Boeing rolled out the first 787 for American Airlines on Oct. 6th. The aircraft was originally supposed to be delivered in November is now slated for delivery on December. It is on the 40-51 Ramp finishing up assembly activities followed by painting.
|
First 787 for American Airlines, Photo by MOONM |
Additionally Boeing has finally delivered one of 3 787-8 flight test aircraft to a customer. The Fuerza Aérea Mexicana (Mexican Air Force) took possession of ZA006, the last test flight aircraft. After undergoing extensive re-work and re-build, the aircraft was bought up to FAA certificate standards though I am not sure if it has it full passenger interior installed or not. The aircraft is at the Charleston Delivery Center and is supposed to fly away tomorrow Oct. 9th).
|
ZA006 at the Charleston Delivery Center, Photo by reader |
Boeing 787 production looks to be in ok shape but it is taking quite a bit of time to deliver the 787 into customer hands. I have observed a continuing movement of delivery dates to the right of the schedule that at this point I think Boeing will deliver about 10 to 11 787s in October. This is not a bad number but it only gradually reduces the built up inventory. I examined the average number of days it took Boeing to get an aircraft from final assembly to delivery. I took out outliers or aircraft where I did not have complete information. The results may surprise you:
February, 2014 - 114.8 days
March, 2014 - 117.6 days
April, 2014 - 126.4 days
May, 2014 - 112.4 days
June, 2014 - 206.5 days
July, 2014 - 141.4 days
August, 2014 - 117.7 days
September, 2014 - 127.5 days
These averages need to be put into proper context. They include the 787-9 (from June on) These early 787-9s had to go through change incorporation and required more build time compared to the 787-8 thus the number of days fro the start of final assembly to delivery were higher for these airplanes and distorted the results. Here are the average number of days it took to build the 787-8:
February, 2014 - 114.8 days
March, 2014 - 117.6 days
April, 2014 - 126.4 days
May, 2014 - 112.4 days
June, 2014 - 125.6 days
July, 2014 - 121.1 days
August, 2014 - 117.7 days
September, 2014 - 118.4 days
As you can observe the average time it takes to build the 787-8 (this includes both Charleston and Everett) is fairly stable. As Boeing get more familiar with building the 787-9 and the need for change incorporation goes away as well as the need for extensive time to finish traveled work, we should see build times for both versions of the 787 go down to below 100 days.
There is still no known timetable when the stabilization of the production system will occur and it appears that Boeing is continuing to struggle with traveled work which has been the bane of the 787 program currently. There has been flashes of hope for a 90 day rate or lower (start of final assembly to contractual delivery). For example Boeing delivered a 78 to Tui Travel in 84 days from Everett and Charleston delivered a 78 in 86 day to Kenya Airways. 2015 should bring much required and welcomed improvements to the 787 production system.
787 Full Production Table