Showing posts with label ZD009. Show all posts
Showing posts with label ZD009. Show all posts

Saturday, April 1, 2017

Boeing delivers 11 787 in March while first 787-10 takes to the air as the quarter ends.

Production Snapshot
Number
Testing Complete3
To be assembled in Everett188
To be assembled in Charleston142
Parts Arriving
6
Undergoing final assembly8
Storage0
Storage/Change Incorporation and Re-Work0
Change Incorporation and Re-Work2
Pre-Flight Prep8
Production Testing3
Non Customer Flight Tests2
Ready for Delivery5
Donation3
Delivered532
TOTAL902

Boeing Photo

Boeing Photo

Boeing Photo






The first quarter of 2017 was a busy period for the 787 program and time highlighted by the very successful first flight of the 787-10 yesterday at quarter end.  To the details of the quarter....

For the month of March, 2017 Boeing delivered 11 Dreamliners (4 x 787-8s and 7 x 787-9s) including the 200th 787-9 to be delivered to a customer. However two of these deliveries aren't confirmed: 1 787-8 ZD009 (LN 17, N947BA) left for Victorville to be stored but left under a Boeing flight number.  This aircraft was supposed to be delivered to Crystal Cruises who is now trying to sell it.  So far there aren't any buyers and is the second 787 that is up for sale.  The other 787 delivery in doubt is ZB703 (LN 533, HZ-AR11) for Saudi Arabian Ministry of Finance (leased to Saudi Arabian Airlines).  The aircraft was supposed to be delivered on March 30th but it is still parked on the Charleston flightline.  We'll know more about these two 787s when Boeing reveals its monthly order and delivery results hopefully on April 6th.  For the quarter, Boeing has delivered 32 787s (8 x 787-8s and 24 x 787-9s).  Total program deliveries stand at 532 (332 x 787-8, 200 x 787-9).  Boeing has delivered the 200th 787-9 to the Saudi Ministry of Finance which is leasing the aircraft to Saudi Arabian Airlines.  This is the aforementioned ZB703.

Production is going smoothly with Boeing rolling out 12 787s (including the second test flight 787-10) during this month and starting assembly on a further 13 787s.  Production efficiency declined due to lower deliveries in March.  In fact for the quarter  while the production rate was more or less on target deliveries were lower.  This is attributable to the introduction of the 787-10 into the production system.  Boeing transferred some 787 production aircraft to Everett from Charleston to mitigate production risk but it looks like Boeing can't transfer all of the Charleston 787 production thus deliveries fell.  During the 1st quarter, Charleston rolled out 12 787 (should be around 15) while delivering 10 (again vs. 15).  Everett, as I mentioned, picked up the slack in production (but not all of it) because of the 787-10 and rolled out 20 (vs. 24) and delivered 22 (vs. 28 including 2 early build deliveries). Production efficiency for March was 1.09 (an efficiency rating of 1 or lower is desirable as it shows declining inventory - roll outs vs. deliveries.  Charleston had a March efficiency ratio of 1.33 while Everett was 1.0.  Again this is all due to the introduction of the 787-10 into production and I expect that this will continue into early May until ZC002 (the third and last 787-10 flight test aircraft) has been rolled out from final assembly.

March deliveries were not all that interesting except for the two early build 787-8s (ZD007 and ZD009 and the 787-9 for the UAE Presidential (VIP) Flight.  For April, I believe that Boeing is targeting another 11 deliveries (3 x 787-8, 8 x 787-9).  This batch should include another early build 787-8 (ZD008) which will again go to Ethiopian Airlines as well as Air France's first direct purchased 787-9, they are currently operating 1 787-9 leased from AerCap.  Additionally, American Airlines will receive the last 787-8 that they have on order.

787-10
By far the most important event in the 787 program during the past quarter was the first flight of ZC001 (LN 528, N528ZC) the first 787-10.  I've included a few Boeing photos as well as embedded a couple of videos from that flight on March 31st.  The flight began much earlier than I anticipated, 9:38AM due to bad weather rolling in soon after.  The flight lasted 4 hours and 57 minutes and landed back at Charleston International Airport at about 2:35PM.  After landing the pilots reported no squawks and had run through the whole list of tests that they needed to perform as well as a few get ahead tasks.  The plan is for Boeing test pilots to fly ZC001 to Boeing Field late next week (I'm guessing next Friday) where it will be based for the remainder of the test flight program as will the other two test flight airplanes.  ZC036, the next 787-10 to fly and the first with GE engines is already on the Charleston flightline going through ground tests and I anticipate that this airplane will probably fly by the end of this month.  ZC002 will start final assembly by end of this week and I believe it should roll out by the end of the first week of May and join the flight test program around early June.  The 787-10 flight test and certification program should last about a year and there will be additional production ready 787-10 that will perform functionality and readiness testing (F & R)  similar to the 787-8 and 787-9 test programs.

Speaking of the flight test program, I will be attempting to track the flight test hours of the 787-10 flight test fleet similar to what I had done with the 787-8 and 787-9.  This is mainly keeping track of flight test as they're reported on FlightAware.com and flightradar24.com.  I will be keeping these logs on the spreadsheets in a tab called "787-10 Flight Test Hours."  You can view these spreadsheets through the link below.

787 Spreadsheets

I will also be posting updates to the test flight program on the blog as they become available.

Thursday, March 2, 2017

March production and delivery schedule for 787

With the 1st two months of the year in the books, Boeing is looking to finish out the 1st quarter in strong fashion.

Delivery wise, Boeing is hoping to deliver 11 787s. Some planned notable deliveries include early build 787-8s to Ethiopian and to a yet to be determine customer who is buying the air frame once bought by Crystal Cruises.  I must stress the deliveries are tentative as we have seen in the past that sometime they just don't occur.  ZD007 (LN 16, ET-ATH) was supposed to be delivered at the end of February and now it is scheduled to be delivered at the end of March.  ZD009 (LN 17) was going to be taken up by Crystal Cruises until they found out it was too small for their use.  They may have found a buyer but it is still unknown who or even if there is a new buyer.

The UAE government will be taking its second 787 and first 787-9 for Presidential/VIP duties in March. Other than that it will be a ho hum affair with deliveries to usual suspects like Saudi Arabian (2), Avianca (1), American (1), JAL (1), Air Canada (1), Virgin Atlantic (1) and Norwegian (1).  Six of the eleven have had their B-1 and one 787-8 (for Avianca) has had it customer flights.  The remaining 5 should have their first flight by March 15th.  Most deliveries (9 of 11) should occur in the second half of the month. Deliveries in March will heavily favor Everett as they should deliver 8 787 while Charleston will deliver 3.  This is due to the introduction of the 787-10 into final assembly thus mandating the need to have some production frames moved to Everett so as not to disrupt assembly of customer aircraft.

Production for the first half of March should see 6 787s start final assembly with another 6 rolling out by mid March.

Lastly, I'm hearing that the 787-10 should make its maiden flight by the end of the month.  March 31st is penciled in for the first flight date but I'll you all know as soon as I can get more clarity on this date.

Thursday, March 10, 2016

Terrible Teen Moves, seat delays and other 787 news



Well it's been a while since my last posting so let's get right into it.

Chris Edwards, a photographer and spotter at Everett got a lot of great detailed photos (which you can view on his Flickr page) of the movements of many of the early build 787-8s around Paine Field in the last couple of days.  A couple of 787s went to the new 777X static test building 45-12 that was just completed and from the photographs that Chris took, it appears that scaffolding and work platforms have been erected around ZD007 (LN 16) which is destined for Ethiopian and ZD009 (LN 17) which will go to Crystal Cruises.  This indicates that the these airplanes will be spending sometime in that building for the change incorporation and re-work that they need to have done.  It's interesting to note that none of the early build aircraft have engines on them but one early build 787-8 for Air Austral just returned from Victorville in a new color scheme for the Reunion-based carrier.  Still this aircraft is not expected to be delivered until May and is in fact just now getting its interior installed on the flightline at Everett.

Boeing is moving 787s out of the EMC (mostly) in order to create room for incoming KC-46 tankers to under go change incorporation and re-wok to get them up to USAF standards.  This is something I allude to in a post late last year.  I had also expected that Boeing would be reducing the number of 787 that are stored on the runway storage area (RWY11/29) but the number of aircraft has actually grown from 3 787-8 to now include 2 747-8s and a 787-9.  The latter is an aircraft for British Airways that is one of 2 787-9s that are being delayed to the British carrier due to supply issues with seat manufacturer Zodiac (yes, again). ZB368 (LN 386, G-ZBKG) and ZB369 (LN 404, G-ZBKH) are both being delayed due to manufacturing issues with seats though ZB370 (LN 406, G-ZBKI) will be delivered on time according to sources.  I'm still trying to ascertain the length of delay to the other two British Airways 787-9s.

In some what related news, because of the engine fire on ZB036 (LN 377, G-VDIA) for Virgin Atlantic that I had reported earlier, Boeing and Rolls Royce are now going through all Trent-1000 powered 787s and replacing a part.  It is not known what the part is or how the engine fire started.  The fact that the Trent powered 787s are still flying seems to indicate that both firms feel confident about the root cause and the solution of the fire.

It appears that United is now taking more 787-9s as they now have stated that they are pulling some 787 orders forward from 2020 to 2017.  If so it seems that they have converted some 787-10 orders to the 787-9.  This explains why we see more 787-9 for United on the firing order than what they have ordered.  They also converted some 787 orders into an order for 4 777-300ER.  What I'm not sure of is if they have exercised any 787 options but more will be revealed when Boeing updates their order and delivery web page in the first week of April but it is interesting to note that with this change in 787 orders, United has 27 787s left to be delivered.  That is 2 more than what they is currently shown on Boeing's site.  I'm thinking that United now has 21 787-9 on order of which they have 5 yet to be delivered while they have 22 787-10s still on order.  Interestingly, Boeing's weekly O&D update shows an addition of 25 737NGs and 4 777s which is corresponds to the order that United recently announced but there was also a decrease of 4 787s which I don't believe is attributable to United.  We'll see where the 787 cancellation came from in early April.

So far in March, Boeing has delivered 2 787s but according to sources they are planning to deliver 11 more 787s this month including 2 in Charleston that have yet to have their first flight and receive its paint job.  Still if they are able to deliver 13 787s this month it'll be a nice recovery for 787 deliveries after 3 months of slow delivery rates.

787 Full Production Table