Wednesday, July 17, 2013

AAIB to put out interim report on Ethiopian 787 incident within days; 787 production slowed in Everett

UPDATE: Jon Ostrower is reporting that the 1st 787-9 (ZB001, LN 126, N789EX) should be rolling out of 40-24 and into the paint hangar at around 11PM PT. Final assembly of this test flight aircraft took 48 days.

The UK's AAIB is expected to put out an interim report on the fire/heat event on board the Ethiopian 787 which occurred on July 12th.  Thus far investigator are looking at the aircraft's lithium-manganese powered emergency locator transmitter (ELT).  This piece of equipment is made by Honeywell and is considered an off the shelf item meaning that it was not designed exclusively for the787 but is probably used on other commercial aircraft models.  It is far from certain if the ELT is the cause or help feed the fire but investigators did find this piece of equipment virtually destroyed and the damaged to the carbon composite structure of the aircraft is in the area where the ELT is located.

In the meantime none of the airlines nor Boeing have stopped 787 operations and the carriers continue to fly their full schedule.

Boeing continues 787 production with the 2nd 787-9, ZB002 (LN133, N789FT) entering final assembly on July 12th in 40-24.  However an analysis of the 787-8s that have started final assembly reveal that the production rate has slowed at Everett. I'm not sure if it was due to the prolong grounding during the winter-early spring, the re-configuration of the main final assembly hall in 40-26 or a combination of both.  Looking at the production table, Boeing loaded ZA563 (LN 127) on June 26th after the reconfiguration and construction in 40-26 but the next two 787-8 that entered into final assembly was LN 128 (6 days later on July 2), LN 130 (14 days later after LN 128) and LN 131 is due to enter assembly 10 days later after LN 130.  To keep up the 5/month rate in Everett Boeing has to be loading one 787 into position 1 every 6 days.  It may be that they are re-ramping up to that rate after the construction but we would have to see.

The situation in Charleston may be similar.  The Post and Courier revealed that the Charleston line is producing at 1.5/month and will not get to 3/month until sometime in the 1st quarter of 2014 but that Boeing still plans to have 787 production at 10/month by the end of this year.

Full 787 List

Current 787 Production List

Delivered 787 List

787 Monthly Delivery Tracking

787 Customer Delivery

 








1 comment:

Jozef said...

LN103 in air http://flightaware.com/live/flight/BOE466