Boeing rolled out the first 787 for American Airlines on Oct. 6th. The aircraft was originally supposed to be delivered in November is now slated for delivery on December. It is on the 40-51 Ramp finishing up assembly activities followed by painting.
First 787 for American Airlines, Photo by MOONM |
ZA006 at the Charleston Delivery Center, Photo by reader |
February, 2014 - 114.8 days
March, 2014 - 117.6 days
April, 2014 - 126.4 days
May, 2014 - 112.4 days
June, 2014 - 206.5 days
July, 2014 - 141.4 days
August, 2014 - 117.7 days
September, 2014 - 127.5 days
These averages need to be put into proper context. They include the 787-9 (from June on) These early 787-9s had to go through change incorporation and required more build time compared to the 787-8 thus the number of days fro the start of final assembly to delivery were higher for these airplanes and distorted the results. Here are the average number of days it took to build the 787-8:
February, 2014 - 114.8 days
March, 2014 - 117.6 days
April, 2014 - 126.4 days
May, 2014 - 112.4 days
June, 2014 - 125.6 days
July, 2014 - 121.1 days
August, 2014 - 117.7 days
September, 2014 - 118.4 days
As you can observe the average time it takes to build the 787-8 (this includes both Charleston and Everett) is fairly stable. As Boeing get more familiar with building the 787-9 and the need for change incorporation goes away as well as the need for extensive time to finish traveled work, we should see build times for both versions of the 787 go down to below 100 days.
There is still no known timetable when the stabilization of the production system will occur and it appears that Boeing is continuing to struggle with traveled work which has been the bane of the 787 program currently. There has been flashes of hope for a 90 day rate or lower (start of final assembly to contractual delivery). For example Boeing delivered a 78 to Tui Travel in 84 days from Everett and Charleston delivered a 78 in 86 day to Kenya Airways. 2015 should bring much required and welcomed improvements to the 787 production system.
787 Full Production Table
Mexican air force - Somewhat similar tail livery to the Kenya colors directly behind it.
ReplyDelete120 days to assemble a 787. Wow, that seems like a very, very long time, especially for a program nearing its' 200th delivery. Especially since many of the major components arrive stuffed and pre-assembled.
ReplyDeleteDoes anyone know how long does it take to assemble a 777?
A 737?
Is Branson flying in to take delivery of their first 787-9?
ReplyDeleteAs he is such a showman, I would expect so. Does anyone know?
The 110 to 120 days include not just Gibsonassembly but all ground and flightby eating, painting and any time needed by the customernot pprepare for delivery.
ReplyDelete83 days for a 77W. 737's are cranked out at 1.4/day
ReplyDelete737's come out @ 1.4 per day yet how long is required for assembly?
ReplyDelete83 days for 777 is the appropriate comparison, thank you. This is where the 787 should be getting close to, after approx 200 deliveries. Taking another 30 days is a failure in my book, as this is no longer a new program. Also, one would think efficiencies learned from other programs would be built into the 787 from the start and therefore assembly should be FASTER than on the 777.
Oh well, until McNerney is gone, Boeing will never excel as it did when Mulally ran commercial.
LN211 for Azerbaijan Airlines painted, on the flightline:
ReplyDeletehttps://www.flickr.com/photos/moonm/15312993038/
@1coolguy1
ReplyDeleteI agree. It's sad that whatever lead Boeing got with the rollout of the 787, they seem more than willing to relinquish to Airbus due to continual production issues. With any other business, any business without such powerful backing, it wouldn't be allowed to continue. Boeing can do better.
@1coolguy1
ReplyDeleteMore misguided fan worship I have never seen -- is Mullaly your uncle? The system put in place to design, engineer and build the 787 was done by Mullaly. It was a train wreck barreling down the tracks when McNerney took over -- not much he could do to change it overnight -- a lot of inertia there. Things are getting better.
Two thoughts: 1) While the direct build time for the -8 is down and ~~stable at ~~112-126 days, it is still impressive! Building one of those things on a good line and without a lot of re-work from bug tubes to customer delivery in ~four months is a major accomplishment for Boeing! I well understand that the actual number of person-hours required is a tightly held number, I wonder...
ReplyDelete2) selling ZA006 to the Mexican Air Force was a good move for both. The test frames turned out to be heavier than expected, a detriment for a busy carrier, but regardless of application, the Mex-AF won't fly it that many hours. Boeing unloaded an otherwise unwanted air frame and the Mex-AF likely got a Very Good Deal. Win-Win.
Two thoughts: 1) While the direct build time for the -8 is down and ~~stable at ~~112-126 days, it is still impressive! Building one of those things on a good line and without a lot of re-work from bug tubes to customer delivery in ~four months is a major accomplishment for Boeing! I well understand that the actual number of person-hours required is a tightly held number, I wonder...
ReplyDelete2) selling ZA006 to the Mexican Air Force was a good move for both. The test frames turned out to be heavier than expected, a detriment for a busy carrier, but regardless of application, the Mex-AF won't fly it that many hours. Boeing unloaded an otherwise unwanted air frame and the Mex-AF likely got a Very Good Deal. Win-Win.
Randy Austin - I wish he was!
ReplyDeleteApparently you have not been paying attention to:
Mulally turned around Ford, which is now a profitable company. Ford is the ONLY US car company that did not accept federal funds, unlike GM and Chrysler. This is regarded by all as one of the most remarkable large corporate turn-arounds in US history.
he is regarded as the father of the 777, which was delivered on the exact date promised to UAL and the program was on budget.
McNerney's "accomplishments"
737 Max: Late to market
747-8: 2+ years late
787: 3+ years late
787: Development costs $28+ BILLION over budget.
K-46A: Over budget and late
It is impossible to calculate how many billions these programs together have cost Boeing, but I understand it is north of $50 billion.
ALL of this is under McNerney.
Let's simply agree we have a different idea of what "success" means.
BTW: Mulally is the LARGEST Ford non-institutional shareholder, as he was rewarded by that board for his exceptional performance.
McNerney is a duffer in comparison. Is he YOUR uncle?
Uresh - Have you or anyone seen this article in Av Week today? It's about AI PARTING OUT??? a 787! What's going on with this?
ReplyDeletehttp://aviationweek.com/blog/whats-air-india-doing-boeing-787
Yes old news
ReplyDelete"787: Development costs $28+ BILLION over budget."
ReplyDeleteWrong.
Half of the figures are for developing the first 40 frames which are LN4 through LN43. Boeing would only lose anywhere from $150 to $200 million for those frames which is about $7 billion instead of $16.3 billion.
So flash forward to 2014, the entire program cost has been somewhere around $70 billion if we're talking about frames up to LN250. Now Boeing is hoping to sell up to 3000 of the 787's which means that the program cost could be somewhere around $600-$700 billion total. Profit from the 787 program could be somewhere around $150 billion to $350 billion. They expect to start turning a profit at LN400-LN500 or so.
I am wondering what LN# is the quickest from roll out to delivery? It seems to be taking 6-8 weeks after roll out to delivery whereas the 737's rolling out seem to be delivered in about two weeks.
ReplyDeleteTo add to Kaitian's points, also remember that the 787 program and its costs currently encompasses 3 separate aircraft -8, -9, and -10 addressing 3 different markets and all models seem to be very successful in the market.
ReplyDeleteCompare this to other programs such as a350 program which currently only have 2 viable aircraft designs and has reached $15B in development costs, with a significant redesign planned around line # 20 or so.
Furthermore, at least $4-5B of the 787 development costs was spent developing the Charleston assembly line and new paint facility, primary Everett line and a surge line in Everett. These facilities will be in use for a very long time (except for the surge line, which already has served its purpose by dramatically reducing the delays for current deliveries relative to the contracted delivery date). Perhaps Uresh might be interested in analyzing just how much this delivery time relative to contractual date has improved with the surge line.
The 787 technologies are already being brought over to other aircraft -- e.g., the new cockpit displays in 777x are right out of the 787. Wing design is similar as well, albeit scaled larger. Same for windows and interior .
And to 1coolguy1's point, the 787 development costs were significantly shared with its suppliers, so despite the cost and schedule overruns, Boeing did not shoulder these alone as it was shared with many suppliers too. So that's why you don't see a gaping $28B hole in the financial sheets of Boeing among other accounting reasons.
Having flown the 787-8 on 8 flights now (and most of its competition except a350), I love the 787 and happily pay more to fly it, and believe it will be as revolutionary to the airline world as the the 747 was when it was introduced.
Hi Uresh!
ReplyDeleteHave you ever heard of Air Austral may order 1 or 2 787-8, probably some early produced?
Article here (sorry in french):
http://www.clicanoo.re/440528-air-austral-negocie-avec-airbus-et-boeing-pour-l-achat-d-un-avion.html
Nicolas
First I heard of it. Frankly, I'm not sure if they're in strong enough financial condition to buy a coffee maker let alone a new fleet of aircraft.
ReplyDeleteIt would be interesting to monitor progress in the engine competition, maybe as 2 additional columns in the "Current 787 Operators" table. With 197 aircraft delivered, I count 72 shipsets for RR and 125 for GE.
ReplyDeleteInteresting to see that Charleston only has one built plane to fly whereas Everitt has fourteen. I realize that Everitt builds at a greater rate with two lines but the difference is striking I think
ReplyDeleteFirst 787-9 should be registered as G-ZBKA msn 38616 i think
ReplyDeleteagincourt
ReplyDeleteWhat are you talking about? Charleston has almost half the amount as Everett does. Charleston is producing at 3 per month which is supposed to go to 7 per month by 2020. All while Everett is going to reducing and eventually eliminating the surge line.
I'm not even sure how you arrived at 14 vs 1?
Kaitian - I just used the tables. Today the figures are Everitt 14 and Charleston 2. Sorry to disappoint you.
ReplyDeleteDo you know of any Swiss airline built 787-800s. I just saw a photo of a 787-800 that is Painted in Swiss and its not a rendering of a future plane...
ReplyDeleteSwiss is not a customer for the 787. Said picture is photoshopped.
ReplyDeleteThat's a dang good job of the photo then. Cause the car lights even show up and are awesome in the photo lol and were talking about the view of the plane on the copilots side correct??
ReplyDeleteUreshs, LN11 is on the flightline now, LN22 inside the EMC, LN246 outside, as well LN139 (this one probably temporarly).
ReplyDeletehttp://www.skyscrapercity.com/showpost.php?p=118441604&postcount=4282
Yes I know.
ReplyDeleteYes I know.
ReplyDeleteI forget to ask. Do you know line numbers of LOT Polish Airlines' last two 788s?
ReplyDeleteThe spreadsheets have all the latest information.
ReplyDeleteHey there,
ReplyDeleteI ran across the registrations planned for the KLM 787-9's, maybe they could be included in the spreadsheet ?
You can find them at PH-BH* :
http://www.hdekker.info/registermap/MB.htm
"agincourt said..."
ReplyDeleteObviously not. Which LN are you referring to?
List them. What criteria are you using?