Dreamliner 4 main fuselage delayed by only a few days.

Ok just out on Bloomberg. Alenia said that a temporary worker put the wrong fasteners in 11 holes in the midbody fuselage which damaged a 30 cm area. The section was repaired with a carbon fiber patch which is the ususal procedure. The section's delivery will be delayed by only a few days as a consequence. The temporary worker was fired.