Friday, January 22, 2010

As the 787 and 747 turns...a round up of 787 and 747 news


Boeing Photos

Well a few tid bits from these two programs came out from the usual suspects and the not so usual suspects.

First off, Bloomberg News had a nice article on the 787's battle of the bulge now that the maximum take off weight is 9.25 tons more than when the program first started. Now we do know that airplane 7, which is built, is the first block point aircraft to incorporate some weight saving measures and Boeing plans to have further weight savings starting with airplane 21. Boeing says that it still plans to meet all performance guarantees made to airlines for the 787 but the performance of the airplane won't be truly known until ZA004 with revised Trent 1000s engines is flying. In addition, Boeing plans to fly ZA100 and ZA102 with the revised engines will be flown to see how the production level aircraft will perform vs the test flight aircraft baseline performance.


Matt Cawby has been great with providing a visual record of the 787 progress in addition to written reports of what is happening at Everett. Last night he got some great video of LN 10 (ZA 103) coming out of the Boeing paint hangar. This airplane was painted white (a white tail) and was towed to the Boeing flight line to wait it's turn for the side of body modification. In addition Matt Cawby got some video of engine runs on ZA002 post fuel tank cleaning. Boeing is trying to get this airplane back in the air as soon as possible. Matt also broke the news of the start of 747-8 gauntlet testing and has further updates in his blog.



Guy Norris posted an update on both the 787 and 747. Currently ZA001 is in a plan lay up at Boeing Field to have more test flight equipment installed, calibrated and tested before continuing flight tests with flight test engineers aboard. ZA002 is continuing to have it's engines runs (see Matt Cawby's video) at Everett before rejoining the test program but I have to assume that all the test equipment testing and re-calibration work is complete and it should be a matter of days until this airplane is flying again for certification and TIA purposes. ZA004 is still getting ready for it's first flight but before then Boeing is conducting test of the emergency escape slides. Guy also has a nice update on the 747-8 confirming the the start of gauntlet testing and saying that taxi tests could occur late next week after safety of flight tests then followed by first flight around January 31st or February 1st.

As I mentioned earlier in this post, Matt Cawby got video of LN 10 (4th production 787) being pulled out of the Boeing paint hangar. This aircraft was painted all white. It was assumed, prior to yesterday that this airplane would be going to ANA and thus it should have been painted in the colors of ANA like the previous three production airplanes. But Flightblogger, Jon Ostrower, broke the news yesterday that this plane and airplane 16 will be delivered to LAN Airlines. Airplane 10 is probably painted as a white tail pending confirmation of the slot swap between ANA and LAN. Flightblogger revealed that the weight savings on airplanes 7 through 20 will come from changes in the wing skin but that after airplane 20 the 787 will have a higher MTOW (maximum take off weight). The increase in MTOW is on the order of about 9.25 tons which is what Bloomberg had reported.

Wednesday, June 17, 2009

Boeing Announces the start of final assembly on ZA100

Boeing has confirmed my earlier post from yesterday that ZA100, the 7th 787 to be built and the first production 787 for ANA has started final assembly. Here is Boeing's press release:


News Release Issued: June 17, 2009 6:32 PM EDT
Final Assembly Begins on First Boeing 787 Dreamliner for ANA
EVERETT, Wash., June 17 /PRNewswire-FirstCall/ -- Final assembly has begun on the first Boeing (NYSE: BA) 787 Dreamliner destined for delivery to launch customer ANA (All Nippon Airways) of Japan.

ANA and Boeing launched the 787 program with a firm order for 50 of the all-new composite jetliner. Deliveries are scheduled to begin in the first quarter of 2010.
Boeing and ANA celebrated the occasion with a traditional "Kagami wari" ceremony, the breaking open of a wooden "Taru" (sake barrel) lid with wooden mallets.
"This is a great day for the 787 team," said Scott Fancher, vice president and general manager of the 787 Dreamliner program. "In 2004, ANA demonstrated great faith in Boeing and the 787 by placing the largest launch order for any new airplane in Boeing history. Since then, the ANA team has been an integral part of developing the 787 family of airplanes.
"Speaking for our entire global 787 team, including our partners, I'd like to say we are honored by ANA's commitment to the Dreamliner," Fancher said. "We look forward to our continued partnership as we prepare the 787 to enter commercial service."
"Congratulations to Boeing on the start of the historic assembly of the first 787 Dreamliner for commercial flight," said ANA President & CEO Shinichiro Ito. "As the launch customer, we are delighted and excited to see the achievement of this milestone and to have worked closely together to reach this day. We look forward to the start of the 787 flight test program and delivery into our fleet next year."
The 787 Dreamliner has 865 orders from 56 airlines, making it the fastest-selling all-new jetliner in aviation history.
Pictured from left to right are: Kinichiro Suetsugu, manager - ANA U.S. Engineering; Takeo Kikuchi, general manager - ANA U.S. Engineering; Scott Fancher, vice president and general manager - 787 program and Mike Fleming, director of Services and Support - 787 program.
More information: http://www.boeing.com/commercial/787family/
Neg. K64723
Contact:
Mary Hanson
787 Communications
+1-206-898-4749
mary.hanson@boeing.com
SOURCE: Boeing
Web site: http://www.boeing.com/

Thursday, May 28, 2009

787 News - May 28,2009

Not too much to report except:

1) Boeing booked 5 orders from an unidentified customer for the 787. No word on which type (-8 or -9) though that will probably be revealed in a couple of weeks when Boeing releases its monthly order and deliviery numbers. Interestingly Boeing also booked a cancellation of 5 767s at the same time so I wonder if the cancellation has anything to do with the order for 5 airplanes? The only airlines that have the 767 on order (passenger version) are ANA, JAL and Lan. These carriers also have already placed orders for the 787 as well.

2) The LCF is on its way to Everett this morning from Charleston. It might be carrying the main fuselage section for ZA100 though we'll know a little later today.

No word on the start of intermediate gauntlet testing yet.

Tuesday, May 26, 2009

Guy Norris: Intermediate Gauntlet May Start On May 28th.

UPDATE: The LCF did fly in the forward fuselage section for ZA100 (the first production 787 for ANA). All that's left is the main fuselage section and final assembly can start on this airplane.

Some news on the schedule for the 787 first flight. Guy Norris is saying that intermediate gauntlet could start as early as this Thursday (May 28th) but it seems that Boeing may still be finalizing the final content of the intermediate. Guy reported that a final pre-intermediate gauntlet test meeting has been pushed back until tomorrow from today.

Also Matt Cawby is reporting on his web site that ZA001 has undergone VHF/RF radio checks until about 2 PM Monday afternoon when they closed down for the Memorial Day holiday. Additionally, Matt reported that the APU was tested twice, once on right common motor controller starter and the other time on the electric motor pump circuit. Matt also said that full gear swing tests were conducted while the aircraft was in the air mode.

Guy's Report
Matt's Report

Finally, it looks like the LCF might be flying in the nose section for ZA100 this afternoon.

Monday, May 4, 2009

More 787 movement


When it rains, it pours...I've been using that comment more often in the last few weeks for many reasons. The reason today in this posting is because Dreamliner 2 (ZA002) has left building 40-26 yesterday and made its way to the same paint hangar that Dreamliner 1 had until recently had occupied.

It's getting its paint job though I'm not sure what paint scheme it'll be painted in. There is also no word on where it will go after the paint job...it could go to the flight line, building 40-24 (767 line) or even back to 40-26. It will have to go through the same set of gauntlet tests that Dreamliner 1 is going through.

This also opens up a spot on the 787 (assuming it doesn't go back to 40-26) for Dreamliner 7 (ZA100). It's not known if Dreamliner 4 through 6 have move down one spot on the line or not though I do think that the last two sections for ZA100 should be in soon.
Charles Concklin is gracious enough to allow me to link to his pictures of Dreamliner 2 being rolled to the paint hangar.

Monday, April 20, 2009

Flightblogger: Factory gauntlet begins at 6:30AM PT on April 20th

UPDATE (April 20, 2009, 3:16PM): Boeing has confirmed to Flightblogger that the factory gauntlet has indeed started and should finish by tomorrow morning. An external computer has been hooked up to Dreamliner 1 to test how the airplane "flies." Read Jon's post here.


According to Jon Ostrower, ZA001 will start the first of three gauntlet tests this morning at around 6:30 AM PT. It is expected that this gauntlet should be done by early morning on April 21st thus paving the way for ZA001 to be moved to the flightline.

Jon also confirmed that the flight test wiring is mostly connected and all the external panels have been reinstalled.

Boeing is also getting an accurate measurement of the 787 OEW (operating empty weight) by removing the ballast and weighing the aircraft. It's not known what the result was but it is widely expected to be over the contractual weight.

Jon also reported that the rear fuselage section that was just delivered for ZA100 (Dreamliner 7) was 96% complete. Read Jon's post here.

As I reported on this blog earlier, it is expected that all traveled work in the 787 program will be eliminated starting with Dreamliner 8 (ZA101).

Lastly, Matt Cawby on his photoblog reported that Dreamliner 1 completed engine and APU fire protection systems tests in both the ground and air modes. See Matt's posting here.