Boeing has taken delivery of ZB001's horizontal and vertical tail plane as well as the wings. In the coming two weeks we should see the delivery of the fuselage sections into Everett.
Boeing is shifting production of 787-8s to the main 40-26 and 88-03 assembly lines in Everett in case issues with the assembly of the first 787-9 encounters problems in 40-24. Already Charleston is taking on more 787-8 but the bulk of the 787-8 production will go to the main final assembly in Everett.
The other two 787-9 test airplanes will follow ZB001 in the 40-24 surge line.
Meanwhile Boeing has resumed deliveries of the 787-8. ZA513 (LN83, JA818A) was delivered to ANA marking the airlines 18th 787 and Boeing's 51st 787 delivered.
LOT Polish Airlines was to have taken its 3rd 787 (ZA272, LN 86, SP-LRC) today but that is being delayed due to some minor issues with the aircraft. Delivery is now expected to take place around Thursday.