Friday, August 8, 2014

787 update - August 8, 2014




787 Deliveries in July
Boeing had a so-so delivery month in July with deliveries of only 8 Dreamliners.  They could have done better but I do think they are set up to deliver upwards of 15 787s in August.  July deliveries included ANA's first 787-9 which they are planning to press into service in early august n domestic routes in Japan.  In terms of production efficiency, Boeing delivered 8 aircraft rolled out 11 787s from all assembly lines.  That translates to an efficiency rating of 1.38 (11 rollouts/8 deliveries).  The lower the number the more efficient the program.  The Charleston plant delivered 3 and rolled out 3 for an efficiency of 1 while Everett delivered 5 aircraft and rolled out 8 giving it a an efficiency of 1.6.  Currently it does appear that Charleston is producing more efficiently given this metric but it doesn't take into account unforeseen circumstances that would not be in the control of Boeing or at either plant (i.e. customer difficulties, etc.). Eight days into August and thus far there have been 3 deliveries.  There has also been a noticeable pick up in flight testing tempo.  I do project that in addition to the 3 already delivered in August, Boeing can deliver 12 more of which 10 have flown and 2 more are awaiting their B-1 flights.







787 Production
The production pace at both plants continue as before with several more -9 entering final assembly in Everett.  Boeing is gradually shifting Everett 787 production from 40-24 where the surge line is located to 40-26 which is the main production line to a point where the surge line will shut down in 2016.  This will allow 40-24 to be freed up for 777X production that should start around 2017 after the surge line undergoes re-construction to prepare it for 777X production.  The build rate in 40-26 appears to be about 6 manufacturing days while in 40-24 it appears to be about 7 manufacturing day.  Over the next 18 months I expect the manufacturing days in 40-26 will decrease to about 3 days as Boeing slowly transfer the surge production to the main line.  During August we should seeing a couple of first: the 1st 787-9 for Scoot and the 1 787-8 for American Airlines should start final assembly during the 3rd week of August and both aircraft should deliver around November.
In Charleston the expansion continues as Boeing continues construction in the 88-30 line in order to prepare it to handle 7 airplanes/month by 2019. Work continues on a new paint facility and firefighting station but the expansion will not likely stop there. Currently the build rate is about 7 days at Charleston which will have that team pulling 3 787s out per month and delivering the same number in August.
The one big news for Charleston came out at the end of July.  Boeing announced that they will build the 787-10 exclusively in Charleston. The reason that was given that the fuselage can't fit into the Dreamlifter for transport to Everett.  According to some information that I received that is technically not true.  The fuselage can fit into the Dreamlifter but the FAA has set a limit as to the length of an object that can be carried by the aircraft.  The mid body fuselage for the 787-10 exceed the maximum length allowed by the FAA. For some time this decision was anticipated to go to Charleston and frankly was not a surprise. Neither was it a surprise that Charleston will taken on the additional rate increase that Boeing has planned for 2016 and around 2018-2019 to take the rate up to 14 aircraft per month.  Boeing has announced that they will build the -10 in Charleston but it remains to be seen if they will conduct certification flight testing in Charleston or if the 787-10 will conduct all it's testing out of Boeing Field where Boeing Flight Test team is headquartered.  It is conceivable that they can set up the facilities necessary to conduct certification tests in Charleston but I doubt that Boeing would take the expense to do that just for one derivative.  Most likely the test flight fleet will be flown to Boeing Field and testing will be based out of Seattle.  The location of the -10 shouldn't change the employment outlook at Charleston but the increase in work as well as the increase of the Boeing foot print in the Charleston area will drive the employment at the Boeing facility.
Here's Boeing's Statement on the 787-10:
Boeing to Assemble 787-10 Dreamliner in South Carolina

EVERETT, Wash., July 30, 2014 /PRNewswire/ -- Boeing [NYSE: BA] announced today that final assembly of the 787-10, the newest and longest member of the 787 Dreamliner family of airplanes, will take place exclusively in North Charleston, S.C. 
Boeing will continue to assemble both 787-8s and 787-9s in Everett, Wash., and North Charleston. Design of the 787-10 is underway in Everett, with final assembly of the first 787-10 scheduled to begin in South Carolina in 2017. 
"We looked at all our options and found the most efficient and effective solution is to build the 787-10 at Boeing South Carolina," said Larry Loftis, vice president and general manager, 787 program, Boeing Commercial Airplanes. "This will allow us to balance 787 production across the North Charleston and Everett sites as we increase production rates. We're happy with our growth and success in South Carolina, and the continued success at both sites gives us confidence in our plan going forward." 
The 787-10 will be 18 feet (5.5 meters) longer than the 787-9. With 10 feet (3 meters) of that increase in the midbody section, the 787-10 midbody is too long to be transported efficiently from North Charleston, where systems integration work is performed, to the Everett facility for final assembly. In addition, introducing the 787-10 in North Charleston takes advantage of that facility's capacity while allowing the Everett facility to continue improving productivity as it focuses on the 787-8 and 787-9. 
The 787 production system includes three production lines: two in Everett (including a temporary surge line) and one in South Carolina. The integrated production system currently operates at a production rate of 10 airplanes per month. As announced last year, the 787 production rate will increase to 12 airplanes per month in 2016 and 14 per month by the end of the decade.  
The Everett facility will continue to assemble seven airplanes per month, while Boeing South Carolina final assembly will gradually increase from three 787s per month today to five per month in 2016 and seven per month by the end of the decade.  
The Boeing 787 Dreamliner family of airplanes offers airlines unmatched fuel efficiencies and environmental performance, while providing a new level of comfort for passengers through the thoughtful application of new technologies. To date, the 787 family has won more than 1,000 orders and more than 165 airplanes have been delivered to 21 customers worldwide.  
The 787-10 will leverage 787 technology to provide more passenger and cargo capacity along with unparalleled seat-mile economics in the medium twin-aisle market. Since its launch in June 2013, the 787-10 has won 132 orders from six global customers.

A couple other notes of interest.  Boeing has stored a 787 that is supposed to be delivered to Azerbaijan Airlines from their order of 2 aircraft.  Rumor has it that the airline now wants to cancel the order though it is just rumor and the airline can also be delaying delivery.  It is unknown if this aircraft has an interior installed already but 2nd aircraft is scheduled to be assembled in Charleston around September for delivery in December.  This situation seems similar to the one Airbus faced with Skymark Airlines when they cancelled their A380 order after two aircraft had already been built.  For now this aircraft is in storage until there is a resolution to the situation with the customer and they will be building the 2nd aircraft as the parts are already in the supply chain. If they do agree to the cancellation then I don't think Boeing will have a problem placing these aircraft with another customer though it may take a few months depending on the interior.

Lastly, the assembly of the 787-9 is starting to hit it stride though the airplanes produced are still going through change incorporation at the Everett Modification Center.  This will continue because when the aircraft was certified there were part manufactured by Boeing or suppliers that had to be bought up to the FAA certification standards.  Many of these parts were deep within the supply chain. when the FAA issued the amended type certificate thus these parts need to be bought up to standard before the FAA certifies each aircraft as being in compliance.  This is the reason why Boeing is deliberately keeping the 787-9 assembly rate slow until the changes are reflected throughout the supply chain.  I believe that Boeing will start assembling aircraft that will not need change incorporation around the time that Charleston starts building it's first 787-9 in November for united Airlines.

787 Full Production Table

Saturday, October 23, 2010

Dreamliner 4 circuit around the country and potential 787 production woes resurfacing?

ZA004 undertook a very long 13+ hour test flight that took it around the country yesterday to test the 787s to test...of all things... the fuel gauge of the aircraft. According to Flightblogger, the test (which I initially thought was an ETOPs flight) was to see how the Fuel Quantity Indication System. The test added a large amount of flight test time to the 787/RR test flight fleet and bought them closer to the 2,430 flight hours needed to certify the 787/Trent 1000 engine combination and allow for deliveries to start to ANA. The Trent 1000 powered 787 test flight fleet has accumulated well over 1,900 flight test hours thus far and the total 787 flight test hours has exceeded 2,100 hours leaving 1,000 flight test hours needed to complete the test flight program.

Flightblogger: 787 goes cross country to check the gas gauge

While the test flight program continues to make progress, there are signs of production troubles on the 787 final assembly line. ZA233, the 29th 787s to be assembled was initially supposed to start final assembly on Oct. 4th. It was pushed back to late October, then early November and now I got news that it won't start assembly until around November 17th...over 6 weeks late. To add to the mystery, Matt Cawby got video of a rear and forward 787 fuselage sections being loaded back on to the 747 LCF in Everett instead of being offloaded. Now the LCF did not depart Everett so my guess is that they might be being stored on board the 747 LCF. I am hoping to hear from Boeing about any production pauses on the 787 line and what reloading of the fuselage sections on the LCF may mean.

Tuesday, March 9, 2010

Albaugh speaks at JP Morgan Aerospace Conference

James Albaugh, Boeing Commercial Aircraft President, spoke at a JP Morgan Investors conference this morning. Here are a few snippets:
  • 787 should receive the TIA (Type Inspection Authorization) by the end of this month (March).

  • Boeing right now putting out 2 787s per month will be up to 2.5 airplanes per month by August, 2010 and up to 10/month by end of 2013.

  • ZA003 should fly this Sunday (confirms what I had reported earlier here)

  • ZA001 reached speeds of around M0.97 (in a dive) during testing.

  • Expects first 787 delivery from Charleston in 1st quarter 2012

  • Boeing has used up some of the 787 flight testing contingency and had about one to one and a half months of contingency left in the test flight program.

  • New 747-8 coming "on line" on March 15, 17 (this means that Initial Airworthiness Testing is complete by then so that the two remaining 747-8 test airplanes will be in the air next week).

In other news, ZA003 ran its engines yesterday on the Boeing flight line and should be conducting its gauntlet testing towards the end of this week followed by first flight on March 14th. ZA002 has departed this morning for Victorville where it will continue flight testing.

A bit of surprising news is Boeing's award of 747 LCF Dreamlifter operations from Evergreen International to Atlas Air.

Unsurprisingly, Evergreen International is upset but their contract was for 35 years but is renewable every 5 years and it was due for renewal this year. Here's an article focusing on Evergreen's reaction.

Also, unsurprisingly, Flightblogger is reporting that the LCF contract was given to Atlas as part compensation for the delays to the 747-8F, 12 of which Atlas has ordered. Atlas is due to take over LCF operations from Evergreen this September. Boeing will retain ownership of the 4 LCFs.

Flightblogger: Sources: Dreamlifter Deal Part of 747-8 Compensation to Atlas

Fleetbuzzeditorial.com : Boeing's Big Choices

Tuesday, February 16, 2010

787 & 747 Tidbits

Well know that Boeing has two major programs in test flights here's some updates.

787

Boeing announced that the fourth Dreamlifter is now in service after the 747-400 underwent major reconstructive surgery (like it's 3 sisterships) in Taiwan. Here's Boeing's Press Release:

News Release Issued: February 16, 2010 2:51 PM EST

Final Boeing 747 Dreamlifter Enters Service
EVERETT, Wash., Feb. 16
/PRNewswire-FirstCall/ -- The fourth Boeing (NYSE:BA) Dreamlifter – the final airplane in the fleet of specially modified 747-400s – entered service today. Dreamlifters transport the large composite structures of the 787 Dreamliner from partners around the world to Everett, Wash. for final assembly. The unique airplane, which was modified by Evergreen Aviation Technologies Corp. in Taipei, Taiwan, took off from Paine Field in Everett early this morning. Bound for Wichita, Kan., the Dreamlifter is returning the equipment used to transport the forward fuselage section known as section 41. The airplane's registry is N718BA.

I heard a couple years ago that Boeing may need as many as 6 Dreamlifter to support the higher production rate. With the Charleston Assembly Line due to start production middle of next year Boeing may have to procure two more low mileage 747-400 for conversion to LCFs to meet the higher expected output.

In the meantime ZA003 underwent more ground testing as does ZA004. Both aircraft still are expected to be in the air by the end of the month with ZA005 in the air by March and ZA006 flying by the end of April.

Flight testing continues with ZA001 starting flutter tests on February 14 with this testing expected to last a few weeks. Soon after that the 787 should receive its TIA (Type Authorization Inspection) which will be the formal start of certification flights with FAA inspectors on board the test flights.

Guy Norris has a great blog post detailing the 787 flutter tests.

787 - Forward to Flutter

On the production front, Boeing has sent airplane 13 to the paint shop after it had completed final assembly activities in building 40-26. Airplane 17 moved into position 1 for the start of final assembly and parts for airplane 18, destined for ANA, has started to arrive in Everett.

747-8

Since conducting first flight of the 747-8F, Boeing has been conducting further ground tests on RC501 as well as checking out the aircraft in preparation for the next flight speaking of which should occur as early as this coming weekend. RC521 is continuing its preparations for its first flight which should occur after RC501 as completed initial airworthiness flights. In the meantime, Boeing released some very spectacular images of RC501's first flight around the Seattle area.

All photos below are Boeing Photos:













Tuesday, January 19, 2010

Some 747-8 news and some 787 news

Ok switching gears for a moment. Here's some 747 news. Flightblogger is reporting that the first 747-8 will start 40 hours of final gauntlet testing later this week. Final gauntlet tests the aircraft's systems and subsystems by making the airplane think that it is flying and seeing how those systems react.

First flight is probably going to occur sometime in February though I still don't have a firm date. That date, like the 787 first flight date before it, is dependent on the results of gauntlet testing and the need, if any, for any further testing.

Guy Norris reports that Boeing is working through a long list of EWAs (Engineering Work Authorizations) which is a long name for systems checks. Boeing has been working on a series of systems to make sure they're ready for final gauntlet. Guy says that given that final gauntlet hasn't started means that first flight won't occur until very late this month to middle of next month.

Matt Cawby got a couple of nice picture of the two 747-8F on the Boeing flightline. Curiously both are registered N747EX.

Lastly, in a somewhat related note, Flightblogger says in his post that the 4th LCF for the 787 program is due in Everett next month after taking it first flight (post conversion) on Friday, January 15. In a 787 related update, ZA004 will be testing the 787's evacuation slides this week and ZA001 will hopefully start further flight envelope expansion tests with further flutter and primary flight control system tests followed by high speed stability and control testing.

Randy Tinseth, in a blog posting on Friday, January 15, talks about the 787 achieving its Initial Airworthiness testing milestone and notes that the 787 fleet has accumulated 59 hours and 15 minutes of flight test time. Using flightware I've calculated 59 hours and 40 minutes of flight time which is close.

Flightblogger's Week Ahead Post

Guy Norris: 747-8 Flight Test Update

Matt Cawby: January 15 747-8 Update

Boeing Prepares 747-8 Flight Test Program

Randy's Journal: Initial Airworthiness

787 flight tests off to a promising start

Friday, October 30, 2009

Flightblogger: The moving parts of the Charleston Decision

Flightblogger posted some very interesting analysis now that Boeing has decided to place the second 787 assembly line in Charleston.

The Surge: Boeing will set up a temporary line at Everett (on the 767 according to Flightblogger) which will handle the production ramp up until Charleston comes online. Flightblogger also said that the 787-9 will be built in Everett though he has not said if it will also be built in Charleston.

Dreamlifter: Flightblogger created an interesting table comparing the number of flights and the flight distances of flying parts into Charleston for final assembly vs flying parts into Everett. In it the Charleston line will require fewer delivery flights and fewer miles flown compared to the Everett line. Boeing currently has three LCFs and plans on adding a fourth but will probably need at least two more to support the 10/month rate coming from two assembly lines.

Lastly, Flightblogger said it is possible that airplanes coming from the Charleston line will be for customers in Europe will those from Everett will be destined for Asia/Pacific/Australia customers. While that might make sense now since the number of Asia/Pacific aircraft outnumbers those going to Europe and even South America, those dynamics could change. I don't know where those aircraft destined for North American customers (Air Canada, Continental, Delta/NW and AA) would come from but they might flow from both lines with AC, and AA taking planes from Everett and CO and DL/NW taking planes from Charleston given where their major hubs are located.

Flightblogger: The many moving parts of the Charleston line decision

Monday, October 26, 2009

Flightblogger: Boeing complete 787 detailed design of 787 fix

Flightblogger is reporting tonight that Boeing has completed the detail design and computer validation of the last few final parts that makes up the 787 side of body join reinforcement fix. These final parts are being fabricated and should be delivered soon to be installed on the static test air frame as well as the test flight aircraft that are currently undergoing the installation of the modification.

Flightblogger is indicating that given that Boeing has finished the detailed design and computer validation of the fix that they have overcome the load issues that were discovered last Spring. Flightblogger is saying the test results received thus far are looking good.

Flightblogger

In other 787 news, Fleetbuzzeditorial.com came out with some great pictures of the 787 final assembly line:

Fleetbuzzeditorial.com - ZA100 and ZA101 at Everett

Additionally, Fleetbuzzeditorial.com also put out an interesting piece about the 2nd assembly line for the 787. This line is going to be crucial for Boeing to meet it delivery obligations. Here the article addresses the issues of the 2nd line, the choice ahead for Boeing and the pitfalls facing Boeing.

Second Guessing 787 Second Line

Lastly, the LCF's continue to make regular runs between the 787 suppliers and Everett. The nose section , wings, main fuselage, horizontal and vertical stabilizers for airplane 12 (LN 12) are already in Everett and I do believe the rear fuselage section is also in there though I have no confirmation. There should have been a line move already or will happen soon so that LN 8 (2nd production aircraft) will be moved out of building 40-26 thus clearing the way for airplane 12 to start final assembly in the coming days. Thus far Boeing is looking to maintain a 1 airplane/month production rate and gradually ramping that up to 10/month by the end of 2012. LN 7, the first production 787 is already outdoor on the Boeing flightline sans the Roll Royce Trent 1000s:

ZA100

Saturday, June 20, 2009

Two Dreamliners and a Dreamlifter

Matt Cawby got this great shot of two 787s and the 747LCF together (sort of). Kind of a cool picture.

Two Dreamliners and a Dreamlifter

Wednesday, April 1, 2009

Dreamlifter Fleet

In a rare moment photographer Matt Cawby got a nice picture of all three 747 Dreamlifter LCFs on the Boeing Ramp yesterday. There's supposed to be a 4th Dreamlifter but that is probably delayed until such time that Boeing will need it during the ramp up to full production.

Click here to see the picture.

Monday, March 23, 2009

Mt Redoubt blows its top: possible implications for 787 assembly?

RELATED UPDATE: Boeing told me that they're monitoring the sitation on Mt. Redoubt but don't expect any disruptions to their operations.

UNRELATED UPDATE: Dreamliner 1 might be making an appearance on the Boeing Everett flight line by around Wednesday or Thursday (March 25/26) of this week.

As some of you know, Alaska's Mt. Redoubt, a volcano about a 100 miles away from Anchorage, Alaska, erupted on Sunday. Geophysicists have said that these eruptions can continue for weeks or months.

Now what does that have to do with the assembly of the 787. Plenty it turns out. Boeing dispatches the 747 Dreamlifter or LCF to Nagoya to pick up the center wing box and mid fuselage sections that are then transported to Charleston, SC for integration with other parts flown in from Italy. These parts, when assembled form the 787 main fuselage. The LCFs also fly the wing boxes (or wings) for the 787 from Nagoya to Everett for final assembly.

Because of these eruptions, Mt Redoubt is throwing up plenty of ash and dust into the atmosphere. This ash and dust, when sucked into the engines of commercial aircraft, can flame out the engines which has happened with a 747 flying through a previous eruption many years ago (fortunately the pilots were able to restart engines before the plane would have crashed). This eruption can and will disrupt air traffic flying into and out of Anchorage, AK. When the LCFs are flying with these heavy sections and wings on their way to the US, they have to have a refueling stop in Anchorage. If Anchorage is shut down or if the dust and ash cloud prevents commercial aircraft from operating near Anchorage (which is on major commercial routes), then the LCF flights can be delayed or perhaps stopped from traveling from Japan to the US.

Note that when the LCFs are empty, they can fly a more southerly route and don't need a refueling stop on its way to Japan from the US. We just have to wait and see how this could effect Boeing in the near term as they attempt to increase 787 production.

Saturday, March 14, 2009

787 line moved on Friday (March 13)

Boeing moved the 787 line on Friday March 13th.). Dreamliner 3 was moved out of the line to building 40-22 (747 line) where it will continue assembly thus moving Dreamliner 4 and Dreamliner 5 down one spot and making room for Dreamliner 6 to start final assembly on Monday March 16th in position 1. Dreamliner 2 will remain it is current spot in position 4 in building 40-26

The final section for that airplane, the main center fuselage is being flown tonight to Everett from Global Aeronautica on the Dreamlifter. Track the LCF flight here.

Wednesday, March 11, 2009

Near term 787 dates

I just got some new information on some near term 787 goals (near term, meaning over the next week). I got confirmation that the forward fuselage for Dreamliner 6 (ZA006) was delivered into Everett last night on the Dreamlifter. That leaves the main fuselage to be delivered. That part should arrive from Global Aeronautica in Charleston, SC on March 13th (this Friday).

The line move that was supposed to occur on March 8th is now slated to occur on March 14-15th.

After that the parts for Dreamliner 6 will be moved into position 1 on the 787 line around March 16th to start final assembly.

Lastly, AF-KLM has announced that they will decide between the 787 and the A350 by the end of 2009 or early 2010. If Airbus doesn't get GE to sign on to the A350 then the odds are in favor of the 787 getting the nod.

Tuesday, March 10, 2009

Dreamliner 6 forward fuselage

The Dreamliner is flying today from Charleston, SC to Wichita today and then later on to Paine Field in Everett. It's my thought that it might be carrying the forward fuselage for Dreamliner 6 (LN 6) to Everett today.

The only way to confirm this is to have someone let me know if the section is actually unloaded at Everett today.

See the Flightaware track.

Tuesday, February 10, 2009

Rear fuselage for Dreamliner 6 heading to Everett?

UPDATE: I got confirmation that the rear fuselage for Dreamliner 6 is on board the Dreamlifter.

A Boeing Dreamlifter is flying to Everett this morning possibly carrying the rear fuselage for Dreamliner 6. It should arrive by about 3:15PM EST. I hope to have some confirmation a little later.

Monday, January 26, 2009

Gettin' Busy in the 787 Program

The 787 is getting busy through out the world. Information that I got says that there has been a tremendous amount of resources thrown at Dreamliner 1 and Dreamliner 2 to those two aircraft finished. LN 2 though as not been powered up and probably won't be until well after it is done with vibration testing.

Additionally Dreamliner 5 will start final assembly today and not tomorrow or Wedensday as I first thought. Section 41 (forward fuselage section) is already in position at the join tool and looks like the main fusealge will follow suit shortly.

Lastly, there has been an uptempo of LCF (Dreamlifter) flights. between the major partners which strongly suggests that the 787 production system is getting ramped up again. I've been tracking flight between Charleston, Nagoya and Grottaglie aswell as Everett. I'll continue to look at this trend to see how frequent the flights are and if they LCFs are making any fueling stops (In Anchorage or the UK) which indicates the presence of fuselage sections or wings that are being transported from Japan and Italy.

However, just because these is an increase in LCF flights doesn't necessarily mean that parts are being transported between sites, however it does bode well now that Dreamliner 5 will start final assembly soon.

UPDATE: Scott Hamilton has a story out on the 6 test 787 flying with temporary fasteners for the test flight program. the temporary fasteners will be replaced when the 6 airplanes undergo post test flight modifications in San Antonio. Read Scott's report here.

Wednesday, September 3, 2008

LCFs evacuate Charleston

Two of Boeing LCFs left Charleston, SC this morning. The two flight plans filed showed one aircraft heading to Pinal Airpark in Arizona and another heading for Anchorage, Alaska. Here are the flightaware flight plans here and here.

Hurricane Hannah is over Bermuda and the current projected track shows it heading to the Charleston, SC area by Saturday morning. I'm not sure what other preparations Vought, Boeing and Alenia are making for the 787 plant in Charleston.

Monday, August 4, 2008

Dreamliner 4 to start assembly soon

UPDATE: Another LCF just left Charleston with the main fuselage for Dreamliner 4. See it here.

The nose section for Dreamliner 4 should be in Everett later today thus setting the stage for the start of final assembly. The Dreamlifter is already in Wichita and has filed a flight plan to go on to Everett. No word yet on when the repaired main fusealge section is due in Everett but my guess is by tomorrow.

Thursday, July 24, 2008

787 Production Update

UPDATE II (7/30/2008): The start of final assembly of LN 4 has been pushed back to August 4, 2008. The Dreamlifter did not deliver any fusealge section from Wichita. It had a fuselage transport fixture that was returned to Japan yesterday when it flew from Charleston to Wichita then to Everett and then on to Nagoya.

UPDATE (7/28/2008): I just got word that LN 1 should be pulled out of the final assembly building just prior to the start of final assembly of LN 5 (projected to be around end of August). It'll go to building 40-24 (the 767 line) and then around September to the paint hanger to re-paint some of the sections (with all the work in the past year, some of the original paint was sure to have come off with all the assembly activities).

Lastly, one of the Dreamlifters might delivering the forward fuselage for LN 4 to Everett today as it filed a flight plan.


I just got word that the fourth flying 787 (LN 4) will enter final assembly on July 29th; one month later than expected due to the repair to the damage on the main fuselage. This ties closely to what I reported earlier that the two remaining sections (the forward fuselage and main fuselage) should be delivered around this weekend or early next week.

Saturday, June 21, 2008

Boeing moves 787 fatigue

ZY998 being moved to building 40-24.
Image Courtesy of Boeing
Yesterday Boeing moved the fatigues aircraft from building 40-26 to building 40-24 where it will stay for about a month finishing up some assembly tasks. Today LN 2 will move to position 3 while LN 3 will remain in position 1 until probably late this week.
As Jon Ostrower reported earlier, the third Dreamlifter, newly modified in Taiwan, will fly to the US in the next few days and immediately will be pressed into service to deliver the center fuselage for LN 4 (the fourth flying 787) late this week. The forward fuselage is also due to be flown into Everett soon and once those two sections have arrived then final assembly will immediately begin. LN 3 will probably move to position 2 late this week to make room for LN 4. The fatigues airframe is expected to move from 40-24 to the fatigue test area in about a month and at the same time LN 1 will move from 40-26 to 40-24 to finish up assembly tasks and prepare it for the move to the flight line. In doing so on or around July 21st, Boeing will make room for LN 5, the 5th test flight aircraft and the first to be fitted with the GEnx engines.
Here's is Boeing's press release here.

Wednesday, June 11, 2008

787 getting close to power on.

BREAKING: Another source says that power on will officially start tomorrow - June 12th. I am trying to get more information.

A source in the 787 program told me that there is still some good progress being made on LN 1, the first 787. Power on should still take place at the end of this month.

More significantly, ZY998, the fatigue test airframe is due to move out of the final assembly building (40-26) on June 19th and into the 767 final assembly building (40-24). It'll stay there until July 20th when it will be moved to the fatigue test site north of Boeing assembly plant.

The move on June 19th will allow Boeing to start assembly on Dreamliner #4 (LN 4).

Jon Ostrower has been in Charleston yesterday and got some great pictures and reported on the progress at Vought and Global Aeronautica. Jon also reported that the third LCF (Dreamlifter) has been certified by the FAA and will be in the US to start hauling 787 sections and parts in July.

More news to note: Boeing and Vought closed on the sale of Vought's share of Global Aeronautica to Boeing today. Boeing and Alenia are now 50-50 partners in the joint venture which assembles the main fuselage section for the 787 from the sections supplied by the three Japanese Heavies and Alenia. In being a partner with Alenia, Boeing is essentially bought inside the Global Aeronautica plant where they can have more control and can continue to look over Vought's shoulder in Charleston.

Lastly,
Dominic Gates from the Seattle Times has a great article on a media visit to Charleston which took place yesterday. Read about it here.