As I had reported last week, Boeing will restart 787 final assembly on Monday, June 14th. This is reinforced with the restart of LCF flights bringing the required fuselage sections into Everett. Yesterday and LCF flew in the rear fuselage for the next 787 to be built...ZA177 (LN 23) for Japan Airlines and horizontal stabs for Air India's first 787, ZA230 (LN 25). Later this afternoon, the forward fuselage will be flown from Wichita to Everett. There should be a line move late this weekend to allow parts for the 23rd 787 to be located in the assembly tool in building 40-26.
Flight Test
ZA002 flew a 2 hour and 35 minute mission this morning (June 8th) out of Victorville. In completing this test flight, the 787 test fleet has completed over 30% of the required 3,100 test flight hours for the program. ZA005 continues its gauntlet testing ahead of a planned first flight on June 16th.
Showing posts with label LN 25. Show all posts
Showing posts with label LN 25. Show all posts
Tuesday, June 8, 2010
Monday, May 17, 2010
Breaking: Flightblogger reports on new design flaw in 787 aft fuselage
Jon "Flightblogger" Ostrower reported that the prime reason for the production halt was not just for suppliers to catch up with production work but also to allow Boeing and it's suppliers to fix a design flaw. The flaw can potentially compromise the structural integrity of the airplane. Flightblogger reported that the flaw was discovered in December, 5 months ago.
The flaw involves shear ties which attaches the fuselage skin to the fuselage structure in section 48 and 48 aft. When there are repeated changes in the thermal condition of the rear fuselage, the shear ties can detach from the aircraft skin thus creating the structural issue.
The Fix
Flightblogger reports that the situation does not represent an immediate safety of flight issue to the test flight fleet and that a fix is identified. The fix involves using thicker shear ties and radius filler alongside the existing shear ties. Boeing says that all airplanes will meet FAA requirements.
Production
LN 23 and LN 24 are being modified now at Charleston with some modification work to be done at Everett. LN 25 will have the fix installed partly in Charleston and partly in Korea where the section 48 Aft is manufactured. The existing airplanes will be modified though apparently ZA001, ZA002 and ZA003 will not receive them as they will not be sold to customers. All customer airplanes are going to receive the modifications. Thus airplanes from LN 4 to LN 22 will all have to receive the modifications and starting with LN 55 the 787 will have a permanent fix in the section 48. Now while there has been some supplier issues that have lead to the temporary halt in production, Flightblogger's sources has said that the shear tie issue is the main reason for the halt. I will try to get more details about this issue.
Boeing said that the issue will not effect first delivery or continued production of the 787.
Flightblogger: Source: 787 design flaw drives supplier freeze
The flaw involves shear ties which attaches the fuselage skin to the fuselage structure in section 48 and 48 aft. When there are repeated changes in the thermal condition of the rear fuselage, the shear ties can detach from the aircraft skin thus creating the structural issue.
The Fix
Flightblogger reports that the situation does not represent an immediate safety of flight issue to the test flight fleet and that a fix is identified. The fix involves using thicker shear ties and radius filler alongside the existing shear ties. Boeing says that all airplanes will meet FAA requirements.
Production
LN 23 and LN 24 are being modified now at Charleston with some modification work to be done at Everett. LN 25 will have the fix installed partly in Charleston and partly in Korea where the section 48 Aft is manufactured. The existing airplanes will be modified though apparently ZA001, ZA002 and ZA003 will not receive them as they will not be sold to customers. All customer airplanes are going to receive the modifications. Thus airplanes from LN 4 to LN 22 will all have to receive the modifications and starting with LN 55 the 787 will have a permanent fix in the section 48. Now while there has been some supplier issues that have lead to the temporary halt in production, Flightblogger's sources has said that the shear tie issue is the main reason for the halt. I will try to get more details about this issue.
Boeing said that the issue will not effect first delivery or continued production of the 787.
Flightblogger: Source: 787 design flaw drives supplier freeze
Labels:
787,
787 Flight Test,
Charleston,
Everett,
LN 22,
LN 23,
LN 24,
LN 25,
LN 4,
LN 55,
Section 48,
Section 48 aft,
shear ties,
Vought,
ZA001,
ZA002,
ZA003,
ZA004