Tuesday, November 2, 2010

Guy Norris: Boeing says first delivery remains on track

Guy Norris posted an article today saying the Boeing still firmly believes they will deliver the first 787 to ANA in mid 1st quarter of 2011 despite the amount of rework that needs to be done.

Guy also says that ZA004 should fly later this week with updated electronic engine control software loaded and will be receiving the package "B" Trent 1000 engines soon. I've been told that ZA004 should go into layup to have those engines installed sometime this month and should re-emerge in December for return to flight after ground testing the engines.

Guy Norris: Boeing: 787 First Delivery Remains on Track

787 flight testing contiues as Boeing reasses delivery schedule

Boeing continues to make huge strides in the 787 flight test program but now the long pole in the delivery tent is now the amount of rework that Boeing needs to perform on each of the 25 787s that are built according to Flightblogger.

As I had posted earlier, Boeing has been flying the 787 test fleet aggressively over the past two weeks. Boeing told me that they have completed over 70% of the required testing needed to certify the Rolls Royce powered 787. While Boeing has flown 80% of the 2,430 flight hours needed to certify the Trent 1000 version of the 787, flight hours does not necessarily translate into test points that have been completed. Boeing has told me that the number of hours needed to certify the 787 might be fewer than the 3,100 hours that they initially estimated. The number of hours needed certainly has changed however.



While Boeing is doing well on the test flight front, they are approaching the end of flight testing and that means getting the production 787s ready for delivery. Given all the testing that has been done, it is normal that Boeing will have to make changes to the 787s on the flight line, in the final assembly bay and on the parts still at suppliers. This is what change incorporation is all about. However, there are numerous changes that have to incorporated into the aircraft all the way back into the supply chain that Boeing may have to delay deliveries to of some of the aircraft. It is plausible that some of the airplanes that yet to be assembled may actually be delivered before planes that are already built due to the incorporation of the design changes in the supply chain and the time needed to rework the 787s already built. It may be easier to put some of the change into supply chain (which has to be done regardless) than it is to access the areas that need work and incorporate the needed rework. Make no mistake, these changes and rework needs to be done before the airplanes can be delivered and the question is can Boeing get these airplanes ready in time given the amount of work that has to be done.

Flightblogger: Boeing reviewing 787 delivery schedule and post-certification rework looms

Sunday, October 31, 2010

787 and 747-8I news

Well let's start with something new. Below is a video of the first 747-8I, RC001, being rolled to the 747 final assembly slant position in Everett. This aircraft should be rolled out late this year or very early next year with first flight occurring during the 1st quarter of 2011. The 747-8I's flight test program will consist of two aircraft and should take only 4 months as the 747-8F is certifying much of the 747-8 aircraft. First delivery is still targeted for end of 2011 to a Kuwaiti sheikh and to Lufthansa in early 2012.

Video Courtesy of the Boeing Company

On to the 787...The flight test program has increased its pace in the last two weeks, with flying almost 230 hours. The GE powered 787 have been getting a real work out of late as well with both ZA005 and ZA006 flying longer duration missions. While these hours have increased the hours per flight they are not ETOPs flights. It is expected that ETOPs flights won't begin until January.

Boeing, I believe is pretty comfortable with the pace of flight testing at this point that they are going to send ZA006 on a marketing trip to Paris and Amsterdam in order to woo Air France/KLM for their potential 100 aircraft order. The company is expected to chose between the 787 and the A350 though the 787 offering the GEnx may have an advantage. Flightblogger has details about this story in his latest post:

Flightblogger: Boeing appears set to woo Air France/KLM with 787 visit

Thursday, October 28, 2010

Flightblogger talks 787 production and horizontal stabilizers

Now that Alenia has effectively shut down 787 production for another 2 weeks....flightblogger revealed in a new post that the Italian company actually may have shut it down for much longer. The reasoning.....there hasn't been a 787 line move since October 3. There were to have been two more line moves in the month of October whch did not occur. The reason is the needed rework of the horizontal tail assemblies that Alenia is responsible for. Boeing has a whole slew of people in Italy trying to get them back on track but it seems that Alenia's troubles probably run very deep.

With all the issues surrounding the horizontal stabilizer, Boeing chose to mocve the line which left ZA231 without a the tailplane. It was being reworked when the line moved and is now installed on airplane 27 (ZA178).

This has thrown 787 final assembly into a tailspin (pun intended) as the horizontal stabs for airplanes 26 to 29 are being reworked as well as those that are already on the fully assembled production airplanes. Stabilizers meant for certain palnes are being installed on others. This won't be a problem as it is a common part, of course, but it does illustrate what the problems at Alenia has caused downstream in the production process.

Here's how things are laid out in building 40-26 in terms of HTP-airframe

Airplane 25 --> HTP #25
Airplane 26 --> HTP #29
Airplane 27 --> HTP #26
Airplane 28 --> HTP #27
Airplane 29 --> HTP #28
Airplane 30 --> HTP #30 --- this is where Boeing will be back to a normal assembly routine.

As evidenced by the number of 787s on the Boeing flightline where the HTP has been disassembled, it is evident that the problem is quite serious with many of them requiring rework prior to delivery. Boeing has set up a tool to allow easy access to the areas of the HTP that need rework but it's clear that the first 23 production airplanes will have quite a bit of work ahead of them before they are delivered next year. Flightblogger's article is a great read and does raise some flags with respect to Alenia. My sense is that if there is way Boeing can extract it self from Alenia it will. They have already indicated that the HTP for the 787-9 will probably come back in house and I think this is a certainty.

Flightblogger: A Closer Look: Inside the 787 delivery hold and horizontal stabilizer issues

Monday, October 25, 2010

787 production update

UPDATE: Dominic Gates has article saying that the latest assembly pause is due to issxues at Alenia, again. No wonder James Albaugh is bringing 787-9 HTP production back in house. Read his article:

Dominic Gates: Boeing calls two week stop on 787 section deliveries to Everett

This past weekend I referred readers to Matt Cawby's web site which showed two 787 fuselage parts being loaded on the the LCF. Boeing has told me that due to high winds in the area, the parts were placed inside the aircraft so that they were out of the elements.

This must indicate that the back of 40-26 is pretty full with 787 parts since these sections could not be stored in the Boeing facilities at Everett.

Boeing has also said that they will tell 787 suppliers that they will have a slight pause in 787 parts shipments into Everett. The pause will average about 2 weeks depending on the supplier. Both suppliers as well as workers on the final assembly line will continue working on the aircraft as the pause only effects shipments into Everett. Here's Boeing's statement:

With regards to the sections being loaded onto the LCF:

We loaded those pieces back on because forecasters here predicted heavy winds and we didn’t want to have them sitting outside in those conditions. Nothing more.

With regards to the shipment pause:

We will formally notify partners in the days ahead that we are going to have a
slight (it’s different partner by partner but on average two weeks) pause in
shipments. As we said in summer, this is one way we will manage the production
system. Partners are continuing to work during this shipment pause as is the
final assembly team here in Everett.

Delta reaffirms 787 order

In an SEC filing, Delta Airlines reaffirm their intention to take delivery of 18 787-8s that the airline inherited in its merger with Northwest Airlines. NWA was the first US airline to order the 787 in 2004. That order was originally supposed to be delivered between 2008 and 2010. However, Delta will now take delivery between 2020 and 2022...ten years from now. No word on the fate of the 50 options that the carrier also holds.

United Airlines will be the first US carrier to receive the airplane sometime next summer.

Saturday, October 23, 2010

Dreamliner 4 circuit around the country and potential 787 production woes resurfacing?

ZA004 undertook a very long 13+ hour test flight that took it around the country yesterday to test the 787s to test...of all things... the fuel gauge of the aircraft. According to Flightblogger, the test (which I initially thought was an ETOPs flight) was to see how the Fuel Quantity Indication System. The test added a large amount of flight test time to the 787/RR test flight fleet and bought them closer to the 2,430 flight hours needed to certify the 787/Trent 1000 engine combination and allow for deliveries to start to ANA. The Trent 1000 powered 787 test flight fleet has accumulated well over 1,900 flight test hours thus far and the total 787 flight test hours has exceeded 2,100 hours leaving 1,000 flight test hours needed to complete the test flight program.

Flightblogger: 787 goes cross country to check the gas gauge

While the test flight program continues to make progress, there are signs of production troubles on the 787 final assembly line. ZA233, the 29th 787s to be assembled was initially supposed to start final assembly on Oct. 4th. It was pushed back to late October, then early November and now I got news that it won't start assembly until around November 17th...over 6 weeks late. To add to the mystery, Matt Cawby got video of a rear and forward 787 fuselage sections being loaded back on to the 747 LCF in Everett instead of being offloaded. Now the LCF did not depart Everett so my guess is that they might be being stored on board the 747 LCF. I am hoping to hear from Boeing about any production pauses on the 787 line and what reloading of the fuselage sections on the LCF may mean.

Thursday, October 21, 2010

787 now in final stages of flight testing

Boeing Chief, Jim McNerney said during the third quarter earnings conference call that the 787 flight testing is in the final stages. Flight testing has picked up in the last week as the 787s have racked up just under 2,100 flight hours and the number of hours needed to certify the Trent 1000 powered version of the 787 is down to under 550. Another important milestone on the 787's road to certification is completion of the required number of simulated flight cycles on the fatigue test airframe (ZY998) for first delivery. Boeing will continue to fatigues test the 787 airframe for the next 3 years but they needed to get a certain number of cycles completed before they delivered the first airplane to ANA. All this work was done on the ground at Everett. Boeing has reiterated its intention to delivery the 787 in mid 1st quarter 2011. McNerney also said that Rolls Royce has a hardware and software fix to prevent the recurrence of the uncontained engine failure that took place in Derby, UK in early August.

Still ahead for the 787 is the all important ETOPS type certification where the specific engine-airframe must be approved for ETOPS flights mainly across the Atlantic and Pacific. Later each individual carrier must get it ETOPS operational certificate. This testing is expected to get underway around January.

In the meantime Boeing continues production of the 787s at Everett. McNerney said that supplier shipments are picking up. Boeing has had to slow down production twice this year in order to allow the supply chain to catch up and reduce the travelled work coming into Everett. Boeing is expected to start final assembly on ZA233 (LN 29) a 787 for Air India.

Lastly, Boeing is talking about bringing production of the horizontal stabilizers for the 787-9 back in house according to Dominic Gates of the Seattle Times. Boeing is still finding workmanship issues coming out of Alenia. According to the article, Boeing has found more issues on the test flight airplanes as well as a few of the production airplanes. A couple of the test flight airframes have been fixed and they're working through the others. I wonder if this was the reason the 787s didn't fly as much between mid September and mid October? You can read Dominic's article here:

Dominic Gates: Boeing considers building 787-9 horizontal tails in-house

Finally, Flightglobal has an article out saying that Boeing believes that the majority of 787 orders will be for the 787-9 model. This is supported by many of the order conversions from the 787-8 to the 787-9 by airlines. You read the article here:

Flightglobal: Bigger 787 variant to boost order share: Boeing



Friday, October 15, 2010

Ten Months In...

The 787 test flight program reached milestone yesterday with 2,000 flight test hours accumulated in the 10 month old flight test program. The milestone was reached when ZA002 flew a 20 minutes test flight to Moses Lake Airport. However, through the last half of September and the first half of October there has been a very noticeable slowdown in the flight test program. In period from Aug. 15 to Sept. 14th, Boeing posted 362.5 flight hours on the 787 spread across 121 flights. From Sept. 15th to Oct. 14th, the 787s flew only 165 hours on 71 sorties. That's a reduction of over 54%. With ZA004 being out a month starting in November, Boeing will have to depend on the remaining three airplanes sustain the flight test program.

Boeing still has over 1,100 test flight hours to complete. The 787-Trent 1000 flight test fleet achieve another milestone by reaching 75% of the required (2,430) flight test hours. That means that the Trent 1000 flight test fleet has a little over 600 flight test hours to complete certification. Boeing says it has completed over 65% of the required testing conditions thus far.

Next month Boeing plans to change out the engines on ZA004 from the current Trent 1000 with package "A" to the package "B" powerplants. The change out should take about a month including ground testing and this airplane will be back in the air sometime in December. It does look like that the first few Trent powered 787s delivered to ANA will be the package A versions though I'm not sure when Rolls Royce will start delivering the package "B" to Boeing.

In the meantime Boeing has flown the Trent 1000 aircraft fairly aggressively in the last few days but I do still believe that they still have a long road ahead of them despite being almost three quarters of the way through the flight test program. If Boeing can fly the four test airplanes about six and a half hours a day for the next three months, they can achieve certification of the Trent powered 787s a month before first delivery. The GE powered airplanes are over 27% done with their test flight program but currently both airplanes are in lay ups and have not flown since early October. I'm still trying to find out when those airplanes are planned to return to the air.

While the test flight program continues on, Dominic Gates of the Seattle Times reported on the 787 that are piling up outside on Everett's flight line:

Dominic Gates: Boeing 787s stack up at Paine Field awaiting FAA approval

ZA102, the first production airplane to fly is now slated to have it's first flight around November 24th as the aircraft continues its final fitting out before being rolled out, presumably early next month.


Boeing Photo

Lastly, the 747-8I program achieved a milestone itself when the first airplane entered final body join. This aircraft should roll out at the end of this year or early next year with the flight test program due to start in early 2011.

Guy Norris has a blog post out that also details the 747-8F test flight program thus far:

Guy Norris: 747-8I Comes Together

Here's Boeing's Press Release:

Boeing Joins Fuselage Sections for First 747-8 Intercontinental

EVERETT, Wash., Oct. 15 /PRNewswire/ -- Boeing (NYSE: BA) moved closer this week toward completing assembly of the first 747-8 Intercontinental as mechanics in Everett, Wash., loaded the forward and aft fuselage sections to join with the wing and center section.

The 747-8 fuselage is 250 feet 2 inches (76.3 meters) long, which is 18 feet 4 inches (5.6 meters) longer than the 747-400. The stretch provides space for 51 additional seats to accommodate 467 passengers in a typical three-class configuration and offers 26 percent more cargo volume.

"Final body join is an important milestone for the 747 program," said Pat Shanahan, vice president and general manager of Airplane Programs in Boeing Commercial Airplanes. "It is a major step toward completing the structural integration and building out our all-new interior. We now have the first real look at the size and distinctive shape of the 747-8 Intercontinental. This is going to be a superb airplane for our customers both from an aesthetic and a performance perspective."

The 747-8 is the new high-capacity 747 that will give airlines the lowest operating costs and best economics of any large airplane while providing enhanced environmental performance. The airplane also features a 787 Dreamliner-inspired interior that will offer passengers a greater feeling of space and comfort.

The 747 program has orders for 109 747-8 Freighter and Intercontinental airplanes. Thirty-three of those are for the 747-8 Intercontinental, with orders coming from Lufthansa, Korean Air and eight VIP customers. The first 747-8 Intercontinental delivery is scheduled for late 2011 to a VIP customer.








Wednesday, October 13, 2010

787 keeps movin' along

As the time to first delivery draws closer, Boeing is ramping up both production as well as the pace of flight testing.

Flight Testing

The 787 flight test fleet is closing on 2000 flight hours flown, they can potentially break through that mark today. The Rolls Royce powered 787s got a real work out on Oct. 12th flying almost 24 flight hours during the day and breaking through the 1800 flight hour mark for the RR/787 flight test combination. Hopefully this signals a push to accumulate the remaining 35% flight test requirements needed to certify the Rolls powered 787s. Boeing has completed almost 75% of the require flight test hours needed to certify the Trent 1000 powered 787s so they are getting close.

While the first four 787s are being pushed, ZA005 is at Everett for some standard inspections as well as fuel transfer tests. ZA006 remains at Boeing Field going through the post first flight lay up where additional flight test instrumentation is being installed. I haven't heard when those two airplanes will be flying again. Currently about 27% of the GEnx/787 flight test hours have been flown.

ZA102 is now scheduled to fly around November 24th instead of November 9th though that date may change. This will be the first flight of a production standard 787 with a full customer interior. Both ZA101 and ZA102 have its Trent 1000 engines. ZA101 will undertake ground testing though I'm not sure if it has a customer interior as well.

Next month ZA004 will down for about a month while it gets new Trent 1000 engines with the package "B" improvements meant to bring the engines to within 1% of the promised SFC (specific fuel consumption) that Rolls Royce promised to its customers.

Production

As the flight test wring out the 787 for delivery, Boeing is slowly ramping up 787 production. Currently ZA230 will moved out of position 4 in building 40-26 and the line should pulse on October 15th but the next airplane ZA233 (LN 29) won't be loaded into position 1 until October 26th. I'm still trying to find out why the 11 day delay. ZA234 (LN 30, a 787 for Air India) is due to start final assembly 9 days later. This indicates that Boeing is attempting a 9 to 10 day run with each airframe is in each of the 4 assembly positions 9 to 10 day. This translates to a final assembly run for each 787 of about 36 to 40 days in building 40-26. At that rate, Boeing should be at ZA236 (LN 35, the 35th 787 being built is for Air India) by the end of the year though they will have 30 787s built and out on the flightline.

Speaking of the flightline, the parking spots for airplanes at Everett are getting full. So full that Boeing is now parking airplanes in a small ramp area in fron of the Future of Flight Museum. According to Matt Cawby, Boeing has leased out space at Everett near the air control tower as well asto the south of the asembly halls in order to store built but undelivered 787s.

Lastly, Flightblogger took a trip to 787 suppliers in Asia and has put up an excellent post of the 787 suppliers in Korea with some great photos. It is a great read.

Flightblogger: From Busan to Boeing: 787s Asian Supply Chain Part 1

Tuesday, October 5, 2010

787 Production Update

Over the next few months Boeing will start final assembly on 787s for Qatar, Korean, United/Continental and Polish Lot Airways. Of the first 57 production 787s to come off the assembly line, ANA will get the most...15 of which 10 are already assembled. This will be followed by 8 for Japan Airlines, 8 for Air India, 5 for United/Continental, 4 for Ethiopian and 3 for China Southern.

Qatar Airways will see it's first 787 assembled by ZA460 (LN 57 or the 57th 787 off the line). Because of the noise tha this airline has created surrounding the delays to their order, Qatar will get 4 787s in quick succession. They will receive the 57th, 58th, 60th and 62nd 787 to be built. Qatar is planning for introduction of these airplanes in 2011. A 787 for LOT will be sandwiched between the two Qatar 787s.

You can see the list below:


Boeing releases video of 787 landing performance


Boeing Video

Boeing released a real nice video of the 787 landing tests that it had conducted over the past month including a portion where ZA001 is dragging its tail along the runway to determine the VMO (Velocity Minimum Unstuck) as well as water landing tests and cross wind landing tests conducted by ZA002 in Iceland.

Pilot Mike Carricker give a great narration of what's going on with these landing performance tests.

Monday, October 4, 2010

Boeing Statement on ZA006 First Flight

Boeing Photo

Boeing released a statement announcing the first flight of the final test 787. However the first test flight was cut short due to a cooling fluid issue according to a Tweet by Flightblogger. The press release doesn't mention the flight being cut short. It mentions the flight lasting a little over an hour as well as reviews the 787 testing to date. Over 65% of the test conditions needed to certify the Rolls Royce powered 787 have been completed according to Boeing. Boeing has also completed 15 cycles on the fatigue test air frame (ZY998) and need to complete 10,000 by the time first delivery is made to ANA in mid February. Boeing is also looking to increase the production of 787s. The 28th 787 (ZA232) to be built just entered final assembly and the next one, ZA233, will enter final assembly 10 days later on Oct. 14th. This could mean that Boeing is attempting a 3/month production rate. Because of the production 787 already built, Boeing has started to store 787 in an area called Kilo North which is a newly constructed ramp area just south of the Future of flight Museum. Three 787s (ZA150, ZA151, and ZA176) were moved to this area over the weekend.

Flightblogger also has a couple of posting up with regards to today's flight:

Flightblogger: Sixth and final 787 test aircraft completes abbreviated test flight

Flightblogger: Liquid cooling squawk tied to abbreviated ZA006 first flight
Sixth Boeing 787 Makes First Flight, Testing Program Making Good
Progress

EVERETT, Wash., Oct. 4 /PRNewswire/ -- The final Boeing (NYSE: BA) 787 Dreamliner to join the flight test fleet made its first flight today from Paine Field in Everett, Wash. The airplane, ZA006, is the second 787 equipped with General Electric GEnx engines to fly.

Captains Christine Walsh and Bill Roberson were at the controls during the 1 hour and 4 minute flight. The airplane landed at Boeing Field at 12:45 p.m. (Pacific time).

"It's great to have our last flight test airplane join the fleet," said Scott Fancher, vice president and general manager of the 787 program. "We have been focused on completing the testing required for certification of the 787 with Rolls-Royce engines, because that is the first model we deliver. A great deal of the testing that we've done also applies to the 787s with GE engines and won't need to be repeated," said Fancher.

There is, however, a smaller portion of testing that is unique to the engine/airframe combination. In general, this portion includes noise testing, extreme weather operations, function and reliability, and extended operations. In addition, testing to verify the airplane handles the same regardless of engine type and that the systems work on both models is required.

Some additional flight tests will be performed on one of the production airplanes, the ninth 787 to be built, but it is not considered a full-time member of the flight test fleet.

787 Testing Progress Report

In addition to achieving first flight of ZA006, the Boeing test team has completed a number of flight test milestones in recent weeks.

Boeing wrapped up a series of natural and artificial icing tests, meeting all requirements with no changes required. Pilots reported that the airplane continues to handle well even in the presence of ice.

Flight loads survey testing, which demonstrates the pressure distribution on the airplane structure throughout the phases of flight in a variety of configurations, also has been completed. The team conducted this testing on ZA004 primarily at the airport at Victorville, Calif. Analysis of this testing continues.

A dramatic series of tests that stress the airplane's brakes, called maximum brake energy testing, was completed in late September at Edwards Air Force Base, also in California. ZA001 conducted this testing as well as a series of extreme takeoff and landing conditions including minimum takeoff speed testing. Earlier in the month, ZA001 completed wet runway testing at Roswell, NM.

ZA003 flew to Glasgow, Mont., to complete community noise testing. All results were within expectations.

As a result of these tests and others, all takeoff performance and handling characteristics testing is complete for the initial version of the 787. Additional testing will be required for 787s equipped with GE engines.

The 787 flight test program has logged more than 1,900 hours over 620 flights and completed more than 65 percent of the flight test conditions for 787s with Rolls-Royce engines.

Equally important to the testing required in the air is the ground testing required to certify a new airplane. Boeing has completed well over 4,000 hours of ground testing on the same airplanes that are in the flight test program.

In addition, fatigue testing has started at a test rig in Everett. Fifteen flights have been simulated. Federal regulations require Boeing to conduct twice as many flight cycles as any airplane in revenue service. Boeing plans to have completed 10,000 flight cycles prior to first delivery.

"We continue to be extremely satisfied with the performance of the 787 in its testing operations," said Fancher. "This airplane handles wonderfully and will be a valuable tool for our customers."


How long ZA006 will be out because of the issue that cropped up during flight is unknown at this time.



Dreamliner 6 flies...for an hour

ZA006 the sixth and final test flight 787 finally has flown after a lengthy delay due to numerous unspecified issues that plagued the aircraft in the month leading up to today flight. The airplane took off at 11:43 AM local time and flew for exactly one hour before diverting to Boeing Field at 12:43 PM. According to Flightaware.com, the airplane was supposed to fly for about 2 hours before landing at Moses Lake and then take off and fly direct to Boeing Field. Boeing later said to the Seattle PI (Aubrey Cohen) that maintenance issues forced the flight to be terminated early. Apparently the gremlins that has plagued its first flight are still around.

At this point in the test flight program the 787 should be mature enough that there wouldn't be a need for extensive flight control checks or testing especially if ZA006 has flown with modification arising from issues discovered during the test flight program to date.

This airplane is minimally instrumented and will undertake ETOPS testing as well as HIRF (High Intensity Radiated Field) Testing, and electromagnetic effects testing.

In the meantime, Flightblogger and Guy Norris each have put up posting about ZA006 as well as some flight testing updates. ZA001 and ZA002 should be back in the air tomorrow and ZA004 should be flying again sometime this weekend.

Flightblogger: Better Know a Dreamliner - Part Six - ZA006

Guy Norris: 787 - show time for ZA006

Production has restarted on the 787 final assembly line in Everett with ZA232 (LN 28) moving into the first position to be assembled.

In other 787 news, the 787-9 seems to be getting popular amongst current 787 customers. ANA and know Vietnam Airlines are now customers for the larger 787 mainly because of the better projected performance of this version over the 787-8. Vietnam Airlines converted its 16 787-8 into the 787-9. ANA converted 15 of it 55 787-8 into the 787-9. This version of the 787 is due to be delivered to Air New Zealand at the end of 2013.

Sunday, October 3, 2010

787s move around Paine and ZA006 first flight on 10/4

Boeing repositioned a few 787s around Paine Field this past weekend with two RAM and one JAL 787 moved to a new parking site known as Kilo North. There are still a couple of 787s stored in front of Boeing main assembly building as well including a JAL 787 and one for LAN. Of the 10 787s built for ANA three are in the Hangar being readied for delivery ZA100, ZA101 ad ZA102) while 6 more are out on the flightline and one more on the flightline tent getting its side of body modifications done.
Matt Cawby got some great photographic documentation on these moves that occured yesterday:

Matt Cawby's Oct. 2 Blog Post

There should be a line move tomorrow where the 11th 787 for ANA (ZA116) and the 28th 787 (ZA232) will be moved into position on the final assembly line at Everett. Boeing is resuming final assembly after a pause to allow suppliers to catch up and to put the supply chain in a position to meet the production ramp up that is to occur around this time. Boeing hopes to be putting out a little less than 3 787s a month starting with ZA232.

Even more important is tomorrow, the final test 787, ZA006, will have its first flight. No flight time has been mentioned but in the past Boeing has flown the 787 on its first flight at around 10AM PST (1PM EST). The aircraft will be flown to Boeing Field where it will conduct a few days of ground tests before resuming flight testing. I hope to have more on ZA006s first flight tomorrow.

Wednesday, September 29, 2010

What are the 787s doing?

Well some of you reading this blog might be wondering about the activity (or lack there of) of test flights on the 787 test fleet. Here's a run down:

ZA001 - Having it's left engine changed (reason unknown); should return to flight around 10/5
ZA002 - In ground tests; should return to flight around 10/5
ZA003 - Maintenance; should return to flight on 9/30 (tomorrow)
ZA004 - Thrust reverser and misc. engine upgrades and additional instrumentation being added; should return to flight on 10/9
ZA005 - Engine change; should return to flight on 10/12
ZA006 - Undergoing flight readiness review for first flight; first flight on 10/4 (not 10/2 anymore)

Interestingly, ZA006 is in the paint hangar for an unknown reason but is still scheduled for its first flight.

Flightblogger, in between tours of various 787 supplier facilities, had time to put up a 787 post.

Some notable news:

  • ZA101 (LN 8) has received its Trent 1000 engines
  • ZA102 (LN 9) performed gear swing tests
  • ZA102 has received a partial passenger cabin (between doors 1 and 2 and another section between door 3 and 4).
  • ZA001 has successfully completed the max energy RTO tests
  • 787 production is set to resume after this weekend with LN 28 (ZA232) for Air India set to start final assembly. This should mark the start of production at just under 3/month.

You can read more in his blog:

Flightblogger: 787 News in Brief: Trent 1000s, ZA006 first flight, float concludes, 787s 8 & 9, RTO in the bag, plus 737 and 747-8

Guy Norris also has a 787 update on the Aviation Week blog roll Things With Wings. He elaborates on ZA006's road to first flight as well as on the activities surrounding the other 5 test flight airplanes.

Guy Norris: Second GE 787 Set to Fly

Until the 787's are back in the air again, here a re some Boeing videos on the 787 for your viewing pleasure:

All Videos Courtesy of Boeing






























Tuesday, September 28, 2010

Boeing and Rolls Royce move to put Trent 1000 issues behind them

Boeing and RR execs are meeting today and tomorrow to review the way forward with the Trent 1000 after the uncontained failure in early August.

In an article on Bloomberg News, Rolls Royce will be presenting Boeing 787 executives with their plan to fix the Trent that would not put the first delivery, scheduled for mid February 2011, in jeopardy. Boeing, presumably knowing some of the general facts of the plan said that they believe they will be ok after getting the detailed briefing.

Susanna Ray: Boeing Scrutinizes Rolls Recovery plan for 787 Dreamliner Jet

Lastly, Dominic Gates of the Seattle Times, has an article out talking about the 787, 747-8 problems and the re-engining of the 737.

Dominic Gates: Albaugh hopeful on engine fixes for delayed 787

Saturday, September 25, 2010

Guy Norris details upcoming 787 test schedule

Today Guy Norris detailed the upcoming tests for the 787 which includes the max energy RTO (rejected take off) certification testing as well as details of the testing that ZA102 (LN 9) will be tasked to perform as part of the "first of model" testing that will be performed on production standard 787s.

Earlier this evening, ZA004 returned to Boeing Field from Glasgow Industrial Airport where it was taking part in community noise testing.

Tomorrow should be a very busy day for ZA001 where it will be performing the max energy RTO to test the carbon braking system of the 787. If it passes this will be a major milestone that will be passed on the road to certification.

Guy Norris: 787 max energy brake tests today

Friday, September 24, 2010

787 news - Sept. 24, 2010

Boeing Photo
Lots of small bits and pieces.

To start off, ZA006 has seemed to have attracted a little bit more attention with both Flightblogger and Susanna Ray of Bloomberg News putting up stories after my last post came out announcing another delay to its first flight.

Well first a little bit of good news for this particular airplane....First flight is no longer scheduled for Oct. 4th but now has been pushed back to Oct. 2...eight days from now. In the last couple of days FAA officials were on board ZA006 for engine run tests. I still don't know if the aircraft has undergone its mini gauntlet or not.

The last test flight 787 has been delayed due to unspecified "challenges" in getting the airplane ready for it's first flight. My personal feeling is that they will get the airplane to fly in the next few day but at this point in the program with hundreds of hours of ground testing and build experience behind them already, Boeing should have retired much of the risk at this point that would lead to the 787s first flight. I have to wonder if these issues can have an effect on getting the production 787s ready for their first flight and eventual delivery to customers? At this point in the development and with all the delays taken into account, the 787 and the systems on board should be a very mature aircraft.

The 787 production aircraft are gearing up for their future as I write this. Already ZA102 (LN9), which will be the next 787 to fly, is now due to have it's first flight on November 8 instead of November 1st. However, I can confirm that this airplane is getting the passenger interior that ANA has ordered (being installed right now) and will fly with a full passenger interior layout. In due course I expect ZA100 (LN7) and ZA101 (LN8) will get their passenger interiors installed very soon. The installation of passenger interiors does highlight how close Boeing is to the finish line with the 787 flight test program though there are still issues, such as the unexplained (as of now) failure of a Trent 1000 IP turbine, that Boeing still has to address. Flightblogger has an article about that on the Flightglobal web site.

Flightblogger: Cause of 787 engine test failure remains unclear

Flightblogger: Trent 1000 engine failure investigation hangs over 787

Flight testing seems to have taken a few days off with no test flight yesterday and no flight plans filed for any of the 787s today (so far). v Boeing would need to fly the Rolls Royce equipped 787s an average of six hours and twenty minutes a day for the next 113 days (mid January) in order to certify the Rolls Royce powered 787s. They would have to fly the GEnx-1B powered 787s an average of 4 hours per day for the next 113 days in order to have that aircraft/powerplant combination certified by mid January.

Lastly, construction workers in South Carolina are topping off the 787 final assembly hall this weekend. The building should be completed by next summer and the first 787 should be rolling off in early 2012.

Here's Boeing Press Release:


Boeing Marks Construction Milestone on South Carolina 787 Final Assembly Building

NORTH CHARLESTON, S.C., Sept. 24 /PRNewswire/ -- Boeing (NYSE: BA) today marked completion of the steel framework for its new 787 Dreamliner Final Assembly building with a special topping-out ceremony. The event was held in conjunction with BE&K/Turner, the design-builder of the facility.

The final piece of steel was put into place on the 1.1 million-square-foot (102,193 square meters) structure less than a year after the November 2009 groundbreaking. Approximately 18,000 tons of steel are used in the building.

"By this time next year, the Final Assembly building will be complete, and we will have begun production of the first South Carolina-built 787 Dreamliner. That is tremendous – from green-field site to airplane production in about 18 months," said Marco Cavazzoni, vice president and general manager, 787 Final Assembly and Delivery. "The support we've received and continue to receive from our South Carolina partners and suppliers, as well as the state and local community is amazing and is one of the main reasons we've been able to reach these significant milestones in such a short timeframe."

Construction on the new facility is on schedule, with airplane production due to begin in July 2011 and first delivery in first-quarter 2012. At full production rate, Boeing will assemble and deliver three 787s per month from South Carolina to customers around the world. The South Carolina Final Assembly facility will be one of only three in the world producing twin-aisle commercial jetliners.

Wednesday, September 22, 2010

ZA006 first flight delayed....again; 787 test flight pace slows down

UPDATE: Susanna Ray of Bloomberg News just posted a news story on ZA006:

Susanna Ray: Boeing's Final Test 787 Faces 'Challenges' for Flight

I've just received news that the first flight for ZA006 has been delayed yet again. Originally this airplane was to flown in April-May but now first flight is scheduled for October 4th...12 days from now. No reason is apparent in this newest delay.

Meanwhile the pace of 787 flight testing has slowed down with only ZA001 and ZA004 conducting flight tests the last few days. I do believe that the other three airplanes are in either lay up or conducting ground tests. The RR/787 test program has exceed 70% of the planned 2,430 flight hours needed for certification while overall the 787 has exceeded 60% of the planned 3,100 flight hours.

Lastly, Boeing has released a video of the first aft fuselage section for the 747-8I as this airplane moves closer to final assembly. Check out the Boeing video below: