 7-7-11 7:00PM ARR. HND 7-7-22 8:30PM
Flight 10 LV. HND 7-10-11 6:25AM ARR. NGO 7-10-11 7:30AM
Flight 11 LV. NGO 7-10-11 6:00PM ARR. HND 7-10-11 6:45PM

When ANA starts revenue service with the 787, the destination will either be Okayama or Hiroshima from its base at Haneda International Airport in Tokyo.

Next stop for ZA002 is India where it will fly be shown to customers Air India and Jet Airways. Air India is expecting it's first 787 in December of this year while Jet Airways will receive its first airplane sometime in 2014. ZA002 will fly from Haneda in Tokyo to Indira Gandhi International Airport in New Delhi and then on to Mumbai. From there it is not known if ZA002 will fly back to Seattle or will fly on to other destination for other visits with customer airlines.

The 787 test fleet continues to fly occasional Boeing test flights with ZA001, ZA003 and ZA005 taking flights over the past week or so.

Production continues at Everett at a rate of two 787s per month. Boeing will starting final assembly on ZA261 (LN44) for Ethiopian Airlines on July 20th but more importantly, the first 787 to be assembled in North Charleston, SC will start final assembly on August 17th. That airplane ZA286 (LN46) for United Airlines already has its wings delivered to the final assembly hall and will be waiting for the forward fuselage from Wichita as well as the center and rear section just next door to the final assembly hall. the horizontal tail plane form Grottaglie, Italy as well as the numerous other parts (tail fin from from Washington State and landing gear) are expected to be delivered soon. Boeing is expected to increase production from 2/month to 2.5/month though it is still unclear when this increase is supposed to happen. The current schedule doesn't show assembly start dates past airplane number 46 which indicates that Boeing is currently reviewing plans for future assembly start dates and thus reviewing the ramp up to the 2.5 rate.

Meanwhile Boeing has added a third 747-8I to the flight test program. The aircraft, RC003/N5020K will be used to perform high intensity radio frequency tests. It is in Southern California currently. The 747-8F F&R testing has continued but RC523 has not carried out any test flights recently. Boeing is very close to finishing off the 747-8F test program and anticipates delivering the first 747-8F to Cargolux this summer.