Thursday, March 22, 2012
JAL to receive first 787 this weekend, possibly two more next month
Japan Airlines is preparing to take ownership of its first and possibly second 787 this weekend. I'm still trying to find out but ZA177 (JA822J, L/N 23) and ZA179 (JA825J, L/N 33) are supposed to be delivered this month with at least one to be delivered this Sunday (March 25) and possibly both being delivered on the same day. Fly away is scheduled for Monday March 26th at 4PM local time. It does seem certain that both ZA177 and ZA179 will be delivered this month.
According to sources, JA806A (ZA117, L/N 40) for ANA is scheduled to be delivered on March 25th as well. It would be an unusual delivery day for Boeing with the company delivering 787s to two customers that are competitors. This is not yet final though and I am trying to confirm. This airplane should also be delivered in March nonetheless.
For April, Boeing is planning to deliver 3 more 787s also all to ANA and JAL. ANA is tentatively scheduled to receive ZA105 (JA808A, L/N 42) around April 17th. Boeing has pulled out two more 787s to the Everett flightline, JA826J (ZA180, L/N 37) and JA827J (ZA181, L/N 38). Both are tentatively scheduled to be delivered to Japan Airlines but the date is uncertain. Again all this is tentative.
One observation which is unsurprising is that most of these airplanes are late build 787s (L/N 33 and higher). Boeing is expecting to work on the early builds and deliver them from now until early 2014. Boeing's first delivery to Air India is also a late build airplane, VT-ANH (ZA236, L/N 35). This airplane was flown to San Antonio for unknown reason though I suspect it is to probably do some last minute work. This airplane should deliver in May. Going forward into the summer we should start seeing deliveries made to Qatar in addition ot AI, JAL and ANA. United will come later in the fall as will LAN, Ethiopian and China Southern.
Thursday, March 8, 2012
Update to March 2012 787 deliveries
I just got some updated delivery dates for 787 deliveries this month.
ZA117 (LN 40, JA806A) on March 21 for ANA
ZA177 (LN 23, JA822J) on March 29 for JAL
ZA179 (LN 33, JA825J) on March 29 for JAL
The two JAL deliveries moved up 2 days while the ANA delivery slide by 5 days. Again this information is preliminary and may change as conditions change at Boeing. Again no word on delivery to Air India of ZA236 (LN 35, VT-ANH). Special thanks to Snooze Control. I would also like to ask Snooze Control to send me an email to ureshs at aol
Wednesday, March 7, 2012
Good news for the 787
The second bit of good news came out today when Boeing announced that they had completed the certification test program for the 787 with the end of the certification program for the GEnx-1B powered version of the Dreamliner. ZA236 (LN 35, VT-ANH) had completed the final bit of F&R and ETOPs testing late last month and flew back to Everett. Boeing had also completed all the final ground tests that they needs to perform. I anticipate that Boeing should receive final type certification for the GEnx powered 787 in the next 1 to 2 weeks. This should still give the company time to deliver the first GE powered Dreamliner to Japan Airlines by March 31st. In fact ZA236 which just completed the certification test flights is back out on the flightline at Everett but painted in Air India colors this time indicating that this aircraft might soon be delivered soon.
Currently, information that I received a bout two weeks ago shows that Boeing has planned to deliver three 787s this month. They are:
ZA117 (LN 40, JA806A) on March 16 for ANA
ZA177 (LN 23, JA822J) on March 31 for JAL
ZA179 (LN 33, JA825J) on March 31 for JAL
In addition Boeing is not planning any B1 flights for any 787. The three aforementioned 787s have all had their B1 flights though they have yet to fly any subsequent pre-delivery flights. IT does seem that the shim issue has slowed down the pace of pulling out the prepared 787s to the flightline to begin the pre-delivery process. The other unknown is if ZA236 will be delivered this month. A lot of that will depend on if the airplane is ready and if Boeing and Air India have concluded negotiations on compensation for the 787 delays.
Lastly, now that the build rate has gone up in Everett, Boeing will still need to park those new 787s around Everett. Boeing has started parking 787s on the Kilo 6 (K6) taxiway at Everett. This taxiway is in the southwest part of the airport near the Flying Heritage Museum. The first one to be parked there was ZA288 (LN 53) for United Airlines. Space is becoming a premium at Everett and the pace of 747 and 787 deliveries has slowed. April will be critical as the 787s that are built at the newer rate will be pushed out the door and that means even more 787 on the Everett ramp unless Boeing starts to deliver those that are in re-work during April. As added pressure, Boeing is also upping the 747 rate to 2/month later this year.
Thursday, February 23, 2012
Getting close to the finish line
Boeing's efforts to complete 787 flight testing with the GEnx-1B engines are close to being completed if they aren't finish already. ZA236 has flown just under 153 flight test hours thus far. The aircraft needed to fly about 150 F&R/ETOPs flight hours to finish the certification program for this version of the 787. Boeing has not confirmed that they are finished with the tests as of yet. The true indication that they are complete is when ZA236 flies back to Everett to finish preparations for delivery to Air India.
As far getting other 787s ready for delivery, there are about 10 787 at the Everett Modification Center that are undergoing change incorporation or shim inspection in the rear fuselage as well as one airplane in 40-24. Three of these airplanes were aircraft that are close to being delivered (to Japan Airlines or ANA) including ZA177 (LN23, JA822J), ZA179 (LN33, JA225J) and ZA117 (LN42, JA806A). Once these airplanes are inspected and repaired (if needed) then they will continue they typical preparations for delivery. The list of 787s at EMC is below with the locations highlighted in green. These are the airplanes I anticipate will be the next few that will be delivered. Interestingly enough these include a few of the very early build airplanes, ZA100 (LN 7), ZA534 (LN 10), and ZA501 (LN 12).
Jim Albaugh, speaking in Singapore has said that up to 55 787s would have to be inspected and repaired for the flaw. To put it in proper context, this would include all the airframes from LN 4 to LN 59, the latter of which is currently in position 1 in 40-26 and just starting final assembly. This number also includes the 5 airframes that have already been delivered to ANA but does not include any airplanes sections that have yet to be delivered to Everett for final assembly.
Friday, February 10, 2012
No 787 Deliveries in February
Saturday, February 4, 2012
Boeing starts final 787/GEnx F&R/ETOPs testing?
It is unknown, at this time, how many hours still need to be flown for the final phases of this test program but when Boeing flew the F&R/ETOPs test for the Rolls Royce powered version of the 787, they ran it to 300 flight test hours with ETOPS testing being done concurrently with the F&R testing on the test flights. Boeing has already run some of hte F&R/ETOPs testing on ZA006, a test airplane which is currently undergoing re-work and refurbishment ot a production standard airplane in San Antonio. The FAA is requiring Boeing to fly some portion of hte F&R/ETOPs testing o na production standard airplane. This testing has been delayed due to technical issues with ZA236, the nature of which is currently unknown.
Assuming that Boeing will still have to fly 300 flight test hours and assuming that half of this testing done by ZA006 is considered complete by the FAA, then Boeing may have to run about 150 flight test hours on ZA236. Assuming about 8 flight test hours per flight that would mean that ZA236 would have to fly 20 days in order to complete final certification flight tests for the GEnx 787. That would leave roughly a week for Boeing to submit the final type certification paperwork to the FAA and to get their final review and approval so that Boeing can begin deliveries to JAL and Air India a the end of this month. This is very tight. Current Boeing plans show have that ZA177 (L/N 23, JA822J) and ZA129 (L/N 33, JA825J) are being prepared for delivery on Feb. 27th with ZA179 scheduled to make its first flight on Feb. 7th. Whether Boeing can hold to this schedule depends on the pace of the F&R/ETOPs testing and any issues that may be revealed as a result of this testing.
Additionally Boeing has an ANA 787, ZA117 (L/N 40, JA806A) tentatively scheduled for delivery around Feb. 19th with a first flight date of Feb. 7th. All these schedules are tentative schedules and may (probably) will change over the course of the next few weeks.
Tuesday, January 17, 2012
Another ANA 787 delivered, another being prepared
ZA117 (JA806A, L/N 40) made an appearance on the Everett flightline after passing the last few months insidethe EMC. Thanks to Johanny who gave us a link to a flickr page maintained by "Simpilot459" which shows this aircraft with lights on at the Compass Rose at Everett. This is scheduled to be the next 787 delivered.
See ZA117
However weather in the Pacific Northwest may become an issue over the next few days that may disrupt the delivery schedule. ZA236 (VT-ANH, L/N 35) was scheduled to fly yesterday but was postponed due to a winter storm that is hitting the Pacific Northwest. This storm is expected to dump snow in the region over the next few days. It's unlikely that this plane will fly its B-1 flight until the storm passes or is reduced in intensity. I'm estimating that it probably won't fly until the end of this week. Likewise, ZA117 is supposed to have it's B-1 flight around the 20th but this is looking increasingly unlikely as it was just pulled out of the EMC and will need to have its first engine start and other pre-flight activities done prior to the flight. I can't se this plane flying before the end of next week.
The end result is that deliveries will be delayed due to the storm as it moves the schedule to the right.
Thursday, January 12, 2012
January 787 delivery update part 2
ZA102 (JA804A, L/N 9) is scheduled to be delivered today and may flyaway a couple of days from now. There were no further test flights of both aforementioned aircraft since January 10th.
ZA117 (JA806A, L/N 40) is still scheduled (tentatively) for delivery on the 30th but this should be taken with a grain of salt as the aircraft has not appeared on the flightline yet.
Further I've gotten information that ZA236 (VT-ANH, L/N 35) may make its first flight around Jan. 16th though this is still up in the air (so to speak). This aircraft is to conduct the final portion of F&R/ETOPs testing on the GEnx powered 787 for certification purposes. If Boeing is able to get this part of the program completed in time with certification of of the GEnx 787s then They may be able to deliver two GEnx 787s starting in February. One each would go to Japan Airlines (ZA177, JA822J, L/N 22) and Air India (ZA236, VT-ANH, L/N 35). Boeing also has a 787 penciled in for ANA (ZA105, JA808A, L/N 42) next month.
There are no definitive delivery dates for these airplanes for obvious reasons and these airplanes themselves may not deliver next month due to continued issues revolving the amount of re-work and the allocation of resources to effectively deal with the amount of work. there should be further clarification of the 787 deliveries on about two weeks when Boeing has it's 2011 earnings conference call.
Saturday, January 7, 2012
Additional January 787 delivery information
JA804A (ZA102, L/N 9) to deliver on Jan. 9
JA807A (ZA104, L/N 41) to deliver on Jan. 11
JA806A (ZA117, L/N 40, first flight on Jan. 20th, deliver on Jan. 30
This information is regarded as preliminary as there can unforeseen issues to can derail any of these milestones. Also note that these dates are not the dates that ANA flies them to Japan but dates where contractual delivery is made and money has changed hands.
Thursday, December 15, 2011
Boeing to attempt 4 787 deliveries in December
In addition to JA805A (L/N31,ZA116) and JA807A (L/N41, ZA104); Boeing will also try to deliver JA804A (L/N9, ZA102) and JA808A (L/N42, ZA 105).
L/N 9 has already flown as it took part in the certification test program when it conducted F&R/ETOPs testing for the 787/Trent-1000 combination. Boeing should be able to deliver this airplane though it still needs to conduct pre-delivery test flights. Of the four airplanes that are mentioned above, only L/N 31 is flying customer and Boeing pre-delivery flights. It it anticipated that this airplane should be delivered within the next one week, before Christmas time.
The other three have yet to fly and are all scheduled to be delivered just before New Year'e Eve (2011 in case you were wondering). L/N 42 was to have flown on Dec. 13th and it is still not on the flightline as of yet. L/N 41 is supposed to fly on the 16th of December.
Additionally, it was revealed that Boeing has penciled in three 787 deliveries for next month. L/N 23 (JA822J, ZA177) will be the first 787 with GEnx-1B engines delivered to a customer. This airplane has just returned from San Antonio where it was undergoing change incorporation. It has received a new paint job (which has underwhelmed the aviation geek community) though I don't know if it has its customer interiors fitted as of yet. L/N 35 (VT-ANH, ZA236) for Air India is also due to be delivered in January. This airplane is supposed to start ETOPs/F&R testing in support of the certification test program for the GEnx powered 787s. According to Flightblogger, this airplane is to have it's first flight around the middle of December so far nothing yet. Lastly, L/N 40 (JA806A, ZA117) will also be delivered to ANA in January. This aircraft is still at EMC. Nothing is certain with these three airplanes and their delivery dates are dependent on getting the work done on them as well as finishing up ETOPS and F&R testing on the GEnx powerplant.
This is quite an ambitious schedule for the next two weeks for Boeing. They are still struggling with the amount of work that has to be done on the 24 or so 787s that are in Everett. Particularly vexing is the amount of work on the early build 787s. As I had mentioned before none these early build 787s are in EMC (yet) or in 40-24. They're all stacked up on the Everett flightline. Most of the deliveries are the late build models which don't require as much work. Even so, the amount of work is so daunting that Boeing is trying hard to get the late build 787s into the air and into the hands of customers. There is a rumor going around that Boeing is pulling people off the 747-8 airplanes that have to be prepared for delivery and putting them on 787. If so then 747 deliveries might fall as a consequence. Boeing has delivered 8 thus far and are planning to deliver 1-2 more 747s.
Time is running out if Boeing is to deliver even two 787s this month let alone 4.
Friday, December 24, 2010
787 Certification Flight can start as early as January 3rd
ZA004 made a successful return to test flight yesterday by flying a 1 hour and 35 minutes test flight around the Seattle/ Puget Sound region.
Here's the current flight test statistics that I've been keeping:
On Dec. 20th there was a line move and the 31st 787 (ZA117/LN31 for ANA) entered final assembly in Boeing's 40-26 final assembly building. LN 27 (ZA178 for Japan Airlines) went to the paint hangar. I have a fully updated spreadsheet below of the current status of the 787s around Everett:
Monday, December 6, 2010
Boeing initiates 3 week 787 production halt; production to resume on Dec. 23rd.
This news comes on top of Spirit Aerosystems announcing that they were temporarily halting production of the 787 forward fuselage sections and reassigning those workers to help with 737 overtime production. Spirit currently has 50 forward fuselage sections either delivered or in the production process in Wichita. It is probably unrelated to the current production halt as Boeing is telling it's suppliers to continue their production and delivery schedules. Flightblogger reported that the main fuselage section for ZA117 has not arrived into Everett leading me to believe that Boeing Charleston might be the source of the current production delay.
This is the 4th production halt this year as Boeing is still attempting to ramp up production of the 787. This only adds to the problems the program is facing in the midst of the power panel fire on ZA002 and the subsequent need to initiate re-design of hardware and software in the 787. It is still unknown when the 787 will return to test flight though I think it'll happen between the first and second week of January.
You can read Flightblogger's post:
Flightblogger: Breaking: Boeing halts 787 part deliveries for another three weeks
Tuesday, November 30, 2010
ZA002 to fly back to Boeing Field, Boeing still expects to issues new schedules in the next several weeks
Flightaware ZA002 track
Here's Boeing's press release:
ZA002 Returning to Seattle
In related news Boeing Commercial Airplane chief, James Albaugh said that Boeing still has more work to do in order to finalize plans for the necessary modifications and fix to the power distribution system and then develop a schedule based on that and probably other considerations in the program. Albaugh is saying that there will be a schedule slip which is expected but has not yet said how long that slip would be. His comments were to Reuters. You can read the article by clicking HERE.Boeing has readied ZA002, the 787 flight test airplane that experienced an electrical fire on Nov. 9, to be flown from Laredo, Texas, to Seattle. Maintenance technicians replaced the damaged P100 power distribution panel, repaired damage to interior composite structure and installed new insulation material.
The team in Laredo, Texas, has completed a series of ground test operations and
inspections to validate the repairs. The flight, which is expected to occur soon, will not include test operations.
Still all this is not sitting well with customers for the 787. ANA is demanding a new schedule as well as details about the problem that caused the fire and subsequent power problems. Qatar Airways has called the 787 a "failed" program though it seems that they're still holding on to their order for 30 787s. China Eastern Airlines is saying that they will cancel their order for 15 787s though Shanghai Airlines, which is owned by China Eastern, has not said if they too will cancel.
It is too early to tell if customers will stick with Boeing and the 787 until the revised schedule is out.
Still Boeing is still continuing with production with the 31st 787 to be loaded into position 1 today or tomorrow. This airplane, ZA117, is destined for ANA. ZA178 which is for Japan Airlines will be rolled out to the paint hangar.
Ground test continue to be performed on the 787 test flight fleet in lieu of flight tests as well. Boeing is also making progress in terms of getting the other 787s ready for flight tests and delivery. As had been reported earlier, a 787 destined for Japan Airlines received it's GEnx-1B engines this past weekend and one of the production 787 that will undertake flight/ground testing was rolled out to the flightline. I had reported that this airplane was ZA102 but it might be ZA101 which is to take part in ground tests though I'm working to try and confirm which aircraft is actually out on the flightline.
Flightblogger reported today that production airplanes will be flown to San Antonio, Texas where they will go through the change incorporation program prior to being delivered. Flightblogger is reporting that the Japan Airlines 787 (ZA177) will be the 3rd or 4th 787 to be delivered. It seems that now production airplanes are starting to get their powerplants in preparation for the flights to San Antonio though when these airplanes will be flown will be determined by the new schedule that Boeing should put out in the next several weeks.
Flightblogger: Repairs complete in Laredo, ZA002 to return home to Seattle
Lastly, I am still standing by my earlier prediction of a three month delay for 787 deliveries.
Sunday, November 14, 2010
ZA002 News - ZA001 and ZA005 to fly back to Boeing Field
On ZA002, Boeing has completed its inspection but not its investigation. They've collected all the data and have begun repairs to the aircraft. There was a some structural damage which Boeing says will be repaired using standard repair techniques that they have developed for the composites on the 787. The repair team will also replace the insulation and the failed power module.
Boeing has not yet established a timeline to complete the repairs or for when test flights will resume. They say they are getting closer to a root cause of the fire but have not yet shared this knowledge.
Boeing said the entire incident lasted only 90 seconds and the fire lasted 30 seconds. Boeing also said that the redundancies allowed the airplane to conclude the flight in a configuration that would have enabled it to fly to a diversion airport if the airplane was flying a typical revenue flight. The meaning of that statement is that the airplane systems worked as advertised (other than the failed power panel) and the safety systems and redundancies made sure that the airplane concluded the flight safely. This would have been the case if the airplane was over the middle of the Atlantic at 40,000 feet.
A local Seattle TV news station said that the pilots didn't declare an emergency until AFTER the 787 had landed in Laredo. It had been widely assumed that the emergency was declared while the airplane was on final approach into the airport.
King 5: Pilots Declared Fire Emergency after 787 landed
In light of the fire, the FAA has stopped certification activities except for ground tests. How long this suspension will last will depend on the nature of the incident and Boeing's ability to demonstrate that they have a fix and that it will not occur again.FAA Hits Brakes on 787 Certification
Guy Norris has a posting on today news:
Guy Norris: 787 will today - briefly
Here's Boeing's statement:
Two Boeing 787 Dreamliners to Return to Seattle; Laredo Investigation Continues
EVERETT, Wash., Nov. 16, 2010 /PRNewswire/ -- While the investigation into the incident onboard 787 Dreamliner ZA002 continues, Boeing has established a plan to fly two other aircraft, ZA001 and ZA005, back to Seattle from Rapid City, S.D., and Victorville, Calif. The U.S. Federal Aviation Administration has reviewed and approved the plans.
ZA001 was undergoing refueling in South Dakota when the incident on ZA002 occurred and the company decided to forgo additional flights. ZA005 was on remote deployment for testing in California.
The flights follow a series of inspections on the airplanes' aft electronics bays. No testing will be performed on the flights.
The team investigating the incident in Laredo has developed a detailed understanding of the ZA002 incident, though more work remains to complete the investigation. In addition to the information already released about the incident, data show that:
The total duration of the incident was less than 90 seconds.
The fire lasted less than 30 seconds.
The airplane concluded the event in a configuration that could have been sustained for the time required to return to an airport suitable for landing from any point in a typical 787 mission profile.
The team in Texas has completed inspection of ZA002 and has begun to
prepare to install a new power panel and new insulation material. The team also is repairing minor structural damage that occurred during the event. This damage will be addressed with standard repair techniques in the airplane structural repair manual. The team is currently evaluating the timeline for completion of the repair work.
The incident on ZA002 demonstrated many aspects of the safety and redundancy in the 787 design, which ensure that if events such as these occur, the airplane can continue safe flight and landing.
No decision has been reached on when flight testing of the 787 will resume. Before
that decision can be made, we must complete the investigation and assess whether any design changes are necessary. Until that time, Boeing cannot comment on the potential impact of this incident on the overall program schedule.
787 production continues
Meanwhile there will be line move in the 787 final assembly building today with the 26th 787 (ZA231) for Air India moving to the paint hangar at Everett.
The first 787 for Air India (ZA230) made it's first appearance being towed to the Boeing flightline at Everett. Flightblogger posted photos of the aircraft being towed to the flightline from the paint hangar. The line move makes room for the 30th 787 (ZA234) to start final assembly. The next 787 to enter final assembly after that will be ZA117 for ANA on Dec. 1st...two weeks from now.
Sunday, November 7, 2010
787 and 747-8I news - November 7, 2010
The August 2nd failure of the Trent 1000 engine on a test stand in Derby was a major factor of the latest 787 delay no matter what anyone else would tell you. Last weeks incident on QF32 with the Trent 900 engine highlighted the potential human cost of an uncontained engine failure. Part of the engine had damaged the wing of the A380 and if the pieces had penetrated the wing fuel tank, it would have most certainly lead to the loss of the aircraft and all on board. The potential lost of QF32 would have been the third worst air disaster ever given the number of souls aboard the airplane.
This incident also underscored Boeing's decision to delay the 787 delivery to ANA (to be equipped with the Trent 1000) to mid February. Now Rolls says they have a hardware and software fix but in light of what happened last week, Rolls Royce has a lot of explaining and soul searching to do. They have to convince the airline industry and the airframe manufacturers that their products are safe. Recent events have thrown much light on their products. Rolls Royce is hurting and I do direct you this this article HERE to get a real good read out on the potential problems that the uncontained failures of the Trent 1000 and Trent 900 engines have for Rolls. Finally, Boeing is not going to be helped by Pratt and Whitney's lawsuit against Rolls Royce for patent infringements. The lawsuits aims to prevent Rolls Royce from delivering any Trent 1000 engines to Boeing and the 787 program. If this goes through Boeing and its customers who ordered the Trent's will be in a very tough spot.
Boeing still has issues with the 787 that they have to grapple with out the Rolls Royce issue and that issue is the travelled work and all the rework that the assembled 787s have to have before they are delivered to customers. Boeing is still mum on the number of 787s that they will deliver next year but there has been press reports that there would be 10 month delay to some deliveries, notably to Air India and Korean Air. Boeing has come out forcefully in the light of those press reports to say that their isn't an further delay beyond those that they have already announced and that the media that originated the newest story was using information that Boeing had released two months ago. The verdict: Boeing is still sticking with the mid 1st quarter 2011 for first delivery but beyond that Boeing has not made any announcement of the pace of deliveries after the first airplane is in ANA's hands.
Air India has come out and said that they are expecting their first 787 in June 2011 which is in line with past reports. Still we will still have to see how the pace of rework goes after the completion of the flight test program in order to better gauge the delivery schedule of the 787s.
Meanwhile, Flightblogger reported the resumption of 787 part deliveries into Everett with the arrival of the wing set for the 31st 787 (ZA117 for ANA). There was a line move late last week where LN 25 (ZA230 for Air India) was moved to the paint hangar allowing ZA233 (also for Air India) to be loaded into the final body join spot.
Flightblogger: Boeing restarts 787 deliveries with arrival of wings for Airplane 31
Flight test activities continued this past weekend with the Boeing test flight fleet logging about 60 flight test hours over the last three days (Nov. 5 - Nov. 7). Some of the milestones include the 787/Trent 1000 fleet surpassing 2,000 flight test hours, the 6 test flight airplanes surpassing 75% of the required test flight hours (3,100 total), ZA001 surpassing 700 flight test hours flown, the test flight fleet surpassing 2,300 flight test hours, the 787/GE test flight fleet surpassing 50% of the required test flight hours, and the 750th test flight of a 787.
Also ZA006 undertook a marketing mission to Amsterdam and Paris in an effort to sell AF/KLM the 787. During this time, ZA006 was parked next to an Air France A380 overnight at Charles De Gaulle in Paris which would have made for a great photo.
747-8I, RC001 makes progress.
Boeing's other major passenger aircraft that's in development also is making progress as the first 747-8I achieved power on for the first time. Power on allows some testing of the aircraft's systems in the assembly hangar while assembly is on going and is an important milestone. Boeing plans a four month test flight program and first delivery in about a year from now. The reason for the short flight test program is that much of the testing has already or will be completed by the 747-8F.
Below is Boeing Press Release as well as video of the power on of RC001:
Boeing Achieves Power On for New 747-8 IntercontinentalBoeing Video
EVERETT, Wash., Nov. 5, 2010 /PRNewswire/ -- Boeing (NYSE: BA) has completed the power on sequence for the new 747-8 Intercontinental. This milestone enables the program to begin functional tests on the airplane.
"This is a critical step in the assembly process for the new 747-8 Intercontinental," said Elizabeth Lund, 747 deputy program manager, Boeing Commercial Airplanes. "The airplane's systems are now live. This milestone is a reflection of the focus and hard work of our engineers, mechanics and suppliers."
Power on is a complex series of tasks that methodically energize and activate the airplane's systems. In this critical stage of the assembly process, the electrical, hydraulic and pneumatic systems are brought on line.
Mechanics connected the 747-8 to an external power cart to energize the flight-deck display and maintenance systems. The electricity coursing through the airplane's 133 miles (214 km) of wire will be as high as 105 kilovoltampere (kVa).
The program also activated the airplane's hydraulic and pneumatic systems. Pressurized to 3,000 pounds per square inch (psi), the hydraulics power the flight control surfaces, landing gear, brakes and steering systems. The 160 psi applied to the pneumatic system enables the airplane to operate the environmental control systems and the leading-edge flaps.
"We are very methodical in ensuring the integrity of the airplane's systems," said Todd Zarfos, vice president of 747 engineering, Boeing Commercial Airplanes. "This accomplishment is a key milestone in validating the design, installation and functionality of the electrical, hydraulic and pneumatic systems."
A video that gives you an inside look at the power on sequence is available at http://bit.ly/dlXgym.
The program is expected to complete assembly of the 747-8 Intercontinental in the first quarter of 2011. The airplane is scheduled to enter service in late 2011 following the flight test program.
The 747-8, which includes the 747-8 Intercontinental and the 747-8 Freighter, was launched in November 2005. Boeing has 109 orders for the 747-8 -- 33 for the 747-8 Intercontinental and 76 for the 747-8 Freighter. The first 747-8 Intercontinental is scheduled to deliver in late 2011.
The new 747-8 Intercontinental offers the lowest operating costs and best economics of any large passenger airplane, while providing enhanced environmental performance. The 747-8 provides new revenue opportunities that allow airlines to maximize profits. Eighteen feet longer than the 747-400, the 747-8 has 51 additional seats to accommodate 467 passengers in a typical three-class configuration, and it also offers 26 percent more cargo volume.
Monday, January 18, 2010
Boeing Complete 787 Inital Airworthiness Testing
- The 787 is safe to fly with more than just the pilot and co-pilot aboard. Now Boeing's flight test engineers can also fly aboard to monitor tests
- The 787 flight envelope can now be expanded beyond the what has already been tested thus far.
Here's Boeing's Press Release:
News Release Issued: January 15, 2010 5:28 PM ESTAs always, the other follows of the 787 program weighed in with their postings and here is a rundown of this weekends commentary.
Boeing 787 Dreamliner Achieves Initial Airworthiness Milestone
EVERETT, Wash., Jan. 15 /PRNewswire-FirstCall/ -- Boeing (NYSE: BA) has completed initial airworthiness testing on the 787 Dreamliner. This milestone will enable more crew members to take part in flights and will allow more airplanes to join the flight test program.
"This is an important step forward," said Scott Fancher, vice president and general manager of the 787 program, Boeing Commercial Airplanes. "We are very pleased with the results we have achieved so far. The airplane has been performing as we expected."
Since the first flight in mid-December, the program has conducted 15 flights, achieving several key accomplishments. Pilots have taken the airplane to an altitude of 30,000 feet (9,144 meters) and a speed of Mach 0.65. Nearly 60 hours of flying have been completed. Initial stall tests and other dynamic maneuvers have been run, as well as an extensive check-out of the airplane's systems. Six different pilots have been behind the controls of the 787.
In the weeks ahead, the team will continue to expand the flight envelope at which the 787 will operate to reach an altitude of more than 40,000 feet (12,192 meters) and a speed of Mach 0.85. Subsequent testing will push the airplane beyond expected operational conditions.
"The pilots have told me the results we are seeing in flight match their expectations and the simulations we've run. That's a real tribute to Boeing's expertise and the international team that helped develop and build the airplane," said Fancher.
Flight testing will continue in the months ahead. First delivery is planned for the fourth quarter of this year.
Flightblogger posted a great update reviewing the previous months' flight test progress as well as reviewing the status of the aircraft that have been built thus far. Here's a synopsis of the aircraft status:
ZA001/LN1 : At Boeing Field undergoing flight tests
ZA002/LN2: At Paine Field for aqueous tank wash
ZA003/LN3: At Paine Field undergoing preparations for its first flight in February
ZA004/LN4: At Paine Field fuel dock undergoing preparations for its first flight in February
ZA005/LN5: At Paine Field ATS Hangar undergoing side of body modifications
ZA006/LN6: At Paine Field ATS Hangar undergoing side of body modifications
ZA100/LN7: At Paine Field flightline awaiting side of body modifications
ZA101/LN8: At Paine Field flightline awaiting side of body modifications
ZA102/LN9: At Paine Field inside temporary hangar undergoing side of body modifications
ZA103/LN10: At Paine Field undergoing painting
ZA104/LN11: At Paine Field building 40-24
ZA105/LN12: At Paine Field undergoing final assembly
ZA115/LN13: At Paine Field undergoing final assembly
ZA116/LN14: At Paine Field undergoing final assembly
ZA117/LN15: At Paine Field undergoing final assembly
Parts for airplane 16 are starting to arrive into Everett. This airplane is the first to be assembled that will not require the side of body modifications. Lastly, Flightblogger reports that when parts for airplane 17 arrives it'll be for for Royal Air Maroc powered by GEnx engines.
787 Flight Test Update: Month One
Guy Norris had a nice synopsis of the 787 program on his blog as well. In it he said that ZA001 is going to be taking a breather while it undergoes checks. The airplane has not flown since January 14th.
Guy Norris: 787 completes initial airworthiness testing
Finally, Innovation Analysis Group, had a great Podcast featuring Jon Ostrower (Flightblogger) and Guy Norris.
Sunday, January 10, 2010
787 Update - January 10, 2010
ZA003 should show up very soon on the Everett ramp as well very soon to start it's preparations for first flight.
Both ZA003 and ZA004 are projected to have their first flights in the first week of February.
Additionally, Matt Cawby reported on his blog that the fatigue test air frame is very close to finishing its side of body modifications and should be moved to the fatigue test area around January 30th to start 3 years of fatigue testing. It will be moved out of the temporary hangar that is on the Boeing flight line.
Matt Cawby's January 9, 2010 Blog Update
Flightblogger got a great article up on the production challenges that the 787 still faces now that the aircraft has entered test flights. Thus far Boeing has completely assembled 1 complete 787s (LN 1 through LN 11) plus two test air frames (ZY997 and ZY998). Currently there are 4 aircraft undergoing final assembly (LN 12 through LN 15) and parts of LN 16 are just starting to arrive in Everett. Flightblogger is reporting that Boeing planes to start increasing production on the 787 round mid February.
Flightblogger: Dreamliner Production Challenges Lie Ahead
Finally through today, January 10, 2010, the 787 test fleet has accumulated over 45 and half hours test flight hours. Also today, Za001 flew the longest 787 test flight thus far at 5 hours and 48 minutes. You can track the 787 flight test hours by going to this spreadsheet here.
Friday, January 1, 2010
Where are the 787s in the New Year?
Future of Flight PhotoNow that the 787 flight test program is well underway, let's update where the fleet is.
LN1 (ZA001) Boeing Flight Test Center, Boeing Field - in flight test
LN2 (ZA002) Boeing Flight Test Center, Boeing Field - in flight test
LN 3 (ZA003) Boeing Paint Hangar, Paine Field (completed Side of Body modifications undergoing fuel tank aqueous wash and painting)
LN 4 (ZA004) Building 40-24, Paine Field (Completed Side of Body modifications, undergoing reassembly after fuel tank aqueous wash and painting)
LN 5 (ZA005) In ATS Hangar
LN 6 (ZA006) In ATS Hangar
LN 7 (ZA100) Boeing Everett Flightline awaiting side of body modification
LN 8 (ZA101) Boeing Everett Flightline awaiting side of body modification
LN 9 (ZA102) Boeing Everett Flightline awaiting side of body modification
LN 10 (ZA103) Building 40-24, Paine Field awaiting side of body modification
LN 11 (ZA104) Building 40-26, position 4 undergoing final assembly
LN 12 (ZA105) Building 40-26, position 3 undergoing final assembly
LN 13 (ZA115) Building 40-26, position 2 undergoing final assembly
LN 14 (ZA116) Building 40-26, position 1 undergoing final assembly
LN 15 (ZA117) Building 40-26, position 0 parts arriving in preparation for Final Assembly