Tuesday, May 5, 2009

Flightblogger: No gas yet and other musing.

Some real good information came from Jon Ostrower today regarding the progress of the 787 program.

Jon was able to post that Dreamliner 1 has not yet started fueling tests but that final checks are being done prior to the start of those tests.

Dreamliner 2 will be painted in ANA colors ('m wondering about the other 4 test airplanes now) and will be going back to the factory (building 40-24) around the middle of he month. It'll be super cool to se a Dreamliner is a customer livery!

Dreamliner 5 will have its GEnx engines hung soon. the engines were delivered last Friday. I saw a picture that Jon had posted showing Dreamliner 4, at the time without its engines but with a Trent 1000 behind the aircraft. I opining that those Trents are now hanging off Dreamliner 4 by now.

There should be a line move coming very soon allowing for Dreamliner 7 (ZA100) to begin final assembly once the two remaining fuselage sections arrive into Everett.

Jon's May 5th 787 Update.