Boeing has temporarily stopped final assembly activities on 3 787 in order that 3 other 787s that have completed the side of body modifications are finished.
In doing so, Boeing has towed ZA151 (LN19) to a spot on the Boeing flightline and took ZA175 (LN 20) and ZA 176 (LN 21) went into temporary storage at the ATS Hangar. In their place Boeing put ZA100 (LN 7) in building 40-26 position 4, ZA101 (LN 8) in position 3 and ZA102 (LN 9) in position 2. These planes all have undergone the side of body modifications. It is anticipated that these airplanes will be in 40-26 for a little bit more than a month. When Boeing is ready to resume production ZA100 will be moved to 40-24 (767 final assembly line) and the line will pulsed so that ZA177 (LN 23) can start final assembly. The two of the three booted airplanes will return to the assembly hall once the reassembly activities are completed on the three early build production airplanes. ZA151 will go to the paint hangar soon and ZA175 and ZA176 will return to 40-26 once the reassembly activities are completed.
In other news, ZA005 may finally light the GEnx-1B engines today. I'll post if that happens.
Showing posts with label LN 21. Show all posts
Showing posts with label LN 21. Show all posts
Monday, May 10, 2010
Wednesday, March 31, 2010
787 review and look ahead
Now that the first quarter of 2010 has come to an end, it seems like a good time for a brief review and a look ahead.
Thus far the 787 flight test fleet has accumulated over 406 test flight hours (through March 31st) spread over 134 flight. ZA001 has conducted most of the test flight as expected with ZA002 conducting the second most flights.
There is some concern amongst many followers of this program (including articles in the Wall Street Journal) that the 787 hasn't been flown enough to achieve the needed flight test hours for certification. Boeing has said that the test flight program will entail 3,100 flight hours spread across the 6 test airplanes. In order for Boeing to have the necessary hours by mid November which is 32 weeks from now (I picked mid-November as it will allow Boeing enough time to get the production 787 ready for customer delivery by Dec. 31, 2010...another 6 weeks) they would need to fly the test fleet at a clip of 82 hours per week starting now.
James Albaugh has stated that the 787 test fleet would be flying around 90 hours per week starting around the middle of this year. However, if Boeing is to meet it's 787 delivery target that it has set for itself, then it would need to start flying longer 787 sorties starting now. Currently, Boeing is averaging a little over 3 hours per flight through the 134 flights that have been conducted thus far. Boeing does plan on flying longer flights but that probably won't occur until the FAA has issued the Type Inspection Authorization that is needed to formally kick off the certification process. That was supposed to have happened by today as of the time I'm writing this post it has not occurred.
Flight Test Look Ahead
In the meanwhile, ZA001 continues to fly test flights. ZA002 is in the midst of upgrading it flight software to the Wedge 5.5 version that ZA004 had recently tested on the ground and in the air. This is the service-ready version of the 787 flight software. It is anticipated that ZA002 should be back in the air by the end of next week (around April 9th). Both ZA003 and ZA004 should both be flying again by Saturday, April 3rd. ZA005 is on the Boeing flightline, preparing for it's first flight and should be flying around May 8th. This will be the first flight of the GEnx-1B on the 787. The last flight test aircraft (also equipped with the GEnx-1B), ZA006, should be in the air by June 4th and is currently in building 40-24.
Production
787 production continues apace with an important milestone taking place yesterday. LN 20 (ZA175), a 787 for Japan Airlines, started final assembly. This is the first weight optimized 787 to enter into final assembly and is introducing a major block point change with weight savings incorporated into the aircraft.
Boeing is slowly ramping up 787 production and the next aircraft LN 21 (ZA176) will enter final assembly around April 12th thus ZA 175 would be in position 1 for about 2 weeks before pulsing to the next assembly position. The dramatic reduction of traveled work (two words that hasn't been mentioned in some time) certainly has helped as well as the learning curve when it comes to assembling the 787s. Now the concern is managing the change incorporation process of the existing production 787s though Boeing does have a plan for that.
Thus far the 787 flight test fleet has accumulated over 406 test flight hours (through March 31st) spread over 134 flight. ZA001 has conducted most of the test flight as expected with ZA002 conducting the second most flights.
There is some concern amongst many followers of this program (including articles in the Wall Street Journal) that the 787 hasn't been flown enough to achieve the needed flight test hours for certification. Boeing has said that the test flight program will entail 3,100 flight hours spread across the 6 test airplanes. In order for Boeing to have the necessary hours by mid November which is 32 weeks from now (I picked mid-November as it will allow Boeing enough time to get the production 787 ready for customer delivery by Dec. 31, 2010...another 6 weeks) they would need to fly the test fleet at a clip of 82 hours per week starting now.
James Albaugh has stated that the 787 test fleet would be flying around 90 hours per week starting around the middle of this year. However, if Boeing is to meet it's 787 delivery target that it has set for itself, then it would need to start flying longer 787 sorties starting now. Currently, Boeing is averaging a little over 3 hours per flight through the 134 flights that have been conducted thus far. Boeing does plan on flying longer flights but that probably won't occur until the FAA has issued the Type Inspection Authorization that is needed to formally kick off the certification process. That was supposed to have happened by today as of the time I'm writing this post it has not occurred.
Flight Test Look Ahead
In the meanwhile, ZA001 continues to fly test flights. ZA002 is in the midst of upgrading it flight software to the Wedge 5.5 version that ZA004 had recently tested on the ground and in the air. This is the service-ready version of the 787 flight software. It is anticipated that ZA002 should be back in the air by the end of next week (around April 9th). Both ZA003 and ZA004 should both be flying again by Saturday, April 3rd. ZA005 is on the Boeing flightline, preparing for it's first flight and should be flying around May 8th. This will be the first flight of the GEnx-1B on the 787. The last flight test aircraft (also equipped with the GEnx-1B), ZA006, should be in the air by June 4th and is currently in building 40-24.
Production
787 production continues apace with an important milestone taking place yesterday. LN 20 (ZA175), a 787 for Japan Airlines, started final assembly. This is the first weight optimized 787 to enter into final assembly and is introducing a major block point change with weight savings incorporated into the aircraft.
Boeing is slowly ramping up 787 production and the next aircraft LN 21 (ZA176) will enter final assembly around April 12th thus ZA 175 would be in position 1 for about 2 weeks before pulsing to the next assembly position. The dramatic reduction of traveled work (two words that hasn't been mentioned in some time) certainly has helped as well as the learning curve when it comes to assembling the 787s. Now the concern is managing the change incorporation process of the existing production 787s though Boeing does have a plan for that.