Sources are indicating some slips in 787 deliveries for September but so far it doesn't seem that any of the slips are into October....yet. The first for Qatar Airways, ZA461 (LN 58, A7-BCB) and ZA119 (LN 69, JA814A) bot hare now tentatively scheduled to deliver around September 20th. Additionally Boeing is working some unknown issues with ZA182 (LN 70, JA828J) and delivery may take place around September 5th but may be even later.
The information thus far hasn't indicated any slide of September deliveries into October just as yet but one has to wonder what are the issues that are causing the delivery slide.
Still no word on the deliveries to Air India though there is a rumor that contractual delivery was made on ZA233 (LN 29, VT-AND) and ZA236 (LN 35, VT-ANH) on Aug. 31st. This is yet unconfirmed and we may not know until Boeing releases its monthly orders and deliveries report for August within the next 10 days. The airplanes are being held in Charleston over some unspecified engine issue is resolved. I don't know if it has anything to do with the GEnx engine failure from July or not. I'll keep an eye on it.
Showing posts with label ZA233. Show all posts
Showing posts with label ZA233. Show all posts
Saturday, September 1, 2012
Friday, August 24, 2012
787 deliveries on tap for the last week of August
Today, according to sources, Boeing may have made a contractual delivery of Air India's first 787. ZA236 (LN 35, VT-ANH) was seen at the Boeing Charleston Delivery Center today and a source did say that the aircraft may be delivering today (contractually). The contractual delivery date is the date that the paperwork is signed and the final delivery payment is made to Boeing by the customer. When asked if this was the case, Boeing spokesperson, Candy Eslinger, replied: "The Air India delivery team is in South Carolina for the delivery scheduled next week." This is confirmation that Boeing will be delivering at least one if not two 787s to Air India this month. I have heard that ZA236 would deliver on Aug. 27 (ceremonial delivery perhaps) and fly away that afternoon/evening for New Delhi. For now there isn't any confirmation about the contractual delivery being made though I suspect that this event may have taken place today (Aug. 24th). In addition to ZA236 being delivered this month, a source has told me that the following deliveries may take place during the next week. Please take this information with a grain of salt as we have seen that some may not materialize due to different circumstances.
ZA536 (LN 68, CC-BBA) to LAN on Aug. 27
ZA461 (LN 58, A7-BCB) to Qatar Airways on Aug. 30
ZA118 (LN 67, JA813A) to ANA on Aug. 30
ZA182 (LN 70, JA828J) to Japan Airlines on Aug. 30 (this airplane has had only one test flight)
ZA233 (LN 29, VT-AND) to Air India on Aug. 31
Additionally ZA237 (LN 46, VT-ANI) is almost ready for delivery but doesn't have a delivery date as of yet. It appears that Air India is trying to pick up one delivery ready 787 each week so it could be that ZA237 could deliver in September. There are two other 787s for Air India both built at Charleston that have yet to take their B-1 flights so I anticipate that those deliveries may happen in late September but more likely in October.
There is also further information on September deliveries which, once again, should be taken with a grain of salt.
ZA119 (LN 69, JA814A) to ANA on Sept. 12
ZA263 (LN 71, ET-AOR) to Ethiopian on Sept. 18 (hasn't taken its B-1 yet)
ZA288 (LN 53, N20904) to United on Sept. 18
ZA178 (LN 27, JA824J) to Japan Airlines on Sept. 20 (hasn't taken its B-1 yet)
ZA463 (LN 64, A7-BCL) to Qatar Airways on Sept. 25 (hasn't taken its B-1 yet)
ZA135 (LN 66, JA815A) to ANA on Sept. 25 (hasn't taken its B-1 yet)
ZA382 (LN 43, B-2727) to China Southern on Sept. 27 (hasn't taken its B-1 yet)
All told the total number of deliveries in August and September may total 16, IF this scheduled is kept.
ZA536 (LN 68, CC-BBA) to LAN on Aug. 27
ZA461 (LN 58, A7-BCB) to Qatar Airways on Aug. 30
ZA118 (LN 67, JA813A) to ANA on Aug. 30
ZA182 (LN 70, JA828J) to Japan Airlines on Aug. 30 (this airplane has had only one test flight)
ZA233 (LN 29, VT-AND) to Air India on Aug. 31
Additionally ZA237 (LN 46, VT-ANI) is almost ready for delivery but doesn't have a delivery date as of yet. It appears that Air India is trying to pick up one delivery ready 787 each week so it could be that ZA237 could deliver in September. There are two other 787s for Air India both built at Charleston that have yet to take their B-1 flights so I anticipate that those deliveries may happen in late September but more likely in October.
There is also further information on September deliveries which, once again, should be taken with a grain of salt.
ZA119 (LN 69, JA814A) to ANA on Sept. 12
ZA263 (LN 71, ET-AOR) to Ethiopian on Sept. 18 (hasn't taken its B-1 yet)
ZA288 (LN 53, N20904) to United on Sept. 18
ZA178 (LN 27, JA824J) to Japan Airlines on Sept. 20 (hasn't taken its B-1 yet)
ZA463 (LN 64, A7-BCL) to Qatar Airways on Sept. 25 (hasn't taken its B-1 yet)
ZA135 (LN 66, JA815A) to ANA on Sept. 25 (hasn't taken its B-1 yet)
ZA382 (LN 43, B-2727) to China Southern on Sept. 27 (hasn't taken its B-1 yet)
All told the total number of deliveries in August and September may total 16, IF this scheduled is kept.
Labels:
787,
Air India,
ANA,
Boeing,
Boeing Charleston,
China Southern,
Ethiopian,
JAL,
LAN,
Qatar Airways,
United Airlines,
ZA118,
ZA119,
ZA182,
ZA233,
ZA236,
ZA237,
ZA263,
ZA461,
ZA536
Tuesday, July 17, 2012
Updated 787 delivery info for July and August
There is new updated delivery information from a variety of sources concerning future deliveries of the 787. First off, ANA apparently has taken delivery of another 787 probably yesterday. ZA508 (LN 51, JA811A) was delivered and should fly to Japan tonight. Apparently that looks to be the only delivery being made this month. However there is more clarity on future deliveries including those to Air India.
Air India - Ajit Singh, the Minister of Civil Aviation, reported that the GoI's CCEA should be taking up the matter of the compensation deal between Air India and Boeing in about 15 days. Now how soon after approval will these airplanes be delivered is another question. According to a posting on airliners.net, the carrier can take delivery of four '87s before August 5th from the flightline at Charleston. This is a rumor and there is nothing official to back it up as of yet. We just have to stay tuned for this drama to play out.
LAN - The first aircraft for LAN has now been moved to the flightline and will presumably be starting the pre-flight testing prior to its B1 flight. There has been some confusion as to when LAN will take this airplane but now there seems to be some clarification. The CEO of LAN told Flightglobal that the carrier will take delivery in September.
ANA - ANA's 787 fleet is well into double digits with several more on the way. There are 4 787s that are winding its way through pre-flight at Everett. According to a posting in airliners.net, ZA100 (LN 7, JA803A) should be making it's B1 flight tomorrow (July 18). This airplane is projected (of course not certain) to deliver around August 8th. The three other 787s are all airplanes that didn't need any re-work done at the EMC. It is quite possible that all these four airplanes can deliver in August though it's more likely that a couple will deliver in August and a couple more in September from this batch. There are still 2 more late build airplanes that are in storage that wold have to finish some amount of change incorporation and I would expect that these airplanes will be delivered later this fall. a, ZA118 is registered as JA813A (LN 67).
Finally, here's an interesting article that sums up Farnborough 2012 air show from aerospace analyst Saj Ahmad.
Air India - Ajit Singh, the Minister of Civil Aviation, reported that the GoI's CCEA should be taking up the matter of the compensation deal between Air India and Boeing in about 15 days. Now how soon after approval will these airplanes be delivered is another question. According to a posting on airliners.net, the carrier can take delivery of four '87s before August 5th from the flightline at Charleston. This is a rumor and there is nothing official to back it up as of yet. We just have to stay tuned for this drama to play out.
LAN - The first aircraft for LAN has now been moved to the flightline and will presumably be starting the pre-flight testing prior to its B1 flight. There has been some confusion as to when LAN will take this airplane but now there seems to be some clarification. The CEO of LAN told Flightglobal that the carrier will take delivery in September.
ANA - ANA's 787 fleet is well into double digits with several more on the way. There are 4 787s that are winding its way through pre-flight at Everett. According to a posting in airliners.net, ZA100 (LN 7, JA803A) should be making it's B1 flight tomorrow (July 18). This airplane is projected (of course not certain) to deliver around August 8th. The three other 787s are all airplanes that didn't need any re-work done at the EMC. It is quite possible that all these four airplanes can deliver in August though it's more likely that a couple will deliver in August and a couple more in September from this batch. There are still 2 more late build airplanes that are in storage that wold have to finish some amount of change incorporation and I would expect that these airplanes will be delivered later this fall. a, ZA118 is registered as JA813A (LN 67).
Finally, here's an interesting article that sums up Farnborough 2012 air show from aerospace analyst Saj Ahmad.
Tuesday, July 3, 2012
787 Movement - July 3, 2012
There was quite a bit of moving around for Boeing's 787 inventory both in Everett and in Charleston. To start, Boeing confirmed that the two Air India 787s that are ready for delivery were flown to Charleston to free up space on the Everett ramp. Boeing said that it was a good move as several of the first few Charleston built planes are also destined for Air India. Speaking of Air India 787 deliveries, there is word that the Ministry of Aviation won't sign off on the deal until next week because one of the ministers is on vacation. Apparently in India business stops if someone is out on vacation. IF, and that is really big IF, everything get signed off by the government of India deliveries conceivably can start towards the end of next week or early the following week. There is a great article in the Charleston Regional Business Journal about Air India, the 787s and the attitude behind the whole fiasco but it sums up the attitude of the GoI and Air India quite nicely.
Boeing flew ZA461 (LN 58, A7-BCB) to Boeing Field on Sunday in preparation for it to fly to Farnborough on Thursday. Word is delivery to Qatar Airways should occur the week of July 16th IF (another big IF) there are no contractual hang ups. A date has not been set and given the unpredictability of Qatar CEO Akbar Al Baker this rough time frame could slide. Qatar's pilots still has to fly the aircraft I believe and this probably won't occur until after the Farnborough Air Show. The airplane is flying July 9th to July 11th and I anticipate that it should return to Everett on July 11th. When it returns to Everett this plane will be carrying two Qatar Airways pilots who might conduct customer flights and may eventually ferry the aircraft back to Doha when delivery is complete. It is conceivable that Qatar could take delivery before Air India making this carrier the third airline to fly the 787 and the first one outside of Japan.
ANA took delivery of its 10th 787 on Sunday, ZA509 (LN 56, JA812A) then flew to Haneda International Airport last night. ANA should be taking delivery of 4 to 5 more 787s by the end of August given the number that is in pre-flight. Another ANA 787 will be pushed out the door tonight. This airplanes is ZA119 (LN 69) will go to the 40-51 ramp to finish off minor assembly tasks before going off to paint.
On the production front, Boeing pulled out ZA238 (LN 54) from building 88-03 in Charleston. It is now on the flight line along with the other three Air India bound 787s. No word on if assembly has started on ZA431 (LN 76) for Hainan Airlines but I'm assuming for now that parts are still arriving. At Everett, Boeing has moved another 787 inside the EMC. ZA460 (LN 57, A7-BCA) for Qatar Airways is now inside where it is continuing with change incorporation along with units for China Southern, United and JAL. One or both of the China Southern airplanes should be out by August where it will go through painting and go into pre-flight. This airline can possibly take delivery in September.
I have updated the tables below to reflect the current disposition of all the 787s that are in production or have been delivered. Have a safe and Happy 4th of July!
Boeing flew ZA461 (LN 58, A7-BCB) to Boeing Field on Sunday in preparation for it to fly to Farnborough on Thursday. Word is delivery to Qatar Airways should occur the week of July 16th IF (another big IF) there are no contractual hang ups. A date has not been set and given the unpredictability of Qatar CEO Akbar Al Baker this rough time frame could slide. Qatar's pilots still has to fly the aircraft I believe and this probably won't occur until after the Farnborough Air Show. The airplane is flying July 9th to July 11th and I anticipate that it should return to Everett on July 11th. When it returns to Everett this plane will be carrying two Qatar Airways pilots who might conduct customer flights and may eventually ferry the aircraft back to Doha when delivery is complete. It is conceivable that Qatar could take delivery before Air India making this carrier the third airline to fly the 787 and the first one outside of Japan.
ANA took delivery of its 10th 787 on Sunday, ZA509 (LN 56, JA812A) then flew to Haneda International Airport last night. ANA should be taking delivery of 4 to 5 more 787s by the end of August given the number that is in pre-flight. Another ANA 787 will be pushed out the door tonight. This airplanes is ZA119 (LN 69) will go to the 40-51 ramp to finish off minor assembly tasks before going off to paint.
On the production front, Boeing pulled out ZA238 (LN 54) from building 88-03 in Charleston. It is now on the flight line along with the other three Air India bound 787s. No word on if assembly has started on ZA431 (LN 76) for Hainan Airlines but I'm assuming for now that parts are still arriving. At Everett, Boeing has moved another 787 inside the EMC. ZA460 (LN 57, A7-BCA) for Qatar Airways is now inside where it is continuing with change incorporation along with units for China Southern, United and JAL. One or both of the China Southern airplanes should be out by August where it will go through painting and go into pre-flight. This airline can possibly take delivery in September.
I have updated the tables below to reflect the current disposition of all the 787s that are in production or have been delivered. Have a safe and Happy 4th of July!
Labels:
787,
88-03,
Air India,
Boeing,
Boeing Charleston,
Boeing Field,
China Southern,
EMC,
Everett,
Hainan Airlines,
Qatar Airways,
ZA119,
ZA233,
ZA236,
ZA237,
ZA238,
ZA431,
ZA460,
ZA461
Sunday, July 1, 2012
Air India 787s on the move, Qatar 787 readied for Farnborough
Over the weekend Matt Cawby spotted the two Air India 787s that are ready for delivery sporting temporary US registration numbers on their fuselages. This lead to speculation that the aircraft are to be flown out of Everett for possible storage, maybe in the desert. Well the speculation was mostly correct. The two 787s, ZA233 (LN 29,VT-AND) and ZA236 (LN 35, VT-ANH) will be flown to Charleston to join sistership ZA237 (LN 46, VT-ANI) on Monday, July 2nd. Now the reason why it is being flown to Charleston isn't officially disclosed but the obvious reason could be for a triple delivery to AIr India and that still could happen but sources have told me that delivery to Air India is still listed as "TBD". It is conceivable that these three airframes for Air India will be delivered from Charleston but another reason is that if Boeing is able to turn the keys over to the carrier between July 4th and July 8th, they will be unable to fly away during those dates as the runway at Everett will be closed. This way Boeing leaves open the delivery and fly away during those dates by transferring these airplanes to Charelston. The most likely reason is to free up space in Everett for other aircraft that are ready to be delivered. Already ZA135 (LN 66, JA815A) is already out of paint and need to prepare for pre-flight. ZA100 (LN 7, JA803A) is currently sitting in the fuel dock sans its rudder (don't know why) this aircraft is projected to be delivered at the end of July but it still needs to have its rudder reattached and go through pre-flight. The pace of aircraft reaching the flightline ready for pre-flight is quickening and Boeing needs the space. Given the uncertainty of the Air India deliveries this is a good move to keep the pace at Everett moving. ZA461 (LN 58, A7-BCB) for Qatar Airways is already at Boeing Field to prepare to fly to Farnborough later this week this airplane is still projected to deliver later this month. Another flightline stall should open up tomorrow as ZA509 (LN 56, JA812A) will deliver today, as far as I know, and should fly away tomorrow July 2. ZA508 (LN 51, JA811A) should deliver around July 11th with fly away on July 12th.
On Tuesday another line move should occur which will push out ZA119 (LN 69) for ANA and will mark the start of final assembly for ZA537 (LN 74) for LAN.
On Tuesday another line move should occur which will push out ZA119 (LN 69) for ANA and will mark the start of final assembly for ZA537 (LN 74) for LAN.
Tuesday, June 12, 2012
June 12, 2012 787 delivery watch and other 787 news
UPDATE (6/12/12, 8:45 PM): There will be a line move tomorrow but on top of that there was some movement of several Qatar Airways 787s.
ZA118 (LN 67) will go straight from 40-26 to the paint hangar 45-01. Sounds like there aren't very many jobs to do on this one and can go to preflight.
ZA461 (LN 58) has gone from Stall 106 to the paint hangar 45-04 sounds like we'll finally see a 787 in Qatar Airways color scheme.
ZA460 (LN 57) went to EMC position Z
ZA511 (LN 63) went to EMC position 3
ZA463 (LN 64) went to EMC position E replacing ZA100 (LN 7)
ZA100 (LN 7) went to paint hangar 45-03 for painting seems this one is done
Lots of news out today.
ZA509 flies
ZA509 (LN 56, JA812A) flew for the first time this afternoon. This is the first 787 to conduct a a B-1 flight in over three weeks. Boeing had filed numerous flight plans over the past few days but it finally took off this afternoon. If there aren't too many issues then it should deliver by the end of this month. it is still unknown why it has taken so long between B-1 flights for the787 and why ZA506 (LN 47, JA809A) and ZA509 (LN 48, JA810A) have not been delivered to ANA. ZA506 did have an experimental sticker and an N registration on it but those have since been removed. I can speculate that this airplane conducted some certification activities, possibly connected to software upgrades, and Boeing is waiting on final FAA approval before signing the airplanes over to ANA. The fact that ZA509 finally took flight might be an encouraging sign that is approval is close or already in hand.
United to take 787 delivery in September
Jeff Smisek, the CEO of United said today at a shareholder meeting that the airline will take delivery of the first Dreamliner in September and will have 5 to 6 787s by the end of the year. Currently there are 5 787s that are assembled and two of the five that are currently undergoing change incorporation. ZA290 (LN 77) will be assembled in Everett and I expect that this airplane will enter final assembly sometime around early September. Boeing can certainly deliver all these 787s to UAL by the end of the year as they probably don't have much change incorporation to be done.
Air India
The word is the the GoI will take up the compensation agreement between Air India and Boeing this week and that first delivery should take place next week. Though this is India and they do love their little drama so I'm not going to believe it until all three 787s, ZA 233 (LN 29, VT-AND), ZA236 (LN 35, VT-ANH) and ZA237 (LN 46, VT-ANI), are all on Indian soil.
Qatar Airways
Of all the 787 that would make a lot of noise I was expecting Qatar Airways, not Air India but some how Air India was able to supplant Akbar Al-Baker as the most annoying (and most dislike) customer in the airline industry. I know I'm comparing an individual with a company but you get the idea. Anyway we've heard not a peep from one of the most vocal airlines in the world. I did get word that delivery of Qatar's first 787 should take place by the end of the month. Further I got confirmation of the following piece of information that was in a Qatar Airways press release:
The Doha-based airline is preparing to take delivery of five 787s during 2012, with the first set to arrive in Qatar this summer.
Production
I expect there to be another line move if not today then by Thursday at the latest. LN 67 should be pushed out and should be in a similar condition as LN 66. This airplane is also for ANA and should most certainly deliver next month. Related to production, Flightglobal writer Steven Trimble came out with an article saying that Boeing is pushing the activation of the surge line to the end of September, ostensibly the start of the 4th quarter. The reason being is that Boeing wants to use the line for chane incorporation for the 39 787s that are out on the Everett ramp. According to Trimble the line is completely ready to support production of the 787s but Boeing wants to use it for change incorporation during the summer. This may make sense as it have two positive effects...1) it allows Boeing to work through the 39 planes that are still need to be finished that more faster thus reducing inventory on the balance sheet and boking revenues on the income statement and 2) it allows Boeing to refine and double check it plans for the surge line and for the rate increase to 5/month that will come this fall. Boeing and its supplies cannot fail on this rate increase and must make sure that it occurs seamlessly across the supply chain. I wouldn't be surprised if some of the 787s that are currently in final assembly are moved to the surge line to finish off some of the minor assembly tasks.
787-9/787-10
Jim Albaugh speaking yesterday said that the 787-10 would be launched before a 777X as it is the derivative that is the most further along. According to Scott Hamilton who cites a Bernstein Research note, the 787-10 launch is almost a certainty. The 787-9 development is proceeding well and will go into production on the surge line next year.
The same Bernstein Research note also raised Boeing outlook based on improvement in the 787 program and in particular the production. It cites supplier performance as a huge factor in the improved production outlook. See the Reuters article that talks about the Bernstein note here.
Performance of ANA 787s
Word is coming out that the performance of ANA 787s on long haul flights is 21% better compared to the 767-300ER that they're replacing. This is compared to the 20% that Boeing was aiming for when they started marketing the 787 to the airlines. These are the overweight aircraft that are equipped with the Trent 1000 package "B" engines that have SFC bought to within 1% of Rolls Royce's performance guarantees. One can only imagine what the performance will be like on the later 787s which are delivered at the promise weight (Boeing is getting there) along with the improved engines coming out from both GE (PIP2) and Rolls Royce (package "C").
ZA118 (LN 67) will go straight from 40-26 to the paint hangar 45-01. Sounds like there aren't very many jobs to do on this one and can go to preflight.
ZA461 (LN 58) has gone from Stall 106 to the paint hangar 45-04 sounds like we'll finally see a 787 in Qatar Airways color scheme.
ZA460 (LN 57) went to EMC position Z
ZA511 (LN 63) went to EMC position 3
ZA463 (LN 64) went to EMC position E replacing ZA100 (LN 7)
ZA100 (LN 7) went to paint hangar 45-03 for painting seems this one is done
Lots of news out today.
ZA509 flies
ZA509 (LN 56, JA812A) flew for the first time this afternoon. This is the first 787 to conduct a a B-1 flight in over three weeks. Boeing had filed numerous flight plans over the past few days but it finally took off this afternoon. If there aren't too many issues then it should deliver by the end of this month. it is still unknown why it has taken so long between B-1 flights for the787 and why ZA506 (LN 47, JA809A) and ZA509 (LN 48, JA810A) have not been delivered to ANA. ZA506 did have an experimental sticker and an N registration on it but those have since been removed. I can speculate that this airplane conducted some certification activities, possibly connected to software upgrades, and Boeing is waiting on final FAA approval before signing the airplanes over to ANA. The fact that ZA509 finally took flight might be an encouraging sign that is approval is close or already in hand.
United to take 787 delivery in September
Jeff Smisek, the CEO of United said today at a shareholder meeting that the airline will take delivery of the first Dreamliner in September and will have 5 to 6 787s by the end of the year. Currently there are 5 787s that are assembled and two of the five that are currently undergoing change incorporation. ZA290 (LN 77) will be assembled in Everett and I expect that this airplane will enter final assembly sometime around early September. Boeing can certainly deliver all these 787s to UAL by the end of the year as they probably don't have much change incorporation to be done.
Air India
The word is the the GoI will take up the compensation agreement between Air India and Boeing this week and that first delivery should take place next week. Though this is India and they do love their little drama so I'm not going to believe it until all three 787s, ZA 233 (LN 29, VT-AND), ZA236 (LN 35, VT-ANH) and ZA237 (LN 46, VT-ANI), are all on Indian soil.
Qatar Airways
Of all the 787 that would make a lot of noise I was expecting Qatar Airways, not Air India but some how Air India was able to supplant Akbar Al-Baker as the most annoying (and most dislike) customer in the airline industry. I know I'm comparing an individual with a company but you get the idea. Anyway we've heard not a peep from one of the most vocal airlines in the world. I did get word that delivery of Qatar's first 787 should take place by the end of the month. Further I got confirmation of the following piece of information that was in a Qatar Airways press release:
The Doha-based airline is preparing to take delivery of five 787s during 2012, with the first set to arrive in Qatar this summer.
The carrier will initially operate the aircraft on intra-Gulf routes to provide flight crew with training hours before Qatar Airways’ 787 is scheduled to appear on static display at the Farnborough Air Show in July and then enter its first long-haul commercial service on the Doha – London Heathrow route.If so then Boeing will need to deliver Qatar's first 787 by the end of this month if it is to conduct inter-Gulf flights for a week and then go to Farnborough for the air show which starts July 9th. It is entirely possible that the airline can take delivery by the end of the first week of July and then fly it to Farnborough for the show. I say this because as of today the plane is still in a flightline stall and there is still work being done on the aircraft and has yet to run its engines for the first time let alone make a B-1 flight. If ZA461 (LN 58) isn't on the ramp at Farnborough a 777-300ER would be in its place) then you can expect U-Turn Al to be back to his normally bombastic self thus regaining his title over Air India.
Production
I expect there to be another line move if not today then by Thursday at the latest. LN 67 should be pushed out and should be in a similar condition as LN 66. This airplane is also for ANA and should most certainly deliver next month. Related to production, Flightglobal writer Steven Trimble came out with an article saying that Boeing is pushing the activation of the surge line to the end of September, ostensibly the start of the 4th quarter. The reason being is that Boeing wants to use the line for chane incorporation for the 39 787s that are out on the Everett ramp. According to Trimble the line is completely ready to support production of the 787s but Boeing wants to use it for change incorporation during the summer. This may make sense as it have two positive effects...1) it allows Boeing to work through the 39 planes that are still need to be finished that more faster thus reducing inventory on the balance sheet and boking revenues on the income statement and 2) it allows Boeing to refine and double check it plans for the surge line and for the rate increase to 5/month that will come this fall. Boeing and its supplies cannot fail on this rate increase and must make sure that it occurs seamlessly across the supply chain. I wouldn't be surprised if some of the 787s that are currently in final assembly are moved to the surge line to finish off some of the minor assembly tasks.
787-9/787-10
Jim Albaugh speaking yesterday said that the 787-10 would be launched before a 777X as it is the derivative that is the most further along. According to Scott Hamilton who cites a Bernstein Research note, the 787-10 launch is almost a certainty. The 787-9 development is proceeding well and will go into production on the surge line next year.
The same Bernstein Research note also raised Boeing outlook based on improvement in the 787 program and in particular the production. It cites supplier performance as a huge factor in the improved production outlook. See the Reuters article that talks about the Bernstein note here.
Performance of ANA 787s
Word is coming out that the performance of ANA 787s on long haul flights is 21% better compared to the 767-300ER that they're replacing. This is compared to the 20% that Boeing was aiming for when they started marketing the 787 to the airlines. These are the overweight aircraft that are equipped with the Trent 1000 package "B" engines that have SFC bought to within 1% of Rolls Royce's performance guarantees. One can only imagine what the performance will be like on the later 787s which are delivered at the promise weight (Boeing is getting there) along with the improved engines coming out from both GE (PIP2) and Rolls Royce (package "C").
Labels:
777X,
787-10,
787-9,
Air India,
ANA,
Everett,
Farnborough,
Farnborough 2012,
Qatar Airways,
Trent 1000,
United Airlines,
ZA233,
ZA236,
ZA237,
ZA290,
ZA461,
ZA506,
ZA507,
ZA508,
ZA509
Wednesday, June 6, 2012
Air India and Boeing come to an agreement
Media outlets in of India are reporting that Air India and Boeing have come to an agreement over the 787 delays. Those reports did not specify the form of compensation though it may involve Air India paying less for each 787 as they are delivered. The agreement has to be approved by the Government of India so that is a reason to be cautious of this agreement. It was the Government of India that insisted on more compensation than had been previously agreed with Boeing.
If approval is given, Air India will take delivery of three 787s: ZA233 (LN 29, VT-AND), ZA236 (LN 35, VT-ANH), ZA237 (LN 46, VT-ANI) all in June. ZA233 is already to go now and I suspect that ZA236 is not that far behind. ZA237 is being painted and has still go through a few more Boeing test flights as well customer tests before it is delivered by the end of this month.
If the approval is given, Boeing can potentially deliver 8 787s this month. 4 787s to ANA that are on the flightline right now: ZA506 (LN 47, JA809A), ZA507 (LN 48, JA810A), ZA508 (LN 51, JA811A), ZA509 (LN 56, JA812A). Additionally Boeing can deliver ZA461 (LN 58) to Qatar Airways this month. This would make 8 airplanes including the three for Air India. ZA135 (LN 66) is an unknown but should be ready for delivery if not by the end of June then certainly in early to mid July.
If approval is given, Air India will take delivery of three 787s: ZA233 (LN 29, VT-AND), ZA236 (LN 35, VT-ANH), ZA237 (LN 46, VT-ANI) all in June. ZA233 is already to go now and I suspect that ZA236 is not that far behind. ZA237 is being painted and has still go through a few more Boeing test flights as well customer tests before it is delivered by the end of this month.
If the approval is given, Boeing can potentially deliver 8 787s this month. 4 787s to ANA that are on the flightline right now: ZA506 (LN 47, JA809A), ZA507 (LN 48, JA810A), ZA508 (LN 51, JA811A), ZA509 (LN 56, JA812A). Additionally Boeing can deliver ZA461 (LN 58) to Qatar Airways this month. This would make 8 airplanes including the three for Air India. ZA135 (LN 66) is an unknown but should be ready for delivery if not by the end of June then certainly in early to mid July.
Wednesday, May 30, 2012
Boeing readies more ANA 787s but AI planes are in limbo
Where to begin as there's a lot of new stuff.
First let's take a look at the positives. Boeing has 4 787s being readied at Everett for ANA. These are ZA506 (LN 47, JA809A), ZA507 (LN 48, JA810A), ZA508 (LN 51, JA811A), and ZA509 (LN 56, JA812A). ZA 508 is currently in the paint hangar but this plane had spent some time at EMC so I do believe that it is getting its aqueous wash and paint job done before being pulled to the fuel dock for fueling tests then to the flightline for mini gauntlet, engine start and first flight. Thus Boeing will have 4 787s ready for ANA in June maybe more. There has been a line move and currently the 4 787s that are inside 40-26 are ZA135 (LN 66, position 4), ZA118 (LN 67, position 3), ZA536 (LN 68, position 2) and ZA119 (LN 69, position 1). All but ZA536 are for ANA with ZA536 going to LAN. It is conceivable but not certain that ZA135 can go straight to paint and flightline with its engines and start preparation for delivery in about 2 weeks and can possibly be delivered at the end of June. This will be a major milestone for Boeing when it happens. Also ZA461 (LN 58) has made an appearance at the Everett Fuel Dock and I believe that this airplane is being prepared for delivery. I expect it will go into the paint hangar shortly before re-emerging for pre-delivery tests and final delivery to Qatar Airways in June and on display at Farnborough in July. Lastly, ZA237 (LN 46) has filed a flight plan fro Charleston to Fort Worth so this airplane can be painted for Air India. It is currently still in Charleston delayed by weather in the Dallas area. This last point is a nice lead into....
The Negatives
Only one (HUGE) negative which Air India. and here I just don't know where to start my rant. I (and probably 99.9% of of the world) thought that the issue of compensation to Air India for the delays was settled. According to the Govt. of India it is not and thus Boeing may have a dozen 787s for Air India sitting on the ramps at Everett and Charleston waiting to be delivered. The Air India debacle is a case study on how not to run an airline particularly when you are government owned and you have bureaucrats who know nothing of the airline industry making key decisions. ZA233 (LN 29, VT-AND) is all ready to be delivered and I suspect so is ZA236 (LN 35, VT-ANH). How long it will take to complete the negotiations on compensation is anyone's guess but this is Air India attempting to have Boeing pay for the decisions made by the carrier mistakes once again. The pilots strike over who flies the Dreamliner is also bleeding the carrier so they need money and they're going to Boeing for that money. This saga won't end until Boeing has delivered the 27th and final 787 to Air India and washes their hands of them.
First let's take a look at the positives. Boeing has 4 787s being readied at Everett for ANA. These are ZA506 (LN 47, JA809A), ZA507 (LN 48, JA810A), ZA508 (LN 51, JA811A), and ZA509 (LN 56, JA812A). ZA 508 is currently in the paint hangar but this plane had spent some time at EMC so I do believe that it is getting its aqueous wash and paint job done before being pulled to the fuel dock for fueling tests then to the flightline for mini gauntlet, engine start and first flight. Thus Boeing will have 4 787s ready for ANA in June maybe more. There has been a line move and currently the 4 787s that are inside 40-26 are ZA135 (LN 66, position 4), ZA118 (LN 67, position 3), ZA536 (LN 68, position 2) and ZA119 (LN 69, position 1). All but ZA536 are for ANA with ZA536 going to LAN. It is conceivable but not certain that ZA135 can go straight to paint and flightline with its engines and start preparation for delivery in about 2 weeks and can possibly be delivered at the end of June. This will be a major milestone for Boeing when it happens. Also ZA461 (LN 58) has made an appearance at the Everett Fuel Dock and I believe that this airplane is being prepared for delivery. I expect it will go into the paint hangar shortly before re-emerging for pre-delivery tests and final delivery to Qatar Airways in June and on display at Farnborough in July. Lastly, ZA237 (LN 46) has filed a flight plan fro Charleston to Fort Worth so this airplane can be painted for Air India. It is currently still in Charleston delayed by weather in the Dallas area. This last point is a nice lead into....
The Negatives
Only one (HUGE) negative which Air India. and here I just don't know where to start my rant. I (and probably 99.9% of of the world) thought that the issue of compensation to Air India for the delays was settled. According to the Govt. of India it is not and thus Boeing may have a dozen 787s for Air India sitting on the ramps at Everett and Charleston waiting to be delivered. The Air India debacle is a case study on how not to run an airline particularly when you are government owned and you have bureaucrats who know nothing of the airline industry making key decisions. ZA233 (LN 29, VT-AND) is all ready to be delivered and I suspect so is ZA236 (LN 35, VT-ANH). How long it will take to complete the negotiations on compensation is anyone's guess but this is Air India attempting to have Boeing pay for the decisions made by the carrier mistakes once again. The pilots strike over who flies the Dreamliner is also bleeding the carrier so they need money and they're going to Boeing for that money. This saga won't end until Boeing has delivered the 27th and final 787 to Air India and washes their hands of them.
Monday, May 14, 2012
Where is Boeing's 787 inventory - May 14, 2012
I just got updated information on the location of Boeing's 787 inventory that is stored or in re-work around Everett. The information is quie interesting as it shows that Boeing is focused on getting the late build 787s through change incorporation and out to the flightline. Many of the 787s that are in the EMC are airplanes 49 to 58 including ones for Qatar Airways, JAL, ANA, and Ethiopian. This shows that Boeig is focused on getting the late builds out the door first and then going back to fix the early builds which will take more time.
Meanwhile Boeing is flying ZA233 (LN 29, VT-AND) in preparation for delivery to Air India by the end of this month. ZA237 (LN46) already has had its first engine run and Boeing is saying that its first flight should come within "days" though I expect it to be some time late this week to middle of next week. This plane will deliver to Air India by the end oof June if not sooner though with Air India things could change given the turmoil within that airline.
Labels:
787,
787 Entry into Service,
Air India,
ANA,
EMC,
Ethiopian,
JAL,
Qatar Airways,
ZA233,
ZA237
Tuesday, May 8, 2012
May 2012 787 Deliveries
I just got information from a source that Boeing MAY only deliver just 1 787 which will be ZA233 (LN 29, VT-AND) for Air India. Given that the other two 787s (ZA506, LN 47, JA809A and ZA507, LN48, JA810A) that are on the flight line have not even flown there may be a lot of truth to this though they can still be delivered if Boeing conducts company and customer test flight over the next 3 weeks. I am not sure for the delay but it does appear that Boeing may be setting for quite a few deliveries in June. There has been speculation of which 787s that are in Boeing's EMC. I've gotten some of that information and it does appear that the following ANA 787s are inside the EMC: ZA100 (LN7), ZA508 (LN 51), and ZA509 (LN 56). Additionally there is a JAL 787 most likely ZA178 (LN 27). There is another 787 which may be for either United or Qatar.
Labels:
787,
787 Entry into Service,
ANA,
Qatar Airways,
United Airlines,
ZA100,
ZA178,
ZA233,
ZA506,
ZA507,
ZA508,
ZA509
Tuesday, April 24, 2012
2 more JAL 787s to deliver tomorrow
Boeing is set for another 787 double delivery to customer Japan Airlines. This time two more late built 787s will be delivered on April 25th. Fly away to Japan is expected around the 26th or 27th, in time for JAL to start 787 service to Moscow and Delhi in May. Japan Airlines is expecting to have 10 787s in its fleet by March 31, 2013. There are still 3 more JAL 787s at Everett that have yet to finish change incorporation. The two 787s that will be delivered are ZA180 (LN 37, JA826J) and ZA181 (LN38, JA827J).
Boeing is preparing ZA506 (LN47, JA809A) for delivery to ANA. This is probably not going to happen until May with it's first flight sometime in the first two weeks of May. This will be ANA's 8th 787. Again Boeing is still clearing out the late and very late built aircraft but clearing out the first 23 787s built has been very slow (LN7 - LN29)
Additionally, it's expected that Boeing will finally deliver Air India's first Dreamliner though the first one ZA236 (LN 35, VT-ANH) is still in San Antonio. It's sister, ZA233 (LN29, VT-AND) has been flying around San Antonio and may be flying to Paine Field right now. This airplane will still need to have its interior installed when it gets back to Everett so it won't be ready for delivery until late May at the earliest.
Finally on Friday Boeing will roll out the first 787 to be built at Boeing Charleston. This airplane, ZA237 (LN46) is destined for Air India and should be delivered around June. Given that this is the first 787 to be built at Charleston, Boeing will probably take its time doing the needed gauntlet testing before conducting its first flight. Boeing will then send the plane to Amarillo, Texas where Leading Edge Aviation Services is contracted to paint the Charleston built Dreamliners. Boeing Charleston doesn't have a paint hangar unlike Everett but I can see that changing with Boeing's acquisition of more land near the plant. The airplanes will then be flown back to Charleston where the interiors will be fitted and further Boeing and customer test flights will be completed.
Boeing is preparing ZA506 (LN47, JA809A) for delivery to ANA. This is probably not going to happen until May with it's first flight sometime in the first two weeks of May. This will be ANA's 8th 787. Again Boeing is still clearing out the late and very late built aircraft but clearing out the first 23 787s built has been very slow (LN7 - LN29)
Additionally, it's expected that Boeing will finally deliver Air India's first Dreamliner though the first one ZA236 (LN 35, VT-ANH) is still in San Antonio. It's sister, ZA233 (LN29, VT-AND) has been flying around San Antonio and may be flying to Paine Field right now. This airplane will still need to have its interior installed when it gets back to Everett so it won't be ready for delivery until late May at the earliest.
Finally on Friday Boeing will roll out the first 787 to be built at Boeing Charleston. This airplane, ZA237 (LN46) is destined for Air India and should be delivered around June. Given that this is the first 787 to be built at Charleston, Boeing will probably take its time doing the needed gauntlet testing before conducting its first flight. Boeing will then send the plane to Amarillo, Texas where Leading Edge Aviation Services is contracted to paint the Charleston built Dreamliners. Boeing Charleston doesn't have a paint hangar unlike Everett but I can see that changing with Boeing's acquisition of more land near the plant. The airplanes will then be flown back to Charleston where the interiors will be fitted and further Boeing and customer test flights will be completed.
Labels:
787,
787 Entry into Service,
Air India,
ANA,
Boeing,
Boeing Charleston,
Everett,
JAL,
Leading Edge Aviation Services,
San Antonio,
ZA180,
ZA181,
ZA233,
ZA236,
ZA506
Sunday, July 31, 2011
787 still faces uphill production issues as flight testing winds down
UPDATE (8/2/2011): ZA233 is now expected to have its B-1 test flight today. The sensor in question was not connected propoerly and the issue has now been rectified. It should be flown to Lackland AFB in San Antonio Texas in about a week or so.
Boeing's 787 program is currently winding up the flight testing and certification program for the 787 as ZA102 has flown more than 2/3 of the needed 300 flight test hours for the F&R/ETOPs flight testing campaign. This aircraft just returned from more than two weeks for flight testing around the western Pacific flying out of Guam. According to the latest stats, ZA102 has completed about 218 hours which puts it on track to complete the final phase of 787 testing in about 11 to 12 days (assuming 7 flight hours per day). Given that Boeing would wait about 30 days for final type certification from the FAA, this would give Boeing the opportunity to finally start deliveries to ANA around mid September. Indeed ANA has announced that the 787 will fly charter service between Narita and Hong Kong starting in October, one month after receiving it's first 787. However, questions are arising as to the timing of future deliveries to ANA and other customers after the first delivery.
As Boeing prepares for the delivery of ZA101 it is currently in the midst of another 787 assembly stoppage in 40-26 as issues with the assembly completion of the rear fuselage sections is forcing Boeing to institute this halt. It appears that Boeing will have these start and stop production hiccups on the 787 final assembly line for the foreseeable future and this is going to complicate Boeing's attempts to ramp up to 10/month by the end of 2013. They're were planning to be at a 2.5 production rate during this summer but now they're saying that the 787 line in Everett will be at 2.5 sometime in 2011. My opinion is that Boeing will not reach 10/month until sometime in mid/ late 2014. The ongoing change incorporation program along with supplier challenges will continue to weigh down the 787 production rate in the near term.
Even so Boeing is still experiencing issues in getting the 30 787s that they have assembled ready for customers. With Boeing trying to correct many of the supplier defects in parts as well as incorporate the changes mandated by the FAA as a result of test flying, Boeing is still having trouble getting planes ready for delivery. Re-work is simply taking way too much time due to the amount of work that has to be done on each airplane though later airplanes need less time in re-work. We have to all stay tuned for development regarding this issue in the 787 program. Boeing has reduced its guidance ithat they will deliver this year (from upwards of 40 to now upwards of 30). It is understoood that the number of 787s will comprise the majority if not all of the reduction guidance.
Lastly, ZA233, a 787 for Air India made it first flight today (July 31, 2011) but unfortunately lasted only 15 minutes as the aircraft an inflight anomoly which they said is a failed sensor. Boeing is currently checking all these sensors in the assembled aircraft. This airplane is scheduled to make the trip to San Antonio for change incorporation and re-work and then be delivered to Air India by the end of the this year. This issue is not expected to cause any delays.
Boeing's 787 program is currently winding up the flight testing and certification program for the 787 as ZA102 has flown more than 2/3 of the needed 300 flight test hours for the F&R/ETOPs flight testing campaign. This aircraft just returned from more than two weeks for flight testing around the western Pacific flying out of Guam. According to the latest stats, ZA102 has completed about 218 hours which puts it on track to complete the final phase of 787 testing in about 11 to 12 days (assuming 7 flight hours per day). Given that Boeing would wait about 30 days for final type certification from the FAA, this would give Boeing the opportunity to finally start deliveries to ANA around mid September. Indeed ANA has announced that the 787 will fly charter service between Narita and Hong Kong starting in October, one month after receiving it's first 787. However, questions are arising as to the timing of future deliveries to ANA and other customers after the first delivery.
As Boeing prepares for the delivery of ZA101 it is currently in the midst of another 787 assembly stoppage in 40-26 as issues with the assembly completion of the rear fuselage sections is forcing Boeing to institute this halt. It appears that Boeing will have these start and stop production hiccups on the 787 final assembly line for the foreseeable future and this is going to complicate Boeing's attempts to ramp up to 10/month by the end of 2013. They're were planning to be at a 2.5 production rate during this summer but now they're saying that the 787 line in Everett will be at 2.5 sometime in 2011. My opinion is that Boeing will not reach 10/month until sometime in mid/ late 2014. The ongoing change incorporation program along with supplier challenges will continue to weigh down the 787 production rate in the near term.
Even so Boeing is still experiencing issues in getting the 30 787s that they have assembled ready for customers. With Boeing trying to correct many of the supplier defects in parts as well as incorporate the changes mandated by the FAA as a result of test flying, Boeing is still having trouble getting planes ready for delivery. Re-work is simply taking way too much time due to the amount of work that has to be done on each airplane though later airplanes need less time in re-work. We have to all stay tuned for development regarding this issue in the 787 program. Boeing has reduced its guidance ithat they will deliver this year (from upwards of 40 to now upwards of 30). It is understoood that the number of 787s will comprise the majority if not all of the reduction guidance.
Lastly, ZA233, a 787 for Air India made it first flight today (July 31, 2011) but unfortunately lasted only 15 minutes as the aircraft an inflight anomoly which they said is a failed sensor. Boeing is currently checking all these sensors in the assembled aircraft. This airplane is scheduled to make the trip to San Antonio for change incorporation and re-work and then be delivered to Air India by the end of the this year. This issue is not expected to cause any delays.
Sunday, November 7, 2010
787 and 747-8I news - November 7, 2010
Last week was an eventful week for the 787 program with the Rolls Royce Trent 900 engine issue raising questions about the design of the Trent 1000 and if there is a larger problem that could affect first delivery.
The August 2nd failure of the Trent 1000 engine on a test stand in Derby was a major factor of the latest 787 delay no matter what anyone else would tell you. Last weeks incident on QF32 with the Trent 900 engine highlighted the potential human cost of an uncontained engine failure. Part of the engine had damaged the wing of the A380 and if the pieces had penetrated the wing fuel tank, it would have most certainly lead to the loss of the aircraft and all on board. The potential lost of QF32 would have been the third worst air disaster ever given the number of souls aboard the airplane.
This incident also underscored Boeing's decision to delay the 787 delivery to ANA (to be equipped with the Trent 1000) to mid February. Now Rolls says they have a hardware and software fix but in light of what happened last week, Rolls Royce has a lot of explaining and soul searching to do. They have to convince the airline industry and the airframe manufacturers that their products are safe. Recent events have thrown much light on their products. Rolls Royce is hurting and I do direct you this this article HERE to get a real good read out on the potential problems that the uncontained failures of the Trent 1000 and Trent 900 engines have for Rolls. Finally, Boeing is not going to be helped by Pratt and Whitney's lawsuit against Rolls Royce for patent infringements. The lawsuits aims to prevent Rolls Royce from delivering any Trent 1000 engines to Boeing and the 787 program. If this goes through Boeing and its customers who ordered the Trent's will be in a very tough spot.
Boeing still has issues with the 787 that they have to grapple with out the Rolls Royce issue and that issue is the travelled work and all the rework that the assembled 787s have to have before they are delivered to customers. Boeing is still mum on the number of 787s that they will deliver next year but there has been press reports that there would be 10 month delay to some deliveries, notably to Air India and Korean Air. Boeing has come out forcefully in the light of those press reports to say that their isn't an further delay beyond those that they have already announced and that the media that originated the newest story was using information that Boeing had released two months ago. The verdict: Boeing is still sticking with the mid 1st quarter 2011 for first delivery but beyond that Boeing has not made any announcement of the pace of deliveries after the first airplane is in ANA's hands.
Air India has come out and said that they are expecting their first 787 in June 2011 which is in line with past reports. Still we will still have to see how the pace of rework goes after the completion of the flight test program in order to better gauge the delivery schedule of the 787s.
Meanwhile, Flightblogger reported the resumption of 787 part deliveries into Everett with the arrival of the wing set for the 31st 787 (ZA117 for ANA). There was a line move late last week where LN 25 (ZA230 for Air India) was moved to the paint hangar allowing ZA233 (also for Air India) to be loaded into the final body join spot.
Flightblogger: Boeing restarts 787 deliveries with arrival of wings for Airplane 31
Flight test activities continued this past weekend with the Boeing test flight fleet logging about 60 flight test hours over the last three days (Nov. 5 - Nov. 7). Some of the milestones include the 787/Trent 1000 fleet surpassing 2,000 flight test hours, the 6 test flight airplanes surpassing 75% of the required test flight hours (3,100 total), ZA001 surpassing 700 flight test hours flown, the test flight fleet surpassing 2,300 flight test hours, the 787/GE test flight fleet surpassing 50% of the required test flight hours, and the 750th test flight of a 787.
Also ZA006 undertook a marketing mission to Amsterdam and Paris in an effort to sell AF/KLM the 787. During this time, ZA006 was parked next to an Air France A380 overnight at Charles De Gaulle in Paris which would have made for a great photo.
747-8I, RC001 makes progress.
Boeing's other major passenger aircraft that's in development also is making progress as the first 747-8I achieved power on for the first time. Power on allows some testing of the aircraft's systems in the assembly hangar while assembly is on going and is an important milestone. Boeing plans a four month test flight program and first delivery in about a year from now. The reason for the short flight test program is that much of the testing has already or will be completed by the 747-8F.
Below is Boeing Press Release as well as video of the power on of RC001:
The August 2nd failure of the Trent 1000 engine on a test stand in Derby was a major factor of the latest 787 delay no matter what anyone else would tell you. Last weeks incident on QF32 with the Trent 900 engine highlighted the potential human cost of an uncontained engine failure. Part of the engine had damaged the wing of the A380 and if the pieces had penetrated the wing fuel tank, it would have most certainly lead to the loss of the aircraft and all on board. The potential lost of QF32 would have been the third worst air disaster ever given the number of souls aboard the airplane.
This incident also underscored Boeing's decision to delay the 787 delivery to ANA (to be equipped with the Trent 1000) to mid February. Now Rolls says they have a hardware and software fix but in light of what happened last week, Rolls Royce has a lot of explaining and soul searching to do. They have to convince the airline industry and the airframe manufacturers that their products are safe. Recent events have thrown much light on their products. Rolls Royce is hurting and I do direct you this this article HERE to get a real good read out on the potential problems that the uncontained failures of the Trent 1000 and Trent 900 engines have for Rolls. Finally, Boeing is not going to be helped by Pratt and Whitney's lawsuit against Rolls Royce for patent infringements. The lawsuits aims to prevent Rolls Royce from delivering any Trent 1000 engines to Boeing and the 787 program. If this goes through Boeing and its customers who ordered the Trent's will be in a very tough spot.
Boeing still has issues with the 787 that they have to grapple with out the Rolls Royce issue and that issue is the travelled work and all the rework that the assembled 787s have to have before they are delivered to customers. Boeing is still mum on the number of 787s that they will deliver next year but there has been press reports that there would be 10 month delay to some deliveries, notably to Air India and Korean Air. Boeing has come out forcefully in the light of those press reports to say that their isn't an further delay beyond those that they have already announced and that the media that originated the newest story was using information that Boeing had released two months ago. The verdict: Boeing is still sticking with the mid 1st quarter 2011 for first delivery but beyond that Boeing has not made any announcement of the pace of deliveries after the first airplane is in ANA's hands.
Air India has come out and said that they are expecting their first 787 in June 2011 which is in line with past reports. Still we will still have to see how the pace of rework goes after the completion of the flight test program in order to better gauge the delivery schedule of the 787s.
Meanwhile, Flightblogger reported the resumption of 787 part deliveries into Everett with the arrival of the wing set for the 31st 787 (ZA117 for ANA). There was a line move late last week where LN 25 (ZA230 for Air India) was moved to the paint hangar allowing ZA233 (also for Air India) to be loaded into the final body join spot.
Flightblogger: Boeing restarts 787 deliveries with arrival of wings for Airplane 31
Flight test activities continued this past weekend with the Boeing test flight fleet logging about 60 flight test hours over the last three days (Nov. 5 - Nov. 7). Some of the milestones include the 787/Trent 1000 fleet surpassing 2,000 flight test hours, the 6 test flight airplanes surpassing 75% of the required test flight hours (3,100 total), ZA001 surpassing 700 flight test hours flown, the test flight fleet surpassing 2,300 flight test hours, the 787/GE test flight fleet surpassing 50% of the required test flight hours, and the 750th test flight of a 787.
Also ZA006 undertook a marketing mission to Amsterdam and Paris in an effort to sell AF/KLM the 787. During this time, ZA006 was parked next to an Air France A380 overnight at Charles De Gaulle in Paris which would have made for a great photo.
747-8I, RC001 makes progress.
Boeing's other major passenger aircraft that's in development also is making progress as the first 747-8I achieved power on for the first time. Power on allows some testing of the aircraft's systems in the assembly hangar while assembly is on going and is an important milestone. Boeing plans a four month test flight program and first delivery in about a year from now. The reason for the short flight test program is that much of the testing has already or will be completed by the 747-8F.
Below is Boeing Press Release as well as video of the power on of RC001:
Boeing Achieves Power On for New 747-8 IntercontinentalBoeing Video
EVERETT, Wash., Nov. 5, 2010 /PRNewswire/ -- Boeing (NYSE: BA) has completed the power on sequence for the new 747-8 Intercontinental. This milestone enables the program to begin functional tests on the airplane.
"This is a critical step in the assembly process for the new 747-8 Intercontinental," said Elizabeth Lund, 747 deputy program manager, Boeing Commercial Airplanes. "The airplane's systems are now live. This milestone is a reflection of the focus and hard work of our engineers, mechanics and suppliers."
Power on is a complex series of tasks that methodically energize and activate the airplane's systems. In this critical stage of the assembly process, the electrical, hydraulic and pneumatic systems are brought on line.
Mechanics connected the 747-8 to an external power cart to energize the flight-deck display and maintenance systems. The electricity coursing through the airplane's 133 miles (214 km) of wire will be as high as 105 kilovoltampere (kVa).
The program also activated the airplane's hydraulic and pneumatic systems. Pressurized to 3,000 pounds per square inch (psi), the hydraulics power the flight control surfaces, landing gear, brakes and steering systems. The 160 psi applied to the pneumatic system enables the airplane to operate the environmental control systems and the leading-edge flaps.
"We are very methodical in ensuring the integrity of the airplane's systems," said Todd Zarfos, vice president of 747 engineering, Boeing Commercial Airplanes. "This accomplishment is a key milestone in validating the design, installation and functionality of the electrical, hydraulic and pneumatic systems."
A video that gives you an inside look at the power on sequence is available at http://bit.ly/dlXgym.
The program is expected to complete assembly of the 747-8 Intercontinental in the first quarter of 2011. The airplane is scheduled to enter service in late 2011 following the flight test program.
The 747-8, which includes the 747-8 Intercontinental and the 747-8 Freighter, was launched in November 2005. Boeing has 109 orders for the 747-8 -- 33 for the 747-8 Intercontinental and 76 for the 747-8 Freighter. The first 747-8 Intercontinental is scheduled to deliver in late 2011.
The new 747-8 Intercontinental offers the lowest operating costs and best economics of any large passenger airplane, while providing enhanced environmental performance. The 747-8 provides new revenue opportunities that allow airlines to maximize profits. Eighteen feet longer than the 747-400, the 747-8 has 51 additional seats to accommodate 467 passengers in a typical three-class configuration, and it also offers 26 percent more cargo volume.
Labels:
747,
747 Flight Test,
747-8,
747-8F,
747-8I,
787,
787 Flight Test,
A380,
Air France,
Air India,
ANA,
KLM,
Rolls Royce,
Trent 1000,
Trent 900,
ZA001,
ZA006,
ZA117,
ZA230,
ZA233
Thursday, October 28, 2010
Flightblogger talks 787 production and horizontal stabilizers
Now that Alenia has effectively shut down 787 production for another 2 weeks....flightblogger revealed in a new post that the Italian company actually may have shut it down for much longer. The reasoning.....there hasn't been a 787 line move since October 3. There were to have been two more line moves in the month of October whch did not occur. The reason is the needed rework of the horizontal tail assemblies that Alenia is responsible for. Boeing has a whole slew of people in Italy trying to get them back on track but it seems that Alenia's troubles probably run very deep.
With all the issues surrounding the horizontal stabilizer, Boeing chose to mocve the line which left ZA231 without a the tailplane. It was being reworked when the line moved and is now installed on airplane 27 (ZA178).
This has thrown 787 final assembly into a tailspin (pun intended) as the horizontal stabs for airplanes 26 to 29 are being reworked as well as those that are already on the fully assembled production airplanes. Stabilizers meant for certain palnes are being installed on others. This won't be a problem as it is a common part, of course, but it does illustrate what the problems at Alenia has caused downstream in the production process.
Here's how things are laid out in building 40-26 in terms of HTP-airframe
Airplane 25 --> HTP #25
Airplane 26 --> HTP #29
Airplane 27 --> HTP #26
Airplane 28 --> HTP #27
Airplane 29 --> HTP #28
Airplane 30 --> HTP #30 --- this is where Boeing will be back to a normal assembly routine.
As evidenced by the number of 787s on the Boeing flightline where the HTP has been disassembled, it is evident that the problem is quite serious with many of them requiring rework prior to delivery. Boeing has set up a tool to allow easy access to the areas of the HTP that need rework but it's clear that the first 23 production airplanes will have quite a bit of work ahead of them before they are delivered next year. Flightblogger's article is a great read and does raise some flags with respect to Alenia. My sense is that if there is way Boeing can extract it self from Alenia it will. They have already indicated that the HTP for the 787-9 will probably come back in house and I think this is a certainty.
Flightblogger: A Closer Look: Inside the 787 delivery hold and horizontal stabilizer issues
With all the issues surrounding the horizontal stabilizer, Boeing chose to mocve the line which left ZA231 without a the tailplane. It was being reworked when the line moved and is now installed on airplane 27 (ZA178).
This has thrown 787 final assembly into a tailspin (pun intended) as the horizontal stabs for airplanes 26 to 29 are being reworked as well as those that are already on the fully assembled production airplanes. Stabilizers meant for certain palnes are being installed on others. This won't be a problem as it is a common part, of course, but it does illustrate what the problems at Alenia has caused downstream in the production process.
Here's how things are laid out in building 40-26 in terms of HTP-airframe
Airplane 25 --> HTP #25
Airplane 26 --> HTP #29
Airplane 27 --> HTP #26
Airplane 28 --> HTP #27
Airplane 29 --> HTP #28
Airplane 30 --> HTP #30 --- this is where Boeing will be back to a normal assembly routine.
As evidenced by the number of 787s on the Boeing flightline where the HTP has been disassembled, it is evident that the problem is quite serious with many of them requiring rework prior to delivery. Boeing has set up a tool to allow easy access to the areas of the HTP that need rework but it's clear that the first 23 production airplanes will have quite a bit of work ahead of them before they are delivered next year. Flightblogger's article is a great read and does raise some flags with respect to Alenia. My sense is that if there is way Boeing can extract it self from Alenia it will. They have already indicated that the HTP for the 787-9 will probably come back in house and I think this is a certainty.
Flightblogger: A Closer Look: Inside the 787 delivery hold and horizontal stabilizer issues
Saturday, October 23, 2010
Dreamliner 4 circuit around the country and potential 787 production woes resurfacing?
ZA004 undertook a very long 13+ hour test flight that took it around the country yesterday to test the 787s to test...of all things... the fuel gauge of the aircraft. According to Flightblogger, the test (which I initially thought was an ETOPs flight) was to see how the Fuel Quantity Indication System. The test added a large amount of flight test time to the 787/RR test flight fleet and bought them closer to the 2,430 flight hours needed to certify the 787/Trent 1000 engine combination and allow for deliveries to start to ANA. The Trent 1000 powered 787 test flight fleet has accumulated well over 1,900 flight test hours thus far and the total 787 flight test hours has exceeded 2,100 hours leaving 1,000 flight test hours needed to complete the test flight program.
Flightblogger: 787 goes cross country to check the gas gauge
While the test flight program continues to make progress, there are signs of production troubles on the 787 final assembly line. ZA233, the 29th 787s to be assembled was initially supposed to start final assembly on Oct. 4th. It was pushed back to late October, then early November and now I got news that it won't start assembly until around November 17th...over 6 weeks late. To add to the mystery, Matt Cawby got video of a rear and forward 787 fuselage sections being loaded back on to the 747 LCF in Everett instead of being offloaded. Now the LCF did not depart Everett so my guess is that they might be being stored on board the 747 LCF. I am hoping to hear from Boeing about any production pauses on the 787 line and what reloading of the fuselage sections on the LCF may mean.
Flightblogger: 787 goes cross country to check the gas gauge
While the test flight program continues to make progress, there are signs of production troubles on the 787 final assembly line. ZA233, the 29th 787s to be assembled was initially supposed to start final assembly on Oct. 4th. It was pushed back to late October, then early November and now I got news that it won't start assembly until around November 17th...over 6 weeks late. To add to the mystery, Matt Cawby got video of a rear and forward 787 fuselage sections being loaded back on to the 747 LCF in Everett instead of being offloaded. Now the LCF did not depart Everett so my guess is that they might be being stored on board the 747 LCF. I am hoping to hear from Boeing about any production pauses on the 787 line and what reloading of the fuselage sections on the LCF may mean.
Labels:
787,
787 Flight Test,
ANA,
Dreamlifter,
ETOPS,
LCF,
Rolls Royce,
Trent 1000,
ZA004,
ZA233
Thursday, October 21, 2010
787 now in final stages of flight testing
Boeing Chief, Jim McNerney said during the third quarter earnings conference call that the 787 flight testing is in the final stages. Flight testing has picked up in the last week as the 787s have racked up just under 2,100 flight hours and the number of hours needed to certify the Trent 1000 powered version of the 787 is down to under 550. Another important milestone on the 787's road to certification is completion of the required number of simulated flight cycles on the fatigue test airframe (ZY998) for first delivery. Boeing will continue to fatigues test the 787 airframe for the next 3 years but they needed to get a certain number of cycles completed before they delivered the first airplane to ANA. All this work was done on the ground at Everett. Boeing has reiterated its intention to delivery the 787 in mid 1st quarter 2011. McNerney also said that Rolls Royce has a hardware and software fix to prevent the recurrence of the uncontained engine failure that took place in Derby, UK in early August.
Still ahead for the 787 is the all important ETOPS type certification where the specific engine-airframe must be approved for ETOPS flights mainly across the Atlantic and Pacific. Later each individual carrier must get it ETOPS operational certificate. This testing is expected to get underway around January.
In the meantime Boeing continues production of the 787s at Everett. McNerney said that supplier shipments are picking up. Boeing has had to slow down production twice this year in order to allow the supply chain to catch up and reduce the travelled work coming into Everett. Boeing is expected to start final assembly on ZA233 (LN 29) a 787 for Air India.
Lastly, Boeing is talking about bringing production of the horizontal stabilizers for the 787-9 back in house according to Dominic Gates of the Seattle Times. Boeing is still finding workmanship issues coming out of Alenia. According to the article, Boeing has found more issues on the test flight airplanes as well as a few of the production airplanes. A couple of the test flight airframes have been fixed and they're working through the others. I wonder if this was the reason the 787s didn't fly as much between mid September and mid October? You can read Dominic's article here:
Dominic Gates: Boeing considers building 787-9 horizontal tails in-house
Finally, Flightglobal has an article out saying that Boeing believes that the majority of 787 orders will be for the 787-9 model. This is supported by many of the order conversions from the 787-8 to the 787-9 by airlines. You read the article here:
Flightglobal: Bigger 787 variant to boost order share: Boeing
Still ahead for the 787 is the all important ETOPS type certification where the specific engine-airframe must be approved for ETOPS flights mainly across the Atlantic and Pacific. Later each individual carrier must get it ETOPS operational certificate. This testing is expected to get underway around January.
In the meantime Boeing continues production of the 787s at Everett. McNerney said that supplier shipments are picking up. Boeing has had to slow down production twice this year in order to allow the supply chain to catch up and reduce the travelled work coming into Everett. Boeing is expected to start final assembly on ZA233 (LN 29) a 787 for Air India.
Lastly, Boeing is talking about bringing production of the horizontal stabilizers for the 787-9 back in house according to Dominic Gates of the Seattle Times. Boeing is still finding workmanship issues coming out of Alenia. According to the article, Boeing has found more issues on the test flight airplanes as well as a few of the production airplanes. A couple of the test flight airframes have been fixed and they're working through the others. I wonder if this was the reason the 787s didn't fly as much between mid September and mid October? You can read Dominic's article here:
Dominic Gates: Boeing considers building 787-9 horizontal tails in-house
Finally, Flightglobal has an article out saying that Boeing believes that the majority of 787 orders will be for the 787-9 model. This is supported by many of the order conversions from the 787-8 to the 787-9 by airlines. You read the article here:
Flightglobal: Bigger 787 variant to boost order share: Boeing
Labels:
787,
787 Flight Test,
787-9,
Air India,
ALenia,
ETOPS,
Everett,
horizontal stabilizer,
Jim McNerney,
Rolls Royce,
Trent 1000,
ZA233,
ZY998
Wednesday, October 13, 2010
787 keeps movin' along
As the time to first delivery draws closer, Boeing is ramping up both production as well as the pace of flight testing.
Flight Testing
The 787 flight test fleet is closing on 2000 flight hours flown, they can potentially break through that mark today. The Rolls Royce powered 787s got a real work out on Oct. 12th flying almost 24 flight hours during the day and breaking through the 1800 flight hour mark for the RR/787 flight test combination. Hopefully this signals a push to accumulate the remaining 35% flight test requirements needed to certify the Rolls powered 787s. Boeing has completed almost 75% of the require flight test hours needed to certify the Trent 1000 powered 787s so they are getting close.
While the first four 787s are being pushed, ZA005 is at Everett for some standard inspections as well as fuel transfer tests. ZA006 remains at Boeing Field going through the post first flight lay up where additional flight test instrumentation is being installed. I haven't heard when those two airplanes will be flying again. Currently about 27% of the GEnx/787 flight test hours have been flown.
ZA102 is now scheduled to fly around November 24th instead of November 9th though that date may change. This will be the first flight of a production standard 787 with a full customer interior. Both ZA101 and ZA102 have its Trent 1000 engines. ZA101 will undertake ground testing though I'm not sure if it has a customer interior as well.
Next month ZA004 will down for about a month while it gets new Trent 1000 engines with the package "B" improvements meant to bring the engines to within 1% of the promised SFC (specific fuel consumption) that Rolls Royce promised to its customers.
Production
As the flight test wring out the 787 for delivery, Boeing is slowly ramping up 787 production. Currently ZA230 will moved out of position 4 in building 40-26 and the line should pulse on October 15th but the next airplane ZA233 (LN 29) won't be loaded into position 1 until October 26th. I'm still trying to find out why the 11 day delay. ZA234 (LN 30, a 787 for Air India) is due to start final assembly 9 days later. This indicates that Boeing is attempting a 9 to 10 day run with each airframe is in each of the 4 assembly positions 9 to 10 day. This translates to a final assembly run for each 787 of about 36 to 40 days in building 40-26. At that rate, Boeing should be at ZA236 (LN 35, the 35th 787 being built is for Air India) by the end of the year though they will have 30 787s built and out on the flightline.
Speaking of the flightline, the parking spots for airplanes at Everett are getting full. So full that Boeing is now parking airplanes in a small ramp area in fron of the Future of Flight Museum. According to Matt Cawby, Boeing has leased out space at Everett near the air control tower as well asto the south of the asembly halls in order to store built but undelivered 787s.
Lastly, Flightblogger took a trip to 787 suppliers in Asia and has put up an excellent post of the 787 suppliers in Korea with some great photos. It is a great read.
Flightblogger: From Busan to Boeing: 787s Asian Supply Chain Part 1
Flight Testing
The 787 flight test fleet is closing on 2000 flight hours flown, they can potentially break through that mark today. The Rolls Royce powered 787s got a real work out on Oct. 12th flying almost 24 flight hours during the day and breaking through the 1800 flight hour mark for the RR/787 flight test combination. Hopefully this signals a push to accumulate the remaining 35% flight test requirements needed to certify the Rolls powered 787s. Boeing has completed almost 75% of the require flight test hours needed to certify the Trent 1000 powered 787s so they are getting close.
While the first four 787s are being pushed, ZA005 is at Everett for some standard inspections as well as fuel transfer tests. ZA006 remains at Boeing Field going through the post first flight lay up where additional flight test instrumentation is being installed. I haven't heard when those two airplanes will be flying again. Currently about 27% of the GEnx/787 flight test hours have been flown.
ZA102 is now scheduled to fly around November 24th instead of November 9th though that date may change. This will be the first flight of a production standard 787 with a full customer interior. Both ZA101 and ZA102 have its Trent 1000 engines. ZA101 will undertake ground testing though I'm not sure if it has a customer interior as well.
Next month ZA004 will down for about a month while it gets new Trent 1000 engines with the package "B" improvements meant to bring the engines to within 1% of the promised SFC (specific fuel consumption) that Rolls Royce promised to its customers.
Production
As the flight test wring out the 787 for delivery, Boeing is slowly ramping up 787 production. Currently ZA230 will moved out of position 4 in building 40-26 and the line should pulse on October 15th but the next airplane ZA233 (LN 29) won't be loaded into position 1 until October 26th. I'm still trying to find out why the 11 day delay. ZA234 (LN 30, a 787 for Air India) is due to start final assembly 9 days later. This indicates that Boeing is attempting a 9 to 10 day run with each airframe is in each of the 4 assembly positions 9 to 10 day. This translates to a final assembly run for each 787 of about 36 to 40 days in building 40-26. At that rate, Boeing should be at ZA236 (LN 35, the 35th 787 being built is for Air India) by the end of the year though they will have 30 787s built and out on the flightline.
Speaking of the flightline, the parking spots for airplanes at Everett are getting full. So full that Boeing is now parking airplanes in a small ramp area in fron of the Future of Flight Museum. According to Matt Cawby, Boeing has leased out space at Everett near the air control tower as well asto the south of the asembly halls in order to store built but undelivered 787s.
Lastly, Flightblogger took a trip to 787 suppliers in Asia and has put up an excellent post of the 787 suppliers in Korea with some great photos. It is a great read.
Flightblogger: From Busan to Boeing: 787s Asian Supply Chain Part 1
Labels:
40-26,
787,
787 Flight Test,
Air India,
Boeing Field,
Everett,
Rolls Royce,
Trent 1000,
ZA001,
ZA002,
ZA003,
ZA004,
ZA005,
ZA006,
ZA101,
ZA102,
ZA230,
ZA233,
ZA234,
ZA236
Monday, October 4, 2010
Boeing Statement on ZA006 First Flight
Boeing PhotoBoeing released a statement announcing the first flight of the final test 787. However the first test flight was cut short due to a cooling fluid issue according to a Tweet by Flightblogger. The press release doesn't mention the flight being cut short. It mentions the flight lasting a little over an hour as well as reviews the 787 testing to date. Over 65% of the test conditions needed to certify the Rolls Royce powered 787 have been completed according to Boeing. Boeing has also completed 15 cycles on the fatigue test air frame (ZY998) and need to complete 10,000 by the time first delivery is made to ANA in mid February. Boeing is also looking to increase the production of 787s. The 28th 787 (ZA232) to be built just entered final assembly and the next one, ZA233, will enter final assembly 10 days later on Oct. 14th. This could mean that Boeing is attempting a 3/month production rate. Because of the production 787 already built, Boeing has started to store 787 in an area called Kilo North which is a newly constructed ramp area just south of the Future of flight Museum. Three 787s (ZA150, ZA151, and ZA176) were moved to this area over the weekend.
Flightblogger also has a couple of posting up with regards to today's flight:
Flightblogger: Sixth and final 787 test aircraft completes abbreviated test flight
Flightblogger: Liquid cooling squawk tied to abbreviated ZA006 first flight
Sixth Boeing 787 Makes First Flight, Testing Program Making GoodHow long ZA006 will be out because of the issue that cropped up during flight is unknown at this time.
Progress
EVERETT, Wash., Oct. 4 /PRNewswire/ -- The final Boeing (NYSE: BA) 787 Dreamliner to join the flight test fleet made its first flight today from Paine Field in Everett, Wash. The airplane, ZA006, is the second 787 equipped with General Electric GEnx engines to fly.
Captains Christine Walsh and Bill Roberson were at the controls during the 1 hour and 4 minute flight. The airplane landed at Boeing Field at 12:45 p.m. (Pacific time).
"It's great to have our last flight test airplane join the fleet," said Scott Fancher, vice president and general manager of the 787 program. "We have been focused on completing the testing required for certification of the 787 with Rolls-Royce engines, because that is the first model we deliver. A great deal of the testing that we've done also applies to the 787s with GE engines and won't need to be repeated," said Fancher.
There is, however, a smaller portion of testing that is unique to the engine/airframe combination. In general, this portion includes noise testing, extreme weather operations, function and reliability, and extended operations. In addition, testing to verify the airplane handles the same regardless of engine type and that the systems work on both models is required.
Some additional flight tests will be performed on one of the production airplanes, the ninth 787 to be built, but it is not considered a full-time member of the flight test fleet.
787 Testing Progress Report
In addition to achieving first flight of ZA006, the Boeing test team has completed a number of flight test milestones in recent weeks.
Boeing wrapped up a series of natural and artificial icing tests, meeting all requirements with no changes required. Pilots reported that the airplane continues to handle well even in the presence of ice.
Flight loads survey testing, which demonstrates the pressure distribution on the airplane structure throughout the phases of flight in a variety of configurations, also has been completed. The team conducted this testing on ZA004 primarily at the airport at Victorville, Calif. Analysis of this testing continues.
A dramatic series of tests that stress the airplane's brakes, called maximum brake energy testing, was completed in late September at Edwards Air Force Base, also in California. ZA001 conducted this testing as well as a series of extreme takeoff and landing conditions including minimum takeoff speed testing. Earlier in the month, ZA001 completed wet runway testing at Roswell, NM.
ZA003 flew to Glasgow, Mont., to complete community noise testing. All results were within expectations.
As a result of these tests and others, all takeoff performance and handling characteristics testing is complete for the initial version of the 787. Additional testing will be required for 787s equipped with GE engines.
The 787 flight test program has logged more than 1,900 hours over 620 flights and completed more than 65 percent of the flight test conditions for 787s with Rolls-Royce engines.
Equally important to the testing required in the air is the ground testing required to certify a new airplane. Boeing has completed well over 4,000 hours of ground testing on the same airplanes that are in the flight test program.
In addition, fatigue testing has started at a test rig in Everett. Fifteen flights have been simulated. Federal regulations require Boeing to conduct twice as many flight cycles as any airplane in revenue service. Boeing plans to have completed 10,000 flight cycles prior to first delivery.
"We continue to be extremely satisfied with the performance of the 787 in its testing operations," said Fancher. "This airplane handles wonderfully and will be a valuable tool for our customers."
Tuesday, May 4, 2010
787 Happenings
Boeing and the FAA continues on the certification flight test path with the test flight fleet accumulating just under 575 flight hours. Interestingly, flights that occurred yesterday were not posted on Flightaware for some reason and flight notifications are not being sent from Flightaware for any 787 flight.
Next week one 787 is going to fly to Colorado Springs Airport for more flight testing around May 11th. I surmise that this trip to Colorado might be for high altitude flight testing. ZA001 should return to flight test today or tomorrow and ZA002 will be flying towards the end of this week. ZA005 is still scheduled to make its first flight towards the end of May while ZA006 will follow by mid June.
Lastly, I have been keeping track of the 787 production and I found out that 4 of 5 787s for LN 26 to LN 30 will be going to Air India. LN 25 (ZA230), LN 26 (ZA231), and LN 28 (ZA232) to LN 30 (ZA234) will be for Air India. LN 27 (ZA178) will be a Japan Airlines bird. I expect that these airplanes will be in final assembly this fall.
Next week one 787 is going to fly to Colorado Springs Airport for more flight testing around May 11th. I surmise that this trip to Colorado might be for high altitude flight testing. ZA001 should return to flight test today or tomorrow and ZA002 will be flying towards the end of this week. ZA005 is still scheduled to make its first flight towards the end of May while ZA006 will follow by mid June.
Lastly, I have been keeping track of the 787 production and I found out that 4 of 5 787s for LN 26 to LN 30 will be going to Air India. LN 25 (ZA230), LN 26 (ZA231), and LN 28 (ZA232) to LN 30 (ZA234) will be for Air India. LN 27 (ZA178) will be a Japan Airlines bird. I expect that these airplanes will be in final assembly this fall.